PROPOSAL FOR FIRE STATION NO. 46GUARANTEED MAXIMUM PRICE PROPOSAL CITY OF CLEARWATER FIRE STATION No. 46 February 2, 2022 (Revs) 546 Mandalay Ave, Clearwater Beach, FL 33767 BCC Project No. 999 COC Project No. 18 -0028 -FD BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 TABLE OF CONTENTS ❖ Article 1 — Guaranteed Maximum Price (GMP) Proposal • Project Summary ❖ Exhibit A — Enumeration of Contract Documents ❖ Exhibit B — Allowances ❖ Exhibit C — Assumptions and Clarifications ❖ Exhibit D — Guaranteed Maximum Price Breakdown ❖ Exhibit E — Construction Schedule ❖ Exhibit F — Design Alternates February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 1 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 ARTICLE 1 - Guaranteed Maximum Price (GMP) Proposal Biltmore Construction Co., Inc. proposes to complete the work, as described herein, for the Guaranteed Maximum Price (GMP) of: Ei2ht million three hundred forty -Six thousand seven hundred seventy-one and 00/100 Dollars ($8,346,771.00). This Price is for the performance of the Work as described herein and in accordance with the Contract Documents and Exhibits A through Exhibit F. This Guaranteed Maximum Price (GMP) proposal must be accepted in writing by the City of Clearwater on or before February 28, 2022, after said date, this Guaranteed Maximum Price (GMP) proposal shall be null and void, absent the express written acceptance by Biltmore Construction Co., Inc. By acceptance of the GMP and issuance of a Contract Amendment, the City of Clearwater hereby incorporates the GMP into the Agreement between Owner and Construction Manager. February 2, 2022 (Revs) BCC Project #999, COC Project # 18 -0028 -FD Page 2 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 PROJECT SUMMARY Clearwater Fire Station 46 546 Mandalay Ave Clearwater, FL. 33767 Demolition of existing Fire Station 46, and construction of a new 2 Bay, approximately 11,000 gross square foot fire station including a 1,500 sgft Parks & Recreation Maintenance Bay. Construction of Fire Station 46 is in accordance with 2020 Florida Building Code, design windspeed 157 mph (Vult). The structure will be composed of a heavy structural mat foundation eliminating the need for driven piles. The site will be enhanced with updated utility service connections to the new building, new sidewalks, driveway, and drainage, as well as a fully landscaped site. Sustainability features include a roof top thin film solar photo voltaic array, rain garden with native landscaping & educational signage, reflective TPO roof natural gas appliances and standby generator, bike racks, and low energy lighting, plumbing and mechanical systems. The building exterior will include new impact resistant storefront system, exterior glazing compliant with FDEP turtle safe ordinance, and bird safe glass silkscreen pattern on South facing elevation. The new living quarters will feature ten new dorm rooms, exercise room, kitchen, dining, dayroom, as well as an outdoor patio. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 3 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV 1#5 EXHIBIT A — Enumeration of Contract Documents Contract Documents include: the Drawings, Specifications, Addenda (Construction Documents), the Agreement, General Conditions, Supplementary Conditions as expressly noted herein, and this Exhibit A, as well as the Guaranteed Maximum Price (GMP) Proposal in its entirety. This GMP Proposal is expressly recognized as a Contract Document since it forms the basis upon which the Guaranteed Maximum Price is based. As such, in the event there is any disagreement, conflict, or ambiguity between the GMP Proposal and any other Contract Document, the GMP Proposal shall govern. The Owner's issuance of any Notice to Proceed, Purchase Order, or any other written directive or instructions to proceed with the Work, after this signed GMP Proposal has been delivered by Biltmore to the Owner, shall constitute an express acceptance of the foregoing Enumeration of Contract Documents and the enforceability thereof. • Report of Geotechnical Exploration prepared by Gulf Coast Testing Laboratory, Inc. dated September 21, 2020. • Demolition Asbestos Survey (Existing Fire Station 46 Building) prepared by I.B.C. Engineering -Environmental & Construction, LLC dated June 2, 2020. • Demolition Asbestos Survey (Parks & Recreation Building) prepared by I.B.C. Engineering -Environmental & Construction, LLC dated May 10, 2021. • Addendum # 1 dated September 29,2021 that revised Specification Section 075423 "Thermoplastic Polyolefm (TPO) Roofing" and drawing details and roofmg notes requiring XPS insulation is excluded; EPS insulation will be provided. The original specification for standard 20 PSI polyisocyanurate will be provided. • Master Consulting Engineers, Inc. Alternatives Narrative and accompanying structural drawings are included for reference only. Alternate pricing is shown in Exhibit F, Item # 6 and # 7. • Highlighted portion of Drawing C-3 of 8 "Drainage Plan" showing certain storm work along Bay Esplanade is to be performed by the City is excluded. Alternate pricing is shown in Exhibit F, Item # 9. See Attached Exhibit A Enumeration of Documents February 2, 2022 (Revs) BCC Project #999, COC Project # 18 -0028 -FD Page 4 Project999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name 00 - Procurement/Contractir 00 - Procurement/Contractir 00 - Procurement/Contractir 00 0000 City of Clearwater Specs 00 0001 Geotechnical Report 06/18/20 00 0002 Asbestos Survey for Demolition 060220 (Existing FS46 Bldg) 1 9/7/2021 9/9/2021 Permit Set 09/07/21 0 9/7/2021 9/9/2021 Permit Set 09/07/21 0 6/2/2020 00 - Procurement/Contractir 00 0003 Asbestos Survey for Demolition 090721 (Parks n Rec Bldg) 0 9/7/2021 00 - Procurement/Contractir 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 01- General Requirements 03 - Concrete 03 - Concrete 03 - Concrete 04 - Masonry 04 - Masonry 05 - Metals 05 - Metals 05 - Metals 05 - Metals 00 0110 011000 012300 012500 012600 012900 013100 013200 013233 013300 014000 014200 015000 016000 017300 017700 017823 017839 017900 03 2900 03 3000 03 3543 04 2000 04 2300 05 1000 05 2100 05 3000 05 5000 Table of Contents Summary Alternates Substitution Procedures Contract Modification Procedures Payment Procedures Project Management and Coordination Construction Progress Documentation Photographic Documentation Submittal Procedures Quality Requirements References Temporary Facilities and Controls Product Requirements Execution Closeout Procedures Operation and Maintenance Data Project Record Documents Demonstration and Training Under -Slab Vapor Barrier/Retarder Cast -in -Place Concrete Polished Concrete Floors Unit Masonry Reinforced Unit Masonry Structural Steel Steel Joists Metal Decking Metal Fabrications 1 9/29/2021 1 9/29/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 O 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 O 9/7/2021 O 9/7/2021 O 9/7/2021 O 9/7/2021 O 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 O 9/7/2021 O 9/7/2021 0 9/7/2021 O 9/7/2021 0 9/7/2021 O 9/7/2021 O 9/7/2021 0 9/7/2021 1 9/29/2021 9/30/2021 9/30/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Addendum 1 Addendum 1 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 05 - Metals 05 - Metals 06 - Wood/Plastics/Composi 06 - Wood/Plastics/Composi 06 - Wood/Plastics/Composi 06 - Wood/Plastics/Composi 05 5213 Pipe and Tube Railings 05 7300 Decorative Metal Railings 06 1000 Rough Carpentry 061533 Plastic Decking 061600 Sheathing 06 4116 Plastic -Laminate -Faced Architectural Cabinets O 9/7/2021 O 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/7/2021 1 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 1813 Pedestrian Traffic Coatings 07 2100 Building Insulation 07 2119 Foamed -In -Place Insulation 07 2713 MODIFIED BITUMINOUS SHEET AIR BARRIERS 0 9/7/2021 0 9/7/2021 0 9/7/2021 0 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 2726 07 4293 07 4646 07 5423 Fluid -Applied Membrane Air Barriers Soffit Panels Fiber -Cement Siding Thermoplastic -Polyolefin (TPO) Roofing 0 9/7/2021 O 9/7/2021 0 9/7/2021 1 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 - Thermal and Moisture P 07 6200 07 7100 07 7200 07 8413 07 9200 Sheet Metal Flashing and Trim Roof Specialties Roof Accessories Penetration Firestopping Joint Sealants 0 9/7/2021 O 9/7/2021 O 9/7/2021 O 9/7/2021 1 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 08 - Openings 08 - Openings 08 1113 Hollow Metal Doors and Frames 08 1416 Flush Wood Doors O 9/7/2021 1 9/29/2021 9/9/2021 Permit Set 09/07/21 9/30/2021 Addendum 1 08 - Openings 08 - Openings 08 3323 Overhead Coiling Doors 08 3613 Sectional Doors 0 9/7/2021 9/9/2021 Permit Set 09/07/21 0 9/7/2021 9/9/2021 Permit Set 09/07/21 Biltmore Construction Co., Inc. 1 of 9 Original Document Project 999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name 08 - Openings 08 - Openings 08 - Openings 08 4113 Aluminum -Framed Entrances and Storefronts 08 7100 Door Hardware 08 7913 KEY STORAGE EQUIPMENT 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 08 - Openings 08 8000 Glazing 9/29/2021 9/30/2021 Addendum 1 08 - Openings 08 9119 Fixed Louvers 9/29/2021 9/30/2021 Addendum 1 09 - Finishes 09 - Finishes 09 2216 Non -Structural Metal Framing 09 2400 Portland Cement Plastering (Stucco) 9/7/2021 9/29/2021 9/9/2021 Permit Set 09/07/21 9/30/2021 Addendum 1 09 - Finishes 09 2900 Gypsum Board 9/29/2021 9/30/2021 Addendum 1 09 - Finishes 09 - Finishes 09 - Finishes 09 3013 Ceramic Tiling 09 3016 Sheet Membrane Waterproofing and Crack Isolation 09 5113 Acoustical Panel Ceilings 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 09 - Finishes 09 - Finishes 09 - Finishes 10 - Specialties 10 - Specialties 10 - Specialties 10 - Specialties 10 - Specialties 09 6513 09 6566 09 9100 101400 10 2600 10 2800 10 4400 10 9050 Resilient Base and Accessories Resilient Athletic Flooring Painting Signs Wall and Door Protection Toilet Accessories Fire Protection Specialties Miscellaneous Specialties 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Addendum 1 11- Equipment 11- Equipment 12 - Furnishings 12 - Furnishings 12 - Furnishings 12 - Furnishings 14 - Conveying Equipment 21- Fire Suppression 21- Fire Suppression 21- Fire Suppression 21- Fire Suppression 21- Fire Suppression 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 22 - Plumbing 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 11 2300 Commercial Laundry Equipment 11 3100 Residential Appliances 12 2413 Roller Window Shades 12 3661 Simulated Stone Countertops 12 4816 Floor Mats and Frames 12 9300 Site Furnishings 14 4200 Vertical Lifts 210500 Common Work Results for Fire Suppression 210517 Sleeves and Sleeve Seals for Fire -Suppression Piping 210518 Escutcheons for Fire Suppression Piping 210553 Identification for Fire -Suppression Piping and Equipment 21 1313 WET -PIPE SPRINKLER SYSTEMS 22 0523 Valves, Cocks and Specialties for Plumbing Systems 22 0553 Identification of Systems and Equipment 22 0700 Insulation for Plumbing Systems 22 1113 Water Distribution Piping 22 1119 Domestic Cold & Hot Water Supply Piping & Hot Water Circulating Pipi 22 1316 Sanitary Sewer, Storm Water & Sanitary Vent Piping 22 1317 Cleanouts and Cleanout Access Covers 22 1600 Natural Gas Piping System 22 3400 Fuel -Fired Domestic Water Heaters 23 0100 General Mechanical Provisions 23 0500 Basic Mechanical Materials and Methods 23 0515 Instructions and Maintenance Manuals 23 0518 Piping Condensate Drain 23 0529 Hangers and Supports 23 0535 Electric Motors, High Efficiency Type 23 0548 Vibration Isolation Equipment 23 0553 Identification for HVAC Piping and Equipment 23 0593 HVAC Testing and Balancing 23 0700 Insulation, HVAC 23 0800 HVAC Commissioning 23 0810 Outside Air Unit 23 0923 Direct -Digital Control System 23 0925 Variable Frequency Drive 23 2313 Refrigerant Pipe, Valves and Specialties 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Biltmore Construction Co., Inc. 2 of 9 Original Document Project 999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 23 - HVAC 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 26 - Electrical 27 - Communications 27 - Communications 27 - Communications 27 - Communications 28 - Electronic Safety/Securil 28 - Electronic Safety/Securii 31- Earthwork 31- Earthwork 32 - Exterior Improvements 32 - Exterior Improvements Architectural Architectural 23 3100 Ductwork 23 3300 Duct System Accessories 23 3314 Dampers, Fire, Fire/Smoke, and Smoke 23 3427 Fans Centrifugal Roof Ventilators 23 3428 Fans Centrifugal Roof Upblast 23 3713 Air Distribution Devices 23 8126 Condensing Units Air Cooled 23 8127 Air Handling Units, Split System 23 8132 Variable Refrigerant Flow (VRF) Air Conditioning System 26 0500 Basic Electrical Requirements 26 0519 Wires and Cables 26 0526 Grounding 26 0533 Outlet Boxes 26 0539 Raceways and Conduit 26 0553 Electrical Identification 26 2416 Panelboards 26 2420 Safety Switches 26 2726 Wiring Devices 26 3213.17 Engine Generators 26 3600 Transfer Switches 26 4113 Lightning Protection for Structures 26 4313 Surge Protective Devices 26 5100 Lighting 27 0010 Technology General Provisions 27 0526 Grounding and Bonding for Communications Systems 27 0528 Raceways for Technology 27 1000 Structured Cabling System 28 0000 City of Clearwater Division 28 Standards 28 3111 Addressable Fire -Alarm Systems 31 3116 Termite Control 31 6219 Timber Piles 32 1313 Concrete Paving 32 1316 Decorative Concrete Paving A-001 SITE PLAN A-101 LEVEL 1- FLOOR PLAN 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 Permit Set 09/07/21 (New Bldg Only) Addendum 1 Architectural A-102 LEVEL 2 - FLOOR PLAN 9/29/2021 9/30/2021 Addendum 1 Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural A-103 HIGH FLOOR PLAN A-106 ROOF PLAN A-110 LEVEL 1- EOS PLAN A-111 LEVEL 1- EOS PENETRATIONS A-112 LEVEL 2 - EOS PLAN A-113 LEVEL 2 - EOS PENETRATIONS A-120 LEVEL 1- DIMENSION PLAN A-121 LEVEL 1- FLOOD VENTS DIMENSION PLAN A-122 LEVEL 2 - DIMENSION PLAN A-124 ROOF - DIMENSION PLAN A-201 LEVEL 1- RCP A-202 LEVEL 2 - RCP A-203 LEVEL 2 - HIGH RCP A-300 EXTERIOR ELEVATIONS A-301 EXTERIOR ELEVATIONS A-302 EXTERIOR ELEVATIONS - COLOR A-303 EXTERIOR ELEVATIONS - COLOR A-310 BUILDING SECTIONS A-311 BUILDING SECTIONS 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Biltmore Construction Co., Inc. 3 of 9 Original Document Project 999 Enumeration of Documents Clearwater Fire Station 46 Discipline/Division Drawing No. Drawing Title Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural A-312 A-313 A-400 A-410 A-411 A-412 A-413 A-414 A-415 A-420 A-500 A-501 A-600 A-601 A-602 A-603 A-604 A-605 A-607 A-620 A-621 A-700 A-701 A-702 A-720 A-721 A-722 A-723 A-724 A-725 A-800 BUILDING SECTIONS BUILDING SECTIONS Rev No. Drawing Date Received Date Revised 10/21/2021 GMP Set Name ENLARGED WATER CLOSET PLANS AND ELEVATIONS ENLARGED PLANS AND ELEVATIONS ENLARGED FLOOR PLANS AND ELEVATIONS ENLARGED PLANS AND ELEVATIONS 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 ENLARGED PLANS AND ELEVATIONS ENLARGED PLANS AND ELEVATIONS ENLARGED PLANS AND ELEVATIONS MILLWORK SECTIONS 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 INTERIOR ELEVATIONS INTERIOR ELEVATIONS STAIR PLAN & SECTIONS STAIR PLAN & SECTIONS STAIR PLAN & SEC. STAIR PLAN & SEC. STAIR PLANS & SECTIONS LADDER SECTIONS STAIR DETAILS CEILING DETAILS CEILING DETAILS WALL SECTIONS WALL SECTIONS WALL SECTIONS BREAKAWAY WALLS PLAN DETAILS ENCLOSURE DETAILS ENCLOSURE DETAILS ENCLOSURE DETAILS ENCLOSURE DETAILS ENCLOSURE DETAILS PARTITION TYPES 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Architectural Architectural Architectural Architectural A-801 A-802 A-803 A-810 PARTITION TYPES PARTITION TYPES PARTITION DETAILS DOOR SCHEDULES 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Architectural A-811 DOOR HARDWARE SCHEDULE 9/29/2021 9/30/2021 Addendum 1 Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural A-812 DOOR DETAILS A-813 DOOR DETAILS A-830 EXTERIOR STOREFRONT & LOUVER ELEVATIONS A-831 INTERIOR STOREFRONT ELEVATIONS & DETAILS A-832 STOREFRONT AND LOUVER DETAILS A-833 STOREFRONT AND LOUVER DETAILS AD -100 DEMO SITE PLAN AD -101 EXISTING TO BE SALVAGED B-101 LEVEL 1- LIFE SAFETY PLAN 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Architectural B-102 LEVEL 2 - LIFE SAFETY PLAN 9/29/2021 9/30/2021 Addendum 1 Architectural Architectural Architectural Architectural Architectural Architectural Architectural Architectural G-100 COVER G-101 DRAWING LEGEND AND BUILDING DATA G-102 SHEET INDEX G-103 CODE ANALYSIS G-104 MOUNTING HEIGHTS G-105 UL LISTINGS G-106 UL LISTINGS ID -101 LEVEL 1- FINISH PLAN 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Architectural ID -102 LEVEL 2 - FINISH PLAN 9/29/2021 9/30/2021 Addendum 1 Biltmore Construction Co., Inc. 4 of 9 Original Document Project999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name Architectural ID -202 LEVEL 2 FURNITURE PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21(New Bldg Only) Architectural ID -401 INTERIOR DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Architectural ID -402 SIGNAGE 0 9/7/2021 9/9/2021 Permit Set 09/07/21(New Bldg Only) Civil C-1 of 8 EX. COND./DEMO & SOIL EROSION CONTROL PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-2 of 8 SITE PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-3 OF 8 PAVING, GRADING & DRAINAGE PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-4 OF 8 UTILITY PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-5 OF 8 CONSTRUCTION DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-6 OF 8 CONSTRUCTION DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-7 OF 8 CONSTRUCTION DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Civil C-8 OF 8 SPECIFICATIONS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-000 LEGEND - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-001 SCHEDULES - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-100 SITE PLAN - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-201 LEVEL 1- FLOOR PLAN - POWER 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-202 LEVEL 2 - FLOOR PLAN - POWER 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-203 ROOF PLAN - POWER 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-301 LEVEL 1- FLOOR PLAN - LIGHTING 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-302 LEVEL 2 - FLOOR PLAN - LIGHTING 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-401 ENLARGED FLOOR PLAN & LIGHTING CONTROLS CONTRACT LAYOUT 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-501 RISER DIAGRAM - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-502 CALCULATIONS -ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-601 PANEL SCHEDULES - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-901 DETAILS - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Electrical E-902 DETAILS - ELECTRICAL 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Fire Protection FP -000 LEGEND - FIRE PROTECTION 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Fire Protection FP -100 SITE PLAN - FIRE PROTECTION 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Fire Protection FP -200 UNDERGROUND - FLOOR PLAN - FIRE PROT. 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Fire Protection FP -201 LEVEL 1- RCP - FIRE PROTECTION 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Fire Protection FP -202 LEVEL 2 - RCP - FIRE PROTECTION 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg only) Fire Protection FP -901 DETAILS - FIRE PROTECTION 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape IR1 IRRIGATION PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape IR2 IRRIGATION NOTES AND DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape IR3 IRRIGATION DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape 10 TREE INVENTORY/ PRESERVATION PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape 11 LANDSCAPE PLAN 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape L2 LANDSCAPE NOTES 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Landscape L3 LANDSCAPE DETAILS 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-000 LEGEND - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-201 LEVEL 1- FLOOR PLAN - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-202 LEVEL 2 - FLOOR PLAN - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-203 ROOF PLAN - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-701 CONTROLS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-801 SCHEDULES - HVAC 1 9/29/2021 9/30/2021 Addendum 1 Mechanical M-802 SCHEDULES - HVAC 1 9/29/2021 9/30/2021 Addendum 1 Mechanical M-901 DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-902 DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-903 DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-904 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-905 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-906 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-907 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-908 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-909 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Mechanical M-910 KITCHEN DETAILS - HVAC 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Biltmore Construction Co., Inc. 5 of 9 Original Document Project 999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name Mechanical Plumbing Plumbing Plumbing Plumbing Plumbing Plumbing M-911 VRF SYSTEM DIAGRAM P-000 LEGEND - PLUMBING P-200 UNDERGROUND - FLOOR PLAN - PLUMBING P-201 LEVEL 1- FLOOR PLAN - GRAVITY P-202 LEVEL 2 - FLOOR PLAN - GRAVITY P-203 ROOF PLAN - PLUMBING P-301 LEVEL 1- FLOOR PLAN - PRESSURE 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Plumbing P-302 LEVEL 2 - FLOOR PLAN - PRESSURE 9/29/2021 9/30/2021 Addendum 1 Plumbing Plumbing Plumbing Plumbing P-501 P-502 P-601 P-901 RISER DIAGRAM - PRESSURE RISER DIAGRAMS - GRAVITY SCHEDULES - PLUMBING DETAILS - PLUMBING 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Plumbing Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Structural Technology Technology P-902 S101 -A1 S102 -A1 S201 -A1 S202 -A1 S203 -A1 S205 -A1 S206 -A1 S301 -A1 S302 -A1 S303 -A1 S304 -A1 S305 -A1 S306 -A1 S308 -A1 S309 -A1 S310 -A1 S401 -A1 S402 -A1 S403 -A1 S404 -A1 S405 -A1 S406 -A1 S407 -A1 S408 -A1 S501 -A1 S502 -A1 S503 -A1 5504-A1 S505 -A1 S601 -A1 S602 -A1 S701 -A1 T-000 T-100 DETAILS - PLUMBING GENERAL STRUCTURAL NOTES WIND DESIGN DATA AND LOAD SCHEDULE FOUNDATION PLAN SLAB ON GRADE PLAN 2ND FLOOR FRAMING PLAN LOW ROOF FRAMING PLAN HIGH ROOF FRAMING PLAN TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS SCHEDULES SCHEDULES ISOMETRIC VIEWS LEGEND -TECHNOLOGY SITE PLAN -TECHNOLOGY 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/7/2021 9/29/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/9/2021 9/30/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Addendum 1 Technology T-201 LEVEL 1- FLOOR PLAN - TECHNOLOGY 9/29/2021 9/30/2021 Addendum 1 Technology T-202 LEVEL 2 - FLOOR PLAN - TECHNOLOGY 9/29/2021 9/30/2021 Addendum 1 Technology Technology T-401 ENLARGED FLOOR PLANS T-501 RISERS - TECHNOLOGY 9/7/2021 9/29/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) 9/30/2021 Addendum 1 Technology Technology Technology T-901 T-902 T-903 DETAILS - TECHNOLOGY DETAILS - TECHNOLOGY DETAILS - TECHNOLOGY 9/7/2021 9/7/2021 9/7/2021 9/9/2021 9/9/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Biltmore Construction Co., Inc. 6 of 9 Original Document Project999 Enumeration of Documents Revised 10/21/2021 Clearwater Fire Station 46 Exhibit A GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name **FOR DEMOLITION PERMIT ONLY **Architectural **Architectural **Architectural **Civil **Civil **Civil **Landscape **Landscape **Landscape **Landscape AD -100 DEMO SITE PLAN AD -101 EXISTING TO BE SALVAGED G-100 COVER C-1 OF 8 EX. COND./DEMO & SOIL EROSION CONTROL PLAN C-5 OF 8 CONSTRUCTION DETAILS C-8 OF 8 SPECIFICATIONS IR1 IRRIGATION PLAN IR2 IRRIGATION NOTES AND DETAILS IR3 IRRIGATION DETAILS LO TREE INVENTORY/ PRESERVATION PLAN 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Permit Set 09/07/21 (Demo Only) Biltmore Construction Co., Inc. 7 of 9 Original Document Project 999 Clearwater Fire Station 46 Discipline/Division Drawing No. Drawing Title Enumeration of Documents ._xhibit A Rev No. Drawing Date Received Date Revised 10/21/2021 GMP Set Name ***THE FOLLOWING DRAWINGS COINCIDE WITH ADD ALTERNATE #7 LISTED ON PAGE 14 OF GMP Structural S101 -A2 Structural S102 -A2 Structural S201 -A2 Structural S202 -A2 Structural 5203-A2 Structural S205 -A2 Structural S206 -A2 Structural S301 -A2 Structural S302 -A2 Structural 5303-A2 Structural S304 -A2 Structural S305 -A2 Structural 5306-A2 Structural S308 -A2 Structural S309 -A2 Structural 5310-A2 Structural S401 -A2 Structural S402 -A2 Structural S403 -A2 Structural S404 -A2 Structural S405 -A2 Structural S406 -A2 Structural 5407-A2 Structural S408 -A2 Structural S501 -A2 Structural 5502-A2 Structural S503 -A2 Structural S504 -A2 Structural S505 -A2 Structural S601 -A2 Structural S602 -A2 Structural S701 -A2 GENERAL STRUCTURAL NOTES WIND DESIGN DATA AND LOAD SCHEDULE FOUNDATION PLAN SLAB ON GRADE PLAN 2ND FLOOR FRAMING PLAN LOW ROOF FRAMING PLAN HIGH ROOF FRAMING PLAN TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS SCHEDULES SCHEDULES ISOMETRIC VIEWS 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) 8of9 Biltmore Construction Co., Inc. Original Document Project999 Enumeration of Documents Clearwater Fire Station 46 Exhibit A Revised 10/21/2021 GMP Discipline/Division Drawing No. Drawing Title Rev No. Drawing Date Received Date Set Name ***THE FOLLOWING DRAWINGS COINCIDE WITH ADD ALTERNATE #6 LISTED ON PAGE 14 OF GMP Structural 5101-A3 Structural 5102-A3 Structural S201 -A3 Structural 5202-A3 Structural S203 -A3 Structural 5205-A3 Structural 5206-A3 Structural 5301-A3 Structural S302 -A3 Structural 5303-A3 Structural 5304-A3 Structural S305 -A3 Structural 5306-A3 Structural 5308-A3 Structural 5309-A3 Structural S310 -A3 Structural S401 -A3 Structural 5402-A3 Structural S403 -A3 Structural 5404-A3 Structural 5405-A3 Structural 5406-A3 Structural 5407-A3 Structural S408 -A3 Structural S501 -A3 Structural S502 -A3 Structural S503 -A3 Structural 5504-A3 Structural 5505-A3 Structural S601 -A3 Structural S602 -A3 Structural S701 -A3 GENERAL STRUCTURAL NOTES WIND DESIGN DATA AND LOAD SCHEDULE FOUNDATION PLAN SLAB ON GRADE PLAN 2ND FLOOR FRAMING PLAN LOW ROOF FRAMING PLAN HIGH ROOF FRAMING PLAN TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS TYPICAL DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS SECTIONS AND DETAILS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS WALL ELEVATIONS SCHEDULES SCHEDULES ISOMETRIC VIEWS 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 O 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 0 9/7/2021 9/9/2021 Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) Permit Set 09/07/21 (New Bldg Only) 9of9 Biltmore Construction Co., Inc. Original Document BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 EXHIBIT B — Allowances The Allowances noted below represent reasonably anticipated values included in this GMP Proposal to cover the cost of certain items absent or not specified in sufficient detail in the Construction Documents as listed in the ENUMERATION OF CONTRACT DOCUMENTS Section of this GMP Proposal or for which uncertainty remains. The amount of the Allowance stipulated herein is inclusive of all labor, materials, equipment, taxes, delivery, insurances, bond and fees necessary to perform the anticipated work, unless otherwise noted. Allowances- Unless otherwise specifically noted, the term "Allowance" refers to the amount of money allocated to cover the cost of both materials and labor to furnish and install the specified material(s) or perform the specified work and any applicable sales tax only; overhead and profit are not included in the line item, how it is calculated within the stipulated fee. Owner understands and agrees that should the actual costs exceed the amount specified in the GMP for the allowance, an adjustment by change order will be made at the final billing for the project. The ASSUMPTIONS AND CLARIFICATIONS section of this GMP Proposal may provide a more detailed description of these Allowances. DESCRIPTION OF ALLOWANCE ALLOWANCE AMOUNT Utility Consumption Allowance After Temporary Permanent Power $ 15,000.00 Dedication Plaque $ 2,500.00 Dewatering Allowance $ 50,000.00 Fitness Equipment and Miscellaneous Moving Allowance $ 7,500.00 February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 5 B11;CSIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #S EXHIBIT C — Assumptions and Clarifications The Contract Documents are amended by Biltmore Construction Co., Inc. as follows: 1. The following are not included in the GMP Proposal: A. Hazardous Materials Survey is excluded. B. Removal of Unsuitable Soils is excluded. C. Impact Fees/Inspection Fees, Plan Review Fees and Permit Fees are excluded. To be waived by the City of Clearwater. D. Threshold inspections are excluded. E. Performance Specifications are excluded. F. Proposal/Bid Bond is excluded. G. Builder's Risk Insurance is excluded. To be provided by the City of Clearwater. H. Permanent Power and Water Consumption Costs are excluded. I. Division 28 `Electronic Safety and Security (Convergint & GSA), Addressable Fire Alarm System (Maire), and 911 System Equipment (Motorola) are excluded. This work is to be contracted directly by the City. J. Division 11 "Equipment" Commercial Laundry Equipment and Residential Appliances, and miscellaneous furniture to be purchased directly by the City. K. Revisions because of City of Clearwater Building Department Plan Review Comments. 2. Warranties and Guarantees: A. Biltmore Construction Co., Inc. Warranties and Guarantees Biltmore Construction Co., Inc. warrants to the City of Clearwater that the materials and workmanship furnished under this Contract will be of good quality and new unless otherwise required or permitted by the Construction/Contract Documents, that the Work will be free from defects not inherent in the quality required or permitted, and that the Work will conform with the requirements of the Construction/Contract Documents. Work not conforming to these requirements may be considered defective. Biltmore Construction Co., Inc.'s warranty excludes remedy for damage or defect caused by insufficient maintenance, improper operation, or normal wear and tear under normal usage. The term and duration of this express warranty is one (1) year from the Date of Substantial Completion. The provisions herein shall not prevent the City of Clearwater from proceeding directly against the manufacturer and/or installer for such longer period as allowed by State Statute. B. Installer / Subcontractor Warranties and Guarantees The Subcontractor shall warrant to the City of Clearwater and to Biltmore Construction Co., Inc. that all workmanship and materials are free from defects in installation. The period customarily being one (1) year from the Date of Substantial Completion established in the Construction/Contract Documents. Notwithstanding anything to the contrary, neither Biltmore Construction Co., Inc., nor its Surety, nor the Subcontractor shall have any joint/several liability relating to, nor shall they be obligated to underwrite, or in any way become guarantor(s) of any manufacturer's warranty/guaranty or product to the City. The City of Clearwater shall be provided with the "standard" manufacturer's warranty, and it shall satisfy the requirements under the Construction/Contract Documents relating thereto. C. Manufacturer's Express Warranties / Guarantees Biltmore Construction Co., Inc. shall collect and transmit to the City of Clearwater all standard manufacturer's warranties and standard manufacturer's guarantees specified in the Construction/Contract Documents. The obligation and liability of Biltmore Construction Co., Inc. and/or its Surety is limited to the collection and proper transmittal of these warranties and guarantees to the City. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 6 BILI'\IOlih: CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 Biltmore Construction Co., Inc. shall defer to and provide the manufacturer's requirements for standard and extended warranties, in all cases of conflict between manufacturer's warranties and those specified in the Construction/Contract Documents. 3. Special conditions relating to City of Clearwater purchased / Contractor installed items and associated tax exemptions: Biltmore Construction Co., Inc. acknowledges that Owner is implementing a direct purchase program pursuant to Florida Statute Section 212.08(6) to avoid sales tax on materials incorporated into the Project (the "ODP Program"). Owner acknowledges and agrees that (i) all deductive change orders issued by Biltmore to its Subcontractors participating in the ODP Program and corresponding deductive Change Orders issued by Owner to Biltmore under the ODP Program (collectively the "ODP Change Orders") include the costs of materials and the applicable Florida state sales tax, (ii) the value of the ODP Change Orders will be based on estimated quantities and costs, except when the ODP Change Order expressly involves the purchase of a single item with a predetermined fixed value, and (iii) the actual costs incurred for materials under the ODP Program will be reconciled with the estimated costs and if the aggregate cost actually incurred by Owner to purchase the materials is less than the value of the ODP Change Order minus applicable sales tax (the "Underrun"), then Owner will issue to Biltmore an additive Change Order in the amount of the Underrun plus the applicable sales tax on such Underrun value, and Biltmore will issue a corresponding additive change order to the applicable Subcontractor. Table below presents an illustration of the foregoing calculation. Description of Purchase Pretax Value 6% Sales Tax Deductive ODP Change Order Value Final Value of Purchase Pretax Value of Underrun 6% Tax on Underrun Additive Reconciliation Change Order Value Paint $100,000 $6,000 $106,000 $75,000 $25,000 $1,500 $26,500 4. Builder's Risk Insurance: City of Clearwater shall purchase and maintain, until the date of Substantial Completion of this project, a standard Special Form (all "Risks of Physical Loss") Completed Value Builder's Risk insurance policy in the amount of the initial contract sum (GMP), including any subsequent modifications thereto, insuring the interests of the City, Biltmore Construction Co., Inc., and Subcontractors in the Work under this contract. All premiums and deductible costs related to this property insurance shall be paid by the City of Clearwater. The following items are the responsibility of the City of Clearwater and are not included in this GMP: a. Property insurance premiums and/or deductible costs. b. Property insurance coverage on existing buildings and/or contents. c. Property insurance coverage on the Work under this Contract after the date of Substantial Completion. d. Flood insurance coverage and/or risk of loss due to flood. e. Windstorm insurance and/or risk of loss due to named Windstorm including all deductibles. 5. Basis of this GMP Proposal relative to Documents and Specifications as issued by Wannemacher Jensen Architect's Inc. identified in Exhibit A, "Enumeration of Documents". 6. Schedule, Price, Escalation In the event of Force Majeure: Neither Party will be liable for any failure or delay in performing an obligation under this Agreement that is due to any of the following causes, to the extent beyond its reasonable control: acts of God, accident, riots, war, terrorist attack, epidemic, pandemic (including the COVID-19 pandemic), quarantine, civil commotion, breakdown of communication facilities, breakdown of web host, breakdown of internet service provider, natural catastrophes, government acts or omissions, changes in laws or regulations, national strikes, fire, explosion, or generalized lack of availability of raw materials and energy. Market conditions today have and are being acted on by influences beyond the control of the Client and the Contractor. As a result of this, we further define the effects of Force Majeure and how we will reach an equitable outcome. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 7 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 If either Party detects a Force Majeure issue, they shall promptly notify the other Party and meet to resolve the schedule and/or cost overruns. In the event of any cost or schedule overruns due to Force Majeure, the Contractor will be allowed to increase the GMP for all direct labor and material costs, without profit on the extra costs. 7. Subcontractor Payments: Notwithstanding anything to the contrary, the City specifically acknowledges and agrees that the Construction Manager (Contractor) operates on a pay -when -paid basis with its subcontractors, and nothing contained herein or elsewhere shall be interpreted to require the Construction Manager and/or its Surety to remit any payment (including final payment) to subcontractors prior to the receipt of payment (including final) from the Owner. 8. GMP Schedule of Values: It is acknowledged and agreed that, notwithstanding anything else to the contrary, the breakdown associated with the Guaranteed Maximum Price and/or the resulting Schedule of values shall in no way act as an individual line item guaranteed maximum price. 9. A Construction Manager Contingency of $193,839.00 is included. Acceptable uses of this Contingency include, but are not limited to: a. Buy -Out of the work not previously awarded in bid packages. b. Repair of damages caused by an unknown source (excluding Builder's Risk claims). c. To improve and/or accelerate the progress of the work. d. To improve the conditions of the work. e. For modifications of the work resulting from an unknown ambiguity (Not an error or omission) in the contract documents. f. To increase and /or supplement staff as necessary to effectively manage the project. g. To adjust the reimbursable General Conditions/Requirements more than the line -item value. 10. No retainage will be held on Bonds, Insurances, General Condition Requirements, Staffing, Construction Phase Fee or OH&P. 11. Electronic BIM or CAD "As-Builts" are not included. Biltmore Construction will maintain "As -Built" documents on site during the construction phase and provide the City of Clearwater and Architect a copy at project completion. 12. We have included costs in the General Conditions Line Item for Document Management and Project Management Control Services. These services will be provided via cloud -based platform that will allow direct access by all construction personnel, including Owners, Architects and Subcontractors. Services will include the ability to access and/or manage information via mobile device over the Internet. Services included will be Plans and Specifications, maintenance and distribution, RFI Control, Submittal Control, Punch List Management, Daily Reports along with other related functions inherent in the platform. The charge for this service shall be $4,000.00 and will be billed as a lump sum amount upon approval of GMP and issuance of Notice to Proceed. 13. We have included costs in the General Conditions line Item for MIS Services related to the project. This includes software updates associated with Biltmore Construction's standard software provided for cost management, computer operating systems, PDF software, word processing applications and spreadsheet applications. This also includes troubleshooting, virus management/remediation, malware/adware, management/remediation, updates and maintenance of these systems. The charge for this service shall be $ 5,000.00 and shall be billed as a lump sum amount upon approval of the GMP and issuance of the Notice to Proceed. 14. Technical Clarifications: A. General Requirements 1. Survey Work required for site and building layout as deemed necessary by the Construction Manager is included. The City's Survey crew may be used at no cost as they may be made available. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 8 BILTMORE CONSTRUCTION CO, INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 2. Materials Testing to include, but is not necessarily limited to, soil densities, concrete compressive strength, steel erection, and any other testing required by specifications or City standards is included. References to the Owner contracting with a testing agency are to be disregarded. This includes, but is not necessarily limited to Specification Sections 033000 "Cast -in Place Concrete", 051000 "Structural Steel", 3. Test and Balance of the HVAC System is included. 4. Master Consulting Engineers, Inc. Alternate 1 is included. 5. An Allowance of $15.000.00 is included for Temporary Utility Consumption Costs. 6. An Allowance of $2,500.00 is included for a Dedication Plaque. No specifications have been provided at the time of this GMP. 7. An Allowance of $50.000.00 is included for Dewatering. 8. An Allowance of $7,500.00 is included to relocate existing fitness equipment and miscellaneous items to the new building. 9. No provision or allowance is included for removal and replacement of unsuitable soils. 10. The issuance of the Construction Manager's Performance and Payment Bonds will be provided after the approval of the GMP and issuance of the Notice to Proceed by the City of Clearwater. 11. Section I, "Advertisement of Bids & Notice to Contractors" of the City of Clearwater Contract Documents & Specification is included. Biltmore Construction Co., Inc. complied with advertising requirement. 12. Section II, "Instruction to Bidders" and "Supplemental Instructions to Bidders" of the City of Clearwater Contract Documents & Specification are excluded. Subcontractor bid requirements are outlined in Exhibit B of the Construction Manager @ Risk Services. 13. Section III, "General Conditions" and Section IIIa "Supplemental General Conditions" of the City of Clearwater Contract Documents are included only as they pertain to and are consistent with the Construction Manager @ Risk Services. 14. Section IV, "Technical Specifications and IVa, "Supplemental Technical Specifications" of the City of Clearwater Contract Documents 7 Specifications are included only as they pertain to the Fire Station 46 Construction Documents (Drawings and Technical Specifications) as listed in the Enumeration of Documents. If confliction, the Construction Documents (Drawings and Technical Specifications) will be followed. 15. Appendix, "ODP Documents and Other Project Documentation" of the City of Clearwater Contract Documents & Specifications was not issued and thus is excluded. 16. Section V, "Contract Documents" of the City of Clearwater Contract Documents and Specifications is excluded. The Construction Manager @ Risk Services will be followed. 17. The City will pay for on-site and off-site stored materials with proper documentation by CM. 18. In the case where a vendor requires advance payment for materials/equipment, The City will allow the CM to bill in advance and make advance payment to the CM for that material/equipment. Vertical Lift manufacturer requires $20,000.00 pre -payment at subcontract signing, $10,000.00 pre -payment at delivery and pre -payment of $3,500.00 at completion of installation. 19. Unless otherwise specified, colors and fmishes shall be only standard selections available from the manufacturer. No premium or exotic colors or finishes are included. 20. No Performance Specifications are included. 21. Delegated Design submittals are limited to the requirements of the Specifications. Including 055213 "Pipe and Tube Railings", 057300 "Decorative Metal Railings", 084113 "Aluminum -Framed Entrances and Storefronts", and 089119 "Fixed Louvers". 22. All railings will be manufactured and installed to comply with Florida Building Code. Shop drawings will be provided. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 9 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 23. Salvaged items to be turned over to the Owner are identified on Drawing AD -101. Any other salvaged materials/equipment will be the property of the Construction Manager. Salvaged items identified to be incorporated into the new building are the Original Station Number, Corner Guards, Badges, EMS Shelves, Fire Pole and Flagpoles, and select furnishings and equipment. 24. Existing asphalt damaged because of new construction will be repaired. 25. Existing sodding damaged because of new construction will be restored. 26. Existing irrigation damaged because of new construction will be repaired. However, no provisions are included to repair the existing irrigation system. 27. Typical Project Sign based on the City of Clearwater Contract Documents and Specifications Article 23.8 is included. City to provide text as required. 28. Responses to Preconstruction Requests for Information are included. Costs for responses received after the date of this GMP Proposal are not included. 29. Specification Section 012600 "Contract Modification Procedures, 012900 "Payment Procedures", 013100 "Project Management and Coordination" and 03200 "Construction Progress Documentation" are disregarded and shall be governed by the Construction Manager at Risk Agreement. 30. Reference Drawing P-601, "Plumbing Fixture Schedule" Mop Sink MS -1 is to be a standard mop sink. Terra.i7o mop sink to be revised by the Design Team. 31. No oil monitoring system is to be provided. None shown. 32. Reference Specification Section 075423 "Thermoplastic-Polyolefm (T.P.0) Roof. GMP includes EPS insulation in lieu of XPS insulation and standard 20 PSI Polyiso insulation. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 10 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 EXHIBIT D - GUARANTEED MAXIMUM PRICE BREAKDOWN Itemized Description of the Work Base GMP Amount Building Demolition $ 35,000.00 Asbestos Abatement $ 13,750.00 Site Work $ 437,530.00 Storm Piping at Bay Esplanade $ 44,000.00 Landscaping/Irrigation $ 127,000.00 Timber Piles - DELETED $ 0.00 Cast in Place Concrete, Site Concrete, & Unit Masonry $ 1,067,342.00 Mat Foundation MCE Alt #2 $ 228,069.00 Polished Concrete $ 40,065.00 Structural Steel/ Miscellaneous Metals $ 594,660.00 Railings $ 116,880.00 General Works $ 30,000.00 Plastic Laminate Faced Cabinets & Solid Surface $ 131,860.00 Caulking & Sealants $ 20,000.00 T.P.O. Roofmg $ 188,281.00 Doors, Frames and Finish Hardware $ 78,604.00 Overhead Coiling & Sectional Doors $ 182,809.00 Aluminum Entrances/Storefront Glass & Glazing $ 263,700.00 Sunshades $ 55,000.00 Metal Studs, Insulation, GWB, Stucco and Hardie -board $ 522,332.00 Ceramic Tile $ 26,463.00 Acoustical Panel Ceilings $ 22,990.00 Traffic Coating (Included in Painting) $ 0.00 Resilient Base and Flooring $ 14,705.00 Painting $ 57,820.00 Paint Public Restroom Exterior $ 1,500.00 Toilet Accessories $ 7,400.00 Fire Extinguishers & Cabinets $ 1,320.00 Corner Guards $ 2,500.00 Signage $ 27,309.00 Laundry Equipment $ By Owner Residential Appliances $ By Owner T.V.'s and Brackets $ Included in Electrical Lockers $ 10,550.00 Roller Window Shades $ 10,500.00 Floor Mats & Frames $ 2,400.00 February 2, 2022 (Revs) BCC Project #999, COC Project # 18 -0028 -FD Page 11 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 Site Furnishings $ 38,230.00 Metal Shelving $ $2,100.00 Vertical Lift $ 31,500.00 Fire Protection System $ 43,000.00 Plumbing $ 310,000.00 HVAC $ 391,340.00 Electrical $ 921,735.00 Photovoltaic System $ 252,562.00 Electric Vehicle Chargers $ 33,483.00 Structured Cabling for Communications $ Included in Electrical Safety & Security $ By Owner Addressable Fire Alarm $ By Owner Fitness Equipment Relocation Allowance $ 7,500.00 Dedication Plaque Allowance $ 2,500.00 Temporary Utility Consumption Allowance $ 15,000.00 Dewatering Allowance $ 50,000.00 Construction Manager's Contingency (3% of $6,461,289.00) $ 193,839.00 Total Work $ 6,655,128.00 Performance & Payment Bond (.75%) $ 63,000.00 Liability Insurance (.92%) $ 77,280.00 Builder's Risk Insurance $ By owner General Conditions/Requirements $ 164,400.00 Administration and Supervision/ Staffmg $ 591,440.00 City Contingency (5% of $6,461,289.00) $ 323,064.00 Subtotal $ 7,874,312.00 OH&P (6% of $7,753,830.00) $ 472,459.00 Total Guaranteed Maximum Price (GMP) $ 8,346,771.00 February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 12 BIL7'MORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 EXHIBIT E — Construction Schedule Subject to the ASSUMPTIONS AND CLARIFICATIONS contained herein, the anticipated construction period shall be Four Hundred Fifty (450) calendar days to achieve Substantial Completion, after receipt, by Biltmore Construction Co., Inc., of all the following requirements: • Execution of the Guaranteed Maximum Price Amendment of the Agreement Between City and Biltmore Construction Co., Inc. • Receipt of the Written Notice to Proceed. • Receipt of all required Permits. • Recorded Notice of Commencement (as applicable). • Construction site available to commence construction activity. • Existing buildings vacated and ready for asbestos abatement. Final Completion shall be within Forty -Five (45) calendar days following the Date of Substantial Completion of the Work. A preliminary Design Phase and Construction Phase Schedule is included herein. Once the subcontractors are selected, we will prepare a more detailed CPM Schedule that will include all design, permitting, procurement and construction activities. Construction Schedule shall be contingent upon anticipated durations of long -lead items that are out of our control. Actual durations may negatively impact the Schedule requiring an Owner Change Order to include time extension and its' associated costs. These items include, but are not necessarily limited to, Underground Utility Structures, Structural Steel Components, Aluminum Entrances & Storefront, Hollow Metal Doors, Frames, Wood Doors & Hardware, Overhead Coiling Doors, Finish Flooring, HVAC Equipment, Plumbing Fixtures, Major Electrical Components, Light Fixtures and Generator. Once the availability and lead times of the aforementioned items are confirmed, a more detailed CPM Project Schedule will be provided in accordance with the requirements of the Construction Manager at Risk Services. February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 13 BILTVIORE CONSTRUCTION CO., INC. City of Clearwater Fire Station 46 Guaranteed Maximum Price (GMP) Proposal REV #5 EXHIBIT F — Alternate Prices per Specification Section 012300 "Alternates" The following values are inclusive of liability insurance, bond and OH&P. Item Itemized Description of the Work Added Value $ 1 Paint Existing Public Restrooms $ Included in GMP $ 2 Photovoltaic MiSole Peel & Stick System $ Included in GMP $ 3 Big Ass Fans in Apparatus Bay $ 33,666.00 $ 4 3M Bird Friendly UV Film on North, East and West $ 23,427.00 $ 5 Acoustical Flooring $ Deleted by WJA $ 6 Non -Frangible Slab with Wood Piles (M.C.E. Alternate 3) $ 46,700.00 $ 7 Mat Foundation with non -frangible slab (M.C.E. Alternate 2) $ Included in GMP $ 8 E.V. Chargers $ Included in GMP $ 9 Storm Water at Bay Esplanade $ Included in GMP $ 10 Photo -Documentation $ 6,476.00 $ $ $ $ $ $ February 2, 2022 (Revs) BCC Project #999, COC Project #18 -0028 -FD Page 14 BILTVIORE CONSTRUCTION Approved as to form: BILTMORE CONSTRUCTION CO., INC. By: Jeffrey '1'C e Viceresident Date 2-117/LZ CITY OF CLEARWATER, FLORIDA Attest: By:Q'--iiit_ - Q.- Owen Kohler Rosemarie Call Assistant City Attorney City Clerk Countersigned: :-.)- 46-;,.,?. .„(16.--k7 Frank Hibbard Jon P. Jennings g Mayor City Manager Date Date 1055 Ponce de Leon Boulevard — Belleair, Florida 33756 — 727.585.2084 - Fax 727.585.2088