WAYFINDING SIGNS PROGRAM - 19-0016-EN - CHANGE ORDER #1Change Order One DATE:
PROJECT: PROJECT NUMBER:
Downtown Wayfinding - Phase 2 PO REFERENCE:
CONTRACTOR:
Biltmore Construction Co., Inc.
1055 Ponce De Leon Blvd
Clearwater, FL 33756
July 27, 2022
19 -0016 -EN
21000825
COUNCIL AWARD: May 20, 2021
DATE OF CONTRACT: May 24, 2021
CODE: 3157549-530300-92842
SCOPE: This Change Order Accepts Revisions to the Contract
Add items to account for work required to complete Phase 2 of the Wayfinding program. This is the final phase of the
program as designed. f�
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $
Change Order 2 - City Council 08/18/2022 $
NEW CONTRACT AMOUNT $
995,826.00
629,493.00
1,625,319.00
ACCEPTED BY:
BiltrlQre 0911 tructio `
;
SFA
Date:
Witness
Owen Kohler, Assistant City Attorney
ATTEST:
i,tt
Rosemarie Call,
Date: L ' kA_1 - x1 Yom'
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
#61°'"
Recommended By:
City of Clearwater
Catherine Corcoran, Project Manager
Jon P. Jennings,
Change Order One Downtown Wayfinding - Phase 2
ITEM
Additions:
DESCRIPTION
City Manager
UNIT
/4lLU
Tara KiveTt PE,
City Engineer
QTY UNIT COST TOTAL COST
13
FDOT Permit Allowance - Phase 2
LS
1
$ 5,000.00
$ 5,000.00
14
Sodding & Landscape Allowance -
Phase 2
LS1
$ 4,500.00
$ 4,500.00
15
Sign Fabrication & Installation - Phase
2
LS1
$ 494,647.00
$ 494,647.00
16
Electrical Allowance - Phase 2
LS
1
$ 5,000.00
$ 5,000.00
17
CM Contingency (3% of $593,861) -
Phase 2
LS1
$ 15,274.00
$ 15,274.00
18
General Conditions, Supervision,
Insurance Bond - Ph 2
LS1
$ 69,440.00
$ 69,440.00
19
Pre -construction Phase Fee
LS
1
$ -
$ -
20
OH&P (6% of $593,861.00)
LS
1
$ 35,632.00
$ 35,632.00
Total Additions:
$ 629,493.00