PARKING LOT 36 RECONSTRUCTION - 25-0003-EN - ADMINISTRATIVE CHANGE ORDER #1Adm irstrativp Change Order 1
PROJECT:
Parking Lot 36 Reconstruction
CONTRACTOR:
Keystone Excavators, Inc.
371 Scarlet Blvd
Oldsmar, Fl 34677
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
January 23, 2025
25 -0003 -EN
25000387
December 19, 2024
December 19, 2024
3357335-546300-D2402
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
to increase for a potable waterline repair - see attachment.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - City Manager
NEW CONTRACT AMOUNT
APPROVED AS
Jerrod Simpson,
ATTEST:
0 FORM:
$ 765,424.75
$ 76,424.75
$ 841,849.50
Sr. Assistant City Attorney
ACCEPTED BY:
By:
Jeff
Kcystone Eya�1nc.
r x e? Alesigriut
)".30,‘O
1,111111,
Date: tip
Witnesses:
Rosemarie Call,
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
City Manager
Recommended By:
City of Clearwater
Annabella Hullen, PE, Project Manager
2ratrdfrPIA/11
City Engineer
" Page 2 of 2
Administrative Change Order I: Parking Lot 36 Reconstuction
ITEM DESCRIPTION
Decreases:
16 Contingency
24 Material Credit (6" Line for 4" Line Ite
Increases:
3
Additions:
15
17
18
19
20
21
22
23
Mobilization
Traffic Control
Disconnect & Plug 6" or 8" Pipe
6" PVC Pipe, C-900 DR 18
6" PVC Restrained Joint Pipe and Fittit
Reverse Deadman for 6" Pipe
6" x 6" Tapping Sleeve Valve & Box
2" Service Connection (short side)
I" Service Connection (short side)
4" Line Stop
UNIT QTY UNIT COST
LS 0.464
LS 1
LS 0.02
LS 0.02
69,550.00
Si 1
Total (Decreases):
400,000.00
165,000.00
Total Increases:
EA 4 750.00
LF 480 67.00
LF 80 265.00
EA 2 3,250.00
EA 2 8,000.00
EA 1 3,750.00
EA 1 2.375.00
EA 2 9,405.00
Total Additions:
TOTAL COST
(32.275 4 )
(6.394 SO)
(38,670.25)
8,000.00
3,300.00
11,300.00
3,000.00
32,160.00
21,200.00
6,500.00
16,000.00
3,750.00
2,375.00
18,810.00
103,795.00
Total Net ( Dee reases►,'Increases/Additions: 76,424.75