ADMINISTRATIVE CHANGE ORDER 1 - AIRPARK LIGHT BEACONAdministrative Change Order 1
PROJECT:
Airpark Light Beacon
CONTRACTOR: Bandes Construction
1368 Spalding Rd.Stc. C
Dunedin, FL 34698-5039
DATE: March 9th, 2026.
PROJECT NUMBER: . 24.0013 -AP;
PO REFERENCE:. 26000357
COUNCIL AWARD: N/A
DATE OF CONTRACT: Deceinber,17th, 2025
CODE: 3027302-565100-02508
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
Increases Sltework line item for the Lift Station- See attached.
STATEMENT OF CONTRACT AMOUNT ACCEPTED. BY: Bandes Construction
ORIGINAL CONTRACT AMOUNT
Administrative Change Order -1 City Manager
NEW CONTRACT AMOUNT
APPROVED A t' FORM:
$ 49,448.70 By:, -1w-A
5 4,45E00, Tony .Pattakos: Contractor
S 53,906.70
Date: 4110/2026
Sr. Assistant City Attorney
CITY OF CLEARWATER, in
PINELL+]S, OU NT16 FLORIDA
Jennifer Poi
Administrative Change Order 1: Airpark Light Beacon
ITEM DESCRIPTION
Increase:
City Manager
Witness:
Witness:
ruktrAl
RECOMMENDED BY:i
City, of Clearwater°
Al ? 4/10/2026
Nate Jozefiki (f V Project Manager
7— Gfif/l�t/
Tara iGK vett, PE, City Engineer
UNIT _ELY UNIT COST NOTAL COST
Relocate existing fuel service contactor, provide new LS I $ 4,458.00 $ 4,458.00
enclosure, bypass feed in old enclosure, install fused
disconnect switch for Beacon Light, install new start
button at the service panels
Total Increase t9 PO: $ 4,45E00
Total Net Increase:, :,S _ __ .. _ 4,458.00_