2021 SIDEWALKS PROJECT - 20-0026-EN - ADMINISTRATIVE CHANGE ORDER #4Administrative Change Order 4
PROJECT:
2021 Sidewalks
CONTRACTOR:
Central Florida Contractors Inc
PO Box 3987
Seminole, FI 33775
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
June 1, 2024
20 -0026 -EN
21000493
January 21, 2021
March 25, 2021
CODE: ENRD 180004-CONS-CNSTRC
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
increasing 6" Thick Concrete Sidewalk for Year 3 only -see attachment.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Change Order 1 City Council 5/5/2022
Change Order 3 City Council 6/15/2023
Admin Change Order 4 City Manager
NEW CONTRACT AMOUNT
APPRO i AS TO FORM:
$ 750,000.00
$ 750,000.00
$ 500,000.00
$ 27,672.50
$ 2,027,672.50
Jerrod Si !;' on, Sr. Assistant City Atto
ATTEST.
Lui-uvutkr.12, aat
Rosemarie Call,
Date: /L,(L 41
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
er Pffirrier,
ACCEPTED BY:
Central Florida Contractors Ine
? : 4=
' 1, «SEAL >> C.)
Prtifclea`t'
By:
George Gomes,
Date:
Witnesses:
CIAAAPV 4 )111,--m
City Manager
Administrative Change Order 1: Fire Station 46
are -10- ( rle5
Recommended By:
City of Clearwater
Kyle aughan, Project Manager
Tara Kivett, PE,
City Engineer
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Increase
4.3b 6" Thick Concrete Sidewalk
(3000psi w/fiber mesh &
wwf)
SF
3689.6667 $
7.50 $ 27,672.50
Total Increase: $ 27,672.50