MARSHALL STREET NORTHEAST WRF CRACK SEALING - FDEP - 18-0046-UT - ADMINISTRATIVE CHANGE ORDER 1 & FINALCLEARWAT ..R BRIGHT AND BEAUTIFUL • BAY TO BEACH Interoffice Correspondence Sheet To: Micah Maxwell, Interim City Manager From: Tara Kivett, City Engineer CC: Lori Vogel, Procurement Manager; Kayleen Kastel, Budget Manager; Kaylynn Price, Project Manager; Stephanie Sansom, Division Controller; Carrie Szurly, Contracts and Procurement Specialist Date: September 15, 2021 RE: Administrative Change Order 1&Final: Marshall Street & Northeast WRF Crack Sealing (FDEP) (18 -0046 -UT) RECOMMENDED ACTION: Approve Administrative Change Order 1&Final to One Source Restoration & Building Services, Inc., of Tampa, FL, for Marshall Street & Northeast WRF Crack Sealing (FDEP) (18 -0046 -UT) with a decrease of $6,297 for a new contract total of $47,526. BACKGROUND: Administrative Change Order 1&Final decreases and increases items in accordance with field conditions to close the contract. PURCHASING OFFICE AND OFFICE OF MANAGEMENT AND BUDGET DEPARTMENT REVIEW I recommend approval based on the administrative change order criteria: 1. Increases do not exceed 10% of the Council approved amount on a cumulative basis. 2. Change does not change the scope of the project. 3. Price increases do not require additional appropriation to the project. 4. Contract price decreases may be approved without limitation. 5. Completion date is not extended more than 60 days. Lori Vogel Date Administration Change Order 1&Final DATE: PROJECT: PROJECT NUMBER: Marshall Street & Northeast WRF Crack Sealing (FDEP) PO REFERENCE: CONTRACTOR: July 20, 2021 18 -0046 -UT 20001058 One Source Restoration & Building Services, Inc. DATE OF CONTRACT: 7/6/2020 102 S. Armenia Ave. Tampa, FL 33609 CODE: 3277327-546900-96664 SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract due to accelerated structual deterioration from prebid to Notice to Proceed - see attached. STATEMENT OF CONTRACT AMOUNT ACCEP ' D : Y: One . ourc. ' e .toration & Building Services, Inc. ORIGINAL CONTRACT AMOUNT $ 53,823.00 Admin Change Order 1 - City Manager $ (6,297.00) By: "*--- cl.---------- (SEAL) NEW CONTRACT AMOUNT $ 47,526.00 Les Mouzon, Execu;tive Vice President Date: C (z..., ',Da., ATTEST: 41A/LK./ ( 4 Rosemarie Call, Date: CITY OF CLEARWATER, in PINELLAS CO M Assistant City Attorney Clet Maxwell Interim City Manager Witnesses: Recommended By: City of Clearwater ara Kivett, PE, Project Manager City Engineer Page 2 of 2: Administrative Change Order 1 & Final Marshall Street & Northeast WRF Crack Sealing (FDEP) ITEM DESCRIPTION UNIT OTY UNIT COST TOTAL COST Decreases: 3 Shallow Patch Repairs SF 3 $ 168.00 $ (504.00) 4 Deep Patch Repairs SF 15 $ 252.00 $ (3,780.00) 6 10% Contingency LS 1 $ 4,893.00 $ (4,893.00) Total (decreases): $ (9,177.00) Increases: 2 Crack Repair via Injection Grouting LF 48 $ 60.00 $ 2,880.00 Total increases: $ 2,880.00 Total Net (Decreases)/Increases: $ (6,297.00)