CLIFF STEPHENS PARK RECREATIONAL PIER - RFQ 40-20 - PROPOSALCERTUS
PO Box 116
Bristol, Honda 32321
Tampa (813) 443-4990
Bristol (850) 558-5693
www.certusbuilders.corn
5/11/2023
Design/Build - Construction Management
Proposal
TO: Matt Anderson, Parks Senior Manager
City of Clearwater Parks & Recreation
100 S. Myrtle Ave.
Clearwater, FL 33756
RE: CLIFF STEPHENS PARK RECREATIONAL PIER
CONTRACT NO.
CITY PROJECT NO.
As requested, enclosed is the proposal for construction of the Cliff Stephens Park Recreational
Pier submitted in accordance with technical specs/plans/study/clarifications of this letter/attached
line item work,etc., for a Guaranteed Maximum Price of $292,811.31.
Scope of Work:
As per plans by Pennoni dated 1/10/2023, and attached Summary with list of clarifications dated
5/8/2023.
Cost Detail:
Description
Amount
Cost of Work
$209,797.82
Subtotal
$209,797.82
General Conditions
$20,487.00
General Liability/Workers
Comp/Automotive Insurance
$4,390.50
P&P Bond
$7,317.50
Construction Management Fee
$24,199.28
Contingency 10%
$26,619.21
Guaranteed Maximum Price
$292,811.31
Project Duration shall be 120 calendar days from the date of the Notice to Proceed.
Existing Contract: This proposal is submitted in conjunction with the existing Construction
Manager at Risk Services Continuing Contract entered into with the City of Clearwater on
September 23, 2020, based on RFO #40-20.
If GMP Exceeds $150,000: Per Section III, Article 5.1 of the Contract Specifications, the
contractor shall provide to the public entity a certified copy of the recorded bond. Once the City
receives a certified copy of the recorded bond, a Notice to Proceed may be issued. Include the
attached bond form as well as the Power of Attorney.
For work performed, invoices shall be submitted to the City of Clearwater, Parks & Recreation
Department, Attn: Matt Anderson, Parks Senior Manager, P.O. Box 4748, Clearwater, Florida,
33758-4748. Contingency services may be billed only after written authorization is provided by
the City to proceed with those services.
CERTUS BUILDERS, INC.
By:
Sharon A Sumner
President
5/11/2023
Date
CITY OF CLEARWATER, FLORIDA
Approved as to form: _ Attest:
issa Isabel
Assistant City Attorney
Countersigned:
Bridn Aungst Sr
Mayor
Rosemarie Call
City Clerk
1
J feoirrier
City Manager
Date
CERTUS
\ ar BUILDERS
SUMMARY
Cliff Stevens Park
Recreational Pier
5/8/2023
TRADE
COST
1 Mobilization
$
3,750.00
2 Miscellaneous Site
$
16,134.52
3 Marine Work
$
189,913.30
Subtotal Cost of Improvements (Lines 1- 3)
$ 209,797.82
CMAR General Conditions
$
20,487.00
Insurance
$
4,390.50
P&P Bond
$
7,317.50
CMAR Fees
$
24,199.28
Owner's Contingency 10%
$
26,619.21
Total
$
292,811.31
Clarifications
Pile Drive Monitoring is not included
Proposal is based on Plans dated 1/10/2023.
Price is based on an July 2023 start of construction.
We have included a P&P Bond
Builders Risk insurance is not included
Davis Bacon not included