JOINT PROJECT AGREEMENT UTILITY INSTALLATION BY ROADWAY CONTRACTORJOINT PROJECT AGREEMENT
UTILITY INSTALLATION BY ROADWAY CONTRACTOR
PROJECT NAME: Old Coachman Road (CR 535) Bridge Replacement over
Alligator Creek
PROJECT LIMITS: Old Coachman Road Bridge over Alligator Creek
COUNTY PROJECT IDENTIFICATION NO.: 001034A
THIS JOINT PROJECT AGREEMENT (Agreement) made and entered into on the
day of , 20 , by and between Pinellas County, a political subdivision of the State of
Florida, hereinafter the "County", and the City of Clearwater, Florida, a municipal corporation of
the State of Florida, hereinafter the "City" (collectively, Parties).
WITNESSETH, That:
WHEREAS, the County intends to construct bridge replacement on Old Coachman Road
(CR 535) over Alligator Creek (County Project No. 001034A or Project), which will call for the
adjustment, relocation and/or installation of the City's utility facilities along, over and/or under
the Project (Utility Work); and
WHEREAS, the County's plans for the Project have been reviewed by the City and the
City has had the opportunity for input into said plans; and
WHEREAS, the County and the City have determined that it would be to the best interest
of the general public and to the economic advantage of both Parties to enter into this Joint Project
Agreement for the Utility Work to be accomplished by the County's contractor as part of the
construction of the Project; and
WHEREAS, the City has expressed its desire to assume all reasonable and necessary costs
to be incurred for this Utility Work and has requested the County to include in said Project certain
plans and specifications to meet the City's needs.
NOW, THEREFORE, in consideration of the sum of One Dollar ($1.00) each to the other
in hand paid, the receipt whereof is hereby acknowledged, and in further consideration of the
mutual covenants hereinafter contained, it is agreed by the Parties as follows:
1. Utility Work
The City's Utility Work within the limits of the Project is more specifically described as the
replacement, relocation or adjustment of a 500 linear foot twelve inch (12") reclaimed water main
that is in conflict with the proposed bridge replacement improvements as part of County PID No.
001034A, located on Old Coachman Road over Alligator Creek.
2. Funding
2.1 The County will be responsible for the bidding and award of the construction
contract for the Project and will include the Utility Work as a separate option item in its bidding
document. After the County receives, opens, and evaluates the bids, the County will notify the
City, in writing, of the County's intent to award the contract ("Notification"). This Notification
will include the amount for the Utility Work option. The bid will be awarded based upon the total
bid amount including the Joint Project Agreement option. The City will have fifteen (15) days from
receipt of the County's notification to request, in writing, that the County delete the Utility
Work option from the County's award of bid/construction contract, and to notify the County of the
City's intent to perform the Utility Work with the City's own forces or its own contractor. In order
not to delay the construction of the Project, the City must show that it is ready and able to
perform all Utility Work prior to requesting that the County delete the Utility Work option from
the contract award. The City does not have the right to delay or affect, in any way, the award of
the contract. In the event the City, in performing the Utility Work causes a compensable delay
to the County's construction of this Project, the City will pay all claims and costs incurred due to
its delay.
2.2 The City hereby certifies that funding for the preliminary estimated Utility Work
cost (Exhibit A) of Four Hundred Eighty Two Thousand Four Hundred Sixty and 0/100
Dollars ($482,460.00), plus five percent (5%) for County construction/contract administration fee
of Twenty Four Thousand One Hundred Twenty Three and 0/100 Dollars ($24,123.00), for a total
cost of Five Hundred Six Thousand Five Hundred Eighty Three and 00/100 Dollars
($506,583.00), has been appropriated and is available for deposit into an interest bearing escrow
account for the purpose of payments by the County to the contractor on the City's behalf. The
deposit will be due to the County no later than thirty (30) days from the date of Notification of
the County's intent to award the construction contract. If the Utility Work option portion of
the contractor's bid selected by the County for the performance of the Utility Work exceeds the
amount of the preliminary estimated Utility Work, then subject to and in accordance with the
limitations and conditions established by Subparagraph 2.1 hereof regarding the City's option to
remove the Utility Work, the City will deposit an amount with the County which equals the total
option item plus 5% of that amount for County construction/contract administration/compaction
and backfill testing. Interest will accrue on the deposit balance and be used toward the cost of the
Utility Work. In the event, the final actual cost of the Utility Work is less than the amount the City
deposited, including all interest earned, but excluding the 5% for County construction/contract
administration/compaction and backfill testing of the actual construction costs, the County will
reimburse the City any excess escrow account funds. Should contract modifications occur that
increase the cost of the Utility Work, or the estimated quantities of items provided by the City
in Exhibit A is exceeded, the City will be notified by the County accordingly. The City will pay
the County within thirty (30) calendar days of notification by the County to ensure that cash on
deposit with the County is sufficient to fully fund the cost of the Utility Work. The County shall
notify the City as soon as it becomes apparent the actual costs will overrun the award amount, and
the City shall pay for the cost overruns (plus a 5% administrative fee) within thirty (30) calendar
days of notification by the County. However, the failure of the County to notify the City shall
not relieve the City from its obligation to pay for the full cost of the Utility Work.
All deposits due to the County referenced in Section 2.2 above shall be mailed to:
Finance Division Accounts Receivable
Pinellas County Board of County Commissioners
P. O. Box 2438
Clearwater, FL 33757
2.3 The County will require the successful contractor to comply with the following
conditions. The City shall be responsible for the costs attributed to said compliance with these
conditions as part of the Utility Work:
(A) Indemnify, hold harmless, pay the costs of defense on behalf of and
defend the County and its agents and employees and the City and its agents and employees from
and against all claims, damages, losses, and expenses arising out of or resulting from the
performance of the Project or the Utility Work;
(B) Provide a dual obligee bond in the full amount of the Project, naming the
City and the County as obligees; and
(C) Provide insurance coverage per the requirements in the insurance section
of the invitation to bid as well as in the executed contract with the successful contractor. Both the
County's invitation to bid and the construction contract will require that the Contractor name the
County and the City as additional insured entities and certificate holders.
3. Joint Project Activities
3.1 The City has already prepared, at its expense, the design of plans and specifications
for all the City's necessary Utility Work and reimbursable Utility Work described above. A
complete plan set, construction cost estimate, and specifications covering all construction
requirements for the Utility Work designed by AECOM, Inc, dated 11/15/2021, and approved by
the City Engineer, Tara L. Kivett, P.E., provided to the county as construction documents.
3.2 The City will obtain all necessary permits required for construction of the Utility
Work. This Agreement does not relieve the City of any requirement to obtain required permits
from the County. A copy of all permits required for said Utility Work will be provided to the
County no later than September 30, 2022.
3.3 All surveys for construction of the Utility Work will be furnished by the successful
contractor, in accordance with the plans and specifications provided by the City.
3.4 The coordination of the City's Utility Work with that of the roadway contractor and
other utilities and/or their contractors will be the responsibility of the County. The City will
cooperate fully and immediately to resolve any delays in the construction of the project occurring
as the result of the City's Utility Work.
3.5 All of the Utility Work done pursuant to this Agreement shall be done in substantial
accordance with the City's plans and specifications, which plans and specifications are
incorporated hereto by reference. All information required for field changes, change orders or
supplemental agreements pertaining to the City's Utility Work will be promptly furnished to the
County.
3.6 During construction of the City's Utility Work, the City will provide the necessary
construction and engineering inspection for the City's Utility Work to determine if the Utility
Work is in substantial compliance with the plans and specifications, and provide all required
testing associated with the City's Utility Work, excluding backfill and compaction testing in
accordance with Pinellas County Minimum Testing Frequency Requirements, and provide results
to the County for same. The contractor shall contact the City's Engineering Inspection Division
at 727-6713, extension 4414 within 24 hours prior to commencement of any City Utility Work
to schedule the appropriate inspection and pressure testing. The City's inspector will immediately
notify the County inspector of any objections to the Utility Work.
3.7 The City will participate in the design, utility coordination, pre -construction, and
other meetings as necessary for Project coordination.
3.8 All adjustments, relocations, repairs, maintenance, and incidental work
("Incidentals") required to be performed to the City's existing utilities for the Joint Project, not
included in the Utility Work, will be the sole responsibility of the City. All such work is to be
coordinated with the construction of this Joint Project and in a manner that will not cause delay to
the County's Project contractor.
3.9 The City's comments and suggestions are invited and will be considered by the
County; however, all services and work under the construction contract will be performed to the
satisfaction of the County's Director of Public Works, who will decide all questions, difficulties,
and disputes of whatever nature which may arise under or by reason of such contract for Utility
Work, the prosecution and fulfillment of the services thereunder, and the character, quality, amount
and value thereof; and who's decision upon all claims, questions, and disputes thereunder are final
and conclusive upon the Parties hereto.
3.10 Upon completion of the entire Project, which will be determined jointly by the
County and the City, the City will own, control, maintain, and be responsible for all City utility
facilities in accordance with the terms of the County issued Utilization Permit. The City will
maintain and keep in repair, or cause to be maintained and kept in repair, all of such constructed
utility facilities.
3.11 The County will forward any accounting records, if requested, to the following City
representative:
Todd Kuhnel
City of Clearwater
100 South Myrtle Avenue
Clearwater, Florida 33756
3.12 Upon final payment to the contractor, the County intends to have its final and
complete accounting of all costs incurred in connection with the work performed hereunder within
three hundred sixty (360) days. All project costs records and accounts shall be subject to audit by
a representative of the Company for a period of three (3) years after the final close out of the
Project.
3.13 Upon completion of the entire Project, the Contractor will supply "as built"
("Record") standard size sheet (11" x 17" or 24" x 36") Utility Work plans to the County, who in
turn will within ninety (90) days, furnish the City with one (1) set.
3.14 Upon completion of the entire Project, the County will ensure that any warranty,
including materials, equipment, workmanship, and closeout documents, by the contractor
constructing and/or installing facilities related to the Utility Work in accordance with this
Agreement, is assigned to the City.
4. Project Managers
The primary contact for each of the Parties is:
4.1 The Project Manager for the City shall be Todd Kuhnel or their designee ("City's
Project Manager"), whose current telephone number is 727-562-4798, the email address is
todd.kuhnel@myclearwater.com and whose post office address is 100 South Myrtle Avenue,
Clearwater, Florida 33756.
4.2 The Project Manager for Pinellas County shall be Amin Vosouli or their designee
("County's Project Manager"), whose telephone number is 727-464-8889, the email address is
avosouli@pinellascounty.org and whose post office address is 14 S. Fort Harrison Avenue,
Clearwater, FL 33756.
4.3 Each Party may designate a replacement Project Manager by giving written notice
of such designation, and the telephone number, e-mail address, and mailing address to the other
party in accordance with this Agreement.
5. Records, Reports, and Inspection
The County shall maintain financial records, accounting and purchasing information, and books
and records for the Project. These books, records, and information shall comply with general
accounting procedures. All documents related to the Project are public records and shall be
retained and provided as required by law.
6. Compliance with Federal, State, County, and Local Laws
Both Parties shall comply with all federal, state, county, and local laws, regulations, and ordinances
at all times.
7. Responsibilities of the Parties
The County and the City shall be fully responsible for their own acts of negligence and
their respective employees' and/or agents' acts of negligence, when such employees' and/
or agents' are acting within the scope of their employment; and shall be liable for any
damages resulting from said negligence to the extent permitted by Section 768.28, Florida
Statutes. Nothing herein is intended to serve as a waiver of sovereign immunity by either the
County or the City. Nothing herein shall be construed as consent by the County or City to be
sued by third parties in any matter arising out of this Agreement.
8. Discrimination
The County and the City shall, during the performance of this Agreement, comply with all
applicable provisions of federal, state, and local laws and regulations pertaining to prohibited
discrimination.
9. Assignment
This Agreement may not be assigned.
10. Severability
Should any section or part of any section of this Agreement be rendered void, invalid, or
unenforceable by any court of law, for any reason, such a determination shall not render void,
invalid, or unenforceable any other section or any part of any section of this Agreement.
11. Entire Agreement
This Agreement constitutes the entire agreement between the Parties, and no change will be valid
unless made by a supplemental written agreement executed by both Parties.
12. Notification
All notices, requests, demands, or other communications required by law, or this Agreement
shall be in writing and shall be deemed to have been served as of the delivery date appearing
upon the return receipt if sent by certified mail, postage prepaid with return receipt requested,
or, if hand delivered, upon the actual date of delivery to the Project Manager, whose address is
set forth in Section 4 above.
13. Waiver
No act of omission or commission of either Party, including without limitation, any failure
to exercise any right, remedy, or recourse, shall be deemed to be a waiver, release, or
modification of the same. Such a waiver, release, or modification is to be effected only
through a written modification to this Agreement.
14. Due Authority
Each Party to this Agreement represents and warrants to the other Party that (i) it is duly
organized, qualified and existing entities under the laws of the State of Florida, and (ii) all
appropriate authority exists so as to duly authorize the persons executing this Agreement to so
execute the same and fully bind the party on whose behalf they are executing.
15. Headings
The paragraph headings are inserted herein for convenience and reference only, and in no way
define, limit, or otherwise describe the scope or intent of any provisions hereof.
16. Fiscal Funding
The obligations of the Parties are subject to appropriate budgeted funds being available in each
budget year to achieve the purposes of this Agreement. In the event that sufficient budgeted
funds are not available in a subsequent fiscal year, this Agreement shall terminate on the last day
of the fiscal year for which sufficient budgeted funds are available without penalty to either of
the Parties.
17. Term
The term of this Agreement shall commence upon execution of this Agreement, per the first
paragraph on page one (1) of the Agreement, by the Parties and shall terminate after completion
and acceptance of the Utility Work and upon final payment in accordance with the provisions of
Paragraph 3.12 of this Agreement. If the County fails to issue a Notice to Proceed to a contractor
for the Project within seven hundred twenty (720) days from the date of full execution of this
Agreement by the Parties, this Agreement shall be deemed terminated and any payments made
by the City to the County shall be refunded in full by the County within thirty (30) days.
IN WITNESS WHEREOF the Parties hereto have caused this Agreement to be executed by their
duly authorized representatives on the day and date first above written.
CITY OF CLEARWATER, FLORIDA,
A municipal corporation and
political subdivision of the State of Florida
B
rank V. Hibbard, Mayor
By: al oft. r.
Jon Jennings,
City Manager
ATTEST:
t3 IL(
Rosemarie
Call
City Clerk
OVED AS TO FORM:
By
Owen Kohler
Lead Assistant
City Attorney
OFFICIAL CITY SEAL
PINELLAS COUNTY, FLORIDA by
and through its Board of County
Commission
By:
Charlie Justice, Chair
ATTEST: Ken Burke,
Clerk of the Circuit Court
By:
Deputy Clerk
APPROVED AS TO FORM:
By:
Office of the County Attorney
Old Coachman/Spectrum Field RCW Pipe Repair Project
City of Clearwater, Florida
Engineer's Opinion of Probable Cost - Issued for Bid
August, 2022
Bid Item
Item Description
Quantity
Unit
Unit Price
Total Cost
CLW -005-0700
Survey and Layout
1
LS
$3,500
$3,500
CLW -005-0900
Survey As -Built
1
LS
$3,500
$3,500
CLW -101-0100
Mobilization/Demobilization
1
LS
$22,000
$22,000
CLW -102-0100
Maintenance of Traffic
1
LS
$3,000
$3,000
CLW -575-0103
Sodding, Bahia
800
SY
$12
$9,600
CLW -1
F&I 12" C-900/RJ CERTA-LOK DR 18 PVC RCW by HDD
240
LF
$240
$57,600
CLW -2
F&I 12" C-900/RJ CERTA-LOK DR 18 PVC RCW by Open Cut
280
LF
$200
$56,000
CLW -3
F&I 12" DI RCW Pipe Installed on Steel Pipe Bridge
1
LS
$175,000
$175,000
CLW -4
Remove & Dispose of Existing Aboveground Bypass Pipe
520
LF
$28
$14,560
CLW -5
Remove & Dispose of Existing Buried 12" RCW Pipe
100
LF
$35
$3,500
CLW -6
F&I 12" Gate Valve & Valve Box
2
EA
$9,200
$18,400
CLW -7
F&I 12" Thrust Restraint for New Fittings & Valves to PVC Pipe
20
EA
$310
$6,200
CLW -8
F&I 12" Thrust Restraint for Existing PVC Pipe
4
EA
$1,750
$7,000
CLW -9
F&I Combination Air Valve & Polyethylene Cover
2
EA
$7,000
$14,000
CLW -10
F&I Compact DI Fittings
1,500
LB
$18
$27,000
CLW -11
Tree Barricades
1
LS
$6,000
$6,000
CLW -12
Root Pruning
200
LF
$28
$5,600
Subtotal Estimated Construction Cost =
$432,460
CLW -999-0000 Unspecified Work
$50,000
Total Estimated Construction Cost =
$482,460
County Construction/Contract Administration Cost (5%):
$24,123
Total Estimated Project Cost:
$506,583
1 of 1