CLEVELAND STREET PHASE III AND FESTIVAL CORE - 16-0003-EN - CHANGE ORDER #2Change Order 2
PROJECT:
Cleveland St Streetscape Phase 3 &
Festival Core
CONTRACTOR:
Gibbs & Register Inc.
232 S Dillard Street
Winter Garden, F134787
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
January 12, 2022
16 -0003 -EN
21000853
May 20, 2021
June 24, 2021
3157541-563800-C2103 A
3197319-563800-C2103 B
3277327-546900-C2103 C
3277327-546900-C2103 D
3277327-546900-C2103 E
3157559-563800-C2105 F
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
decreasing, increasing and adding items to deflect water mains to avoid conflict with storm sewer and provide service
connections to reclaimed water system and add 63 calendar days to the contract -see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - CM
Change Order 2 - City Council 2/3/2022
NEW CONTRACT AMOUNT
Frank Hibbard,
AP�•I ED AS T
wl
en Kohler,
ATTEST:
$ 15,215,742.30
$ 1,209,110.15
S 16,424,852.45
7CagfiA/s4"
Rosemarie Call,
Date: c.2/•�-
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Jon P. Jennings,
Mayor
City Manager
ACCEPTED BY:
B
Joh driguez
Date: % /2
Gibbs & Register Inc.
SEAL
President
)
ZZ
Witnesses:
Recommended By:
City of Clearwater
Catherine Corcoran, Project Manager
Tara PE,
City Engineer
Change Order 2 Cleveland St Streetscape Phase 3 & Festival Core
ITEM
Water Code C:
Decreases:
7002
7007
7010
DESCRIPTION
5/8" WATER SERVICE
8" PVC Water Main
LINE STOP 20"
Increases:
7003 1" WATER SERVICE
7004 2" WATER SERVICE
7006 6" DIP WATER MAIN
7011 LINE STOP 8"
7012 LINE STOP 6"
7013 LINE STOP 4"
7014 8" GATE VALVE
7015 6" GATE VALVE
7018 FITTINGS & APPURTENANCES
7020 FIRE HYDRANT ASSEMBLY
7021 CONTINGENCY
Additions:
7023 1" METER CONNECTION
7024 2" METER CONNECTION
7025 8" DIP Water Main
Reclaimed Water Code D:
Decreases:
8001 4" PVC RECLAIM MAIN
Increases:
8002 1" RECLAIM SERVICE
8007 CONTINGENCY
Additions:
8008 4" DIP RECLAIM MAIN (incl. fittings
& appurtenances)
8009 RECLAIM WATER SERVICES - SAN
JUAN CT
Sewer Code E:
Decreases:
9006 SANITARY SEWER PIPE -10" PVC
9007 SANITARY SEWER PIPE - 8" PVC
Increases:
9010 Contingency
Additions:
9011 SANITARY SEWER PIPE -10" DIP
9012 SANITARY SEWER PIPE 8" DIP
9013 Conflict Box - Cast in Place
UNIT
LF
LF
EA
LF
LF
LF
EA
EA
LF
EA
EA
TN
EA
LS
EA
EA
LF
QTY UNIT COST TOTAL COST
1024.2
530
3
$ 45.00
$ 57.00
$ 20,000.00
Total (Decreases):
$ (46,087.00)
$ (30,210.00)
$ (60,000.00)
$ (136,297.00)
1921 $ 48.00 $ 92,208.00
630 $ 75.00 $ 47,250.00
251 $ 121.00 $ 30,371.00
1 $ 8,500.00 $ 8,500.00
3 $ 8,000.00 $ 24,000.00
1 $ 7,000.00 $ 7,000.00
3 $ 1,700.00 $ 5,100.00
8 $ 1,200.00 $ 9,600.00
4.057 $ 23,000.00 $ 93,311.00
1 $ 6,000.00 $ 6,000.00
0.7186 $ 235,589.11 $ 169,288.50
Total Increases: $ 492,628.50
112 $ 700.00
12 $ 850.00
615 $ 110.00
Total Additions:
$ 78,400.00
$ 10,200.00
$ 67,650.00
$ 156,250.00
Total Net (Decreases)/Increases/Additions Code C: $ 512,581.50
LF 480 $ 35.00 $ (16,800.00)
Total (Decreases): $ (16,800.00)
LF 2600 $ 50.00 $ 130,000.00
LS 1.8 $ 77,220.38 $ 140,865.38
Total Increases: $ 270,865.38
LF 555 $ 215.00 $ 119,325.00
LS 1 $ 85,700.00 $ 85,700.00
Total Additions: $ 205,025.00
Total Net (Decreases)/Increases/Additions Code D: $ 459,090.38
LF
LF
LS
LF
LF
EA
60 $ 70.00
40 $ 66.00
Total (Decreases):
0.80 $
60 $
40 $
8 $
85,578.55 $
Total Increase: $
165.00
155.00
20,000.00
Total Additions:
(4,200.00)
(2,640.00)
(6,840.00)
68,178.27
68,178.27
$ 9,900.00
$ 6,200.00
$ 160,000.00
$ 176,100.00
Total Net (Decreases)/Increases/Additions Code E: $ 237,438.27
Total Net (Decreases)/Increases/Additions to Contract: $ 1,209,110.15