WATER TREATMENT PLANT EAST DOME AND AERATOR AND MISCELLANEOUS IMPROVEMENTS - 20-0012-UT (WTP3) - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1
PROJECT:
CONTRACTOR:
WTP3 East Dome and Aerator and Misc.
Improvements
DATE:
PROJECT NUMBER:
PO REFERENCE:
May 9, 2023
20 -0012 -UT
23000086
COUNCIL AWARD: September 1, 2022
Razorback, LLC DATE OF CONTRACT: January 13, 2023
177 Anclote Road
Tarpon Springs, FL 34689 CODE: 3217321-546900-96782
SCOPE OF CHANGE: This Change Order is for an unexpected baffle wall repair needed on the water tank.
Change order will reallocate budget from line item #4 to line item #2 with a zero dollar effect on the total contract sum. Original construction
contract approved by Council on 09/01/2022 7.4 Ill #22-0805
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - City Manager
NEW CONTRACT AMOUNT
ACCEPTED BY: Razorback, LI.0
$ 1,791,334.60
$ By: .,.G (SEAL)
$ 1,791,334.60 Anthony Houllis, MGRM
Owen Kohler, Assist t . Attorney
ATTEST: n/�
Lam_ f1 i t u-- �4- .
Rosemarie Call,
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Jennifer Poirrier
Date:
c"12o1 2023
es: ri
ee„, _i - Lei cJ
Recommended By:
City of Clearwater
Adrian Gonzalez, Project Manager
Digitally signed by Richard Gardner
DN: cn=Richard Gardner, o=City of
Clearwater, ou=Public Utilities,
emai I=richa rd.gardner@myclearwater.com,
c -US
Date: 2023.05.28 13:11:44 -0400'
City Manager Richard C. Gardner, PE PU Director
Administrative Change Order 1: WTP3 East Dome and Aerator and Misc Improvements
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
4 Overhead concrete repair: Delaminated areas, FT3 1000 $ 200.00 $ (200,000.00)
spalls, resurfacing and exposed metal in overhead
interior dome roof surface of both tanks.
Estimated quantity is 2,000 cubic feet.
Total (Decreases): $ (200,000.00)
Increases:
2 Vertical concrete repair: Delaminated areas, FT3 333.333 $ 600.00 $ 200,000.00
spalls, and exposed metal in interior wall surfaces
of both tanks and baffle wall surface of east tank.
Estimated quantity is 25 cubic feet.
Total Increases: $ 200,000.00
Total Net (Decreases)/Increases: $ 0.00