CLEVELAND STREET PHASE III AND FESTIVAL CORE - 16-0003-EN - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1
PROJECT:
Cleveland St Streetscape Phase 3 &
Festival Core
CONTRACTOR:
Gibbs & Register Inc.
232 S Dillard Street
Winter Garden, F134787
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
December 27, 2021
16 -0003 -EN
21000853
May 20, 2021
June 24, 2021
3277327-546900-C2103 C
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
decreasing, increasing and adding items to deflect water mains to avoid conflict with storm sewer.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 15,215,742.30
Admin Change Order 1 - CM approval 12/30/21 $
NEW CONTRACT AMOUNT
$ 15,215,742.30
ACCEPTED BY:
By
Gibbs & Register Inc.
Joh J' odrig z,
Date: 22--
Witnesses:
2Witnesses:
SEAL)
President
Owen Kohler,
ATTEST:
Assistant City Attorney
Rosemarie Call,
Date: 1 /
CITY OF CLEARWATER, in
PINELLAS COUNT FLORIDA
Jon P.nnings,
City Manager
Recommended By:
City of Clearwater
Coltolana
Catherine Corcoran,
7ara Kivett, PE,
Project Manager
Administrative Change Order 1 Cleveland St Streetscape Phase 3 & Festival Core
ITE
Water Code C:
Decreases:
7002 5/8" WATER SERVICE
DESCRIPTION
Increases:
7003 1" WATER SERVICE
7004 2" WATER SERVICE
7006 6" DIP WATER MAIN
7014 8" GATE VALVE
7015 6" GATE VALVE
7018 FITTINGS & APPURTENANCES
UNIT QTY
LF
LF
LF
LF
EA
EA
TN
UNIT COST
2726.8 $ 45.00 $
730 $
470 $
49 $
5 $
4 $
1.443 $
City Engineer
TOTAL COST
Total (Decreases): $
48.00
75.00
121.00
1,700.00
1,200.00
23,000.00
Total Increases:
(122,708.00)
(122,708.00)
$ 35,040.00
$ 35,250.00
$ 5,929.00
$ 8,500.00
$ 4,800.00
$ 33,189.00
$ 122,708.00
Total Net (Decreases)/Increases Code C: $ Q;OO
Total Net (Decreases)/Increases to Contract: $ 0700