GUARANTEED MAXIMUM PRICE - GMP3Imagine Clearwater Guaranteed Maximum Price (GMP 3) Clearwater, FL June 28, 2021 SKANSKA Stantec SKANSKA Table of Contents Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Section 1- GMP 3 Summary • Executive Summary / Project Overview • Guaranteed Maximum Price Summary • GMP 3 Bid Package Breakdown of Direct Cost • Alternates Summary Section 2 - Basis of the Guaranteed Maximum Price • General Qualifications • Allowances • Schedule • Logistics Plan & Laydown SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Executive Summary / Project Overview This GMP 3 is based upon the documents prepared by Stantec, see document log for documents that GMP 3 is based on. Further project scope definition has been developed by Skanska USA Building Inc., and various assumptions that are attached to this proposal. This GMP 3 proposal incorporates the value of all associated construction work as of this date and reflects the decision on scope and quality as they have been decided by the client and NE team. Skanska USA Building Inc. recommends that the attached documents be carefully reviewed; questions and comments be referred back to us for resolution; and the overall project be approved for further progress. Based on the scope of Work, schedule, logistics plan, approved alternates and other content identified or included in the "Basis of GMP 3" section, Skanska hereby proposes a GMP 3 of $55,370,250 to complete such scope of Work for this Project. The Project Schedule upon which the GMP 3 is based is appended to this GMP 3 Proposal. The Project Schedule identifies the schedule milestones and associated completion dates set forth in Table 1-1 for the Project. Table 1-1 Milestone Description Completion Date 1 Issuance of GMP 3 Notice to Proceed July 22, 2021 2 Substantial Completion (Overall Project) May 17, 2023 3 Final Completion (Overall Project) July 16, 2023 This GMP 3 Proposal is valid until August 15, 2021. Page 1 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Guaranteed Maximum Price Summary EXECUTIVE SUMMARY GMP 3 Flatwork & Vertical Construction June 28, 2021 Site (Acres) 24 Direct Cost of Work: Total of All GMP 3 Bid Packages (see page 2 for detail) $ 40,160,801 Owner Accepted Alternates (Direct Cost) $ 4,120,774 Temporary power, water, gas Allowance (3 months) Materials testing and inspection Allowance General Cleanup $ 100,000 $ 250,000 215,000 Total Direct Cost of Work: $ 44,846,575 Contingency: Contractor Construction Contingency 4.00% Owner Construction Contingency Allowance General Conditions 6.00% $ Lump Sum $ 1,793,863 2,690,795 1,750,000 Added General Conditions for Accepted Alternates Insurances & Bonds: 329,662 Sub Bonds/ SDI 1.42% On Cost of Work & Contractor Contingency $ 662,294 Building Permit BY OWNER Misc Permits/Fees (LDP, Tap Fees, Etc.) BY OWNER CCIP 2.58% On Total Construction Cost $ 1,428,552 Builder's Risk BY OWNER Skanska P&P Bond 0.41% $ 226,091 Fee 3.50% On Direct Cost of Work + Lump Sum GCs/GRs $ 1,642,418 Total Construction Cost (GMP 3): $ 55,370,250 Page 2 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 GMP 3 Bid Package Breakdown of Direct Cost Bid Pkg No. 01 General Requirements Ola Final Cleaning Bid Package Description Olb Temporary Fencing (GMP 2) Olc Surveying GMP3 DIRECT COST $102,786 $22,500 $0 $100,000 03a CIP Concrete (Buildings) $2,411,200 03f Concrete Flatwork/Hardscape/Standard Retaining Walls $3,523,536 03g Select Retaining Walls (Gateway, Pond & South Bluff Retaining Walls) $1,019,500 03h Miscellaneous Feature/Amenity Foundations (Shade Structures, Torchiers, etc) 04a Masonry 05a Structural Steel & Misc Steel 05b Ornamental Metals / Railings 05c Decorative Metals for Park Elements 05d Torchiers 06b Millwork / Finish Carpentry 06d Wood Structures (Lake Bridge) 07a Waterproofing & Caulking 07b Roofing 07d Fireproofing 08a Doors / Frames / Hardware 08c Glass & Glazing 08f Overhead Doors 09a Framing Drywall & Stucco 09b Acoustical Ceilings & Wall Panels 09c Tile 09e Resilient Flooring / Carpet 09i Painting & Wallcoverings 10a Toilet Partitions & Bathroom Accessories $148,646 lOb Signage (Interior & Building ID Signage) $32,404 10d Fire Protection Specialties $5,684 log Wall & Door Protection $24,059 $285,000 $475,396 $ 563,611 $291,813 $572,835 $619,548 $254,297 $189,750 $246,847 $335,376 $ 56,838 $242,888 $358,855 $14,114 $1,675,692 $463,420 $261,948 $58,700 $120,409 10h Aluminum Walkway Canopies $109,442 10j Signage (Site Monument & Wayfinding Signage) $194,179 lid Loading Dock Equipment $32,027 lle Playground Equipment $489,348 11f Theater / Stage Equipment $220,590 11J Audience Seating Platforms $73,122 13a Engineered Seating Canopy (Bandshell) $8,872,300 13e Water Features $1,570,821 13f Engineered Shade Structures $304,800 _ 14a Elevators $124,565 21a Fire Sprinkler $103,087 22a Plumbing $1,058,558 23a HVAC $498,800 26a Electrical $6,924,616 3la Earthwork / Grading / Utilities (GMP 2) $243,300 3 lb Deep Foundations $ 1,686,600 31c Wet Utilities (GMP 2) $0 31d CLOMR & Revetment (GMP 2) $0 32a Site Improvements (Fences & Gates) $309,855 32b Asphalt Paving / Curb & Gutter/ Striping & Signage $827,649 32c Landscaping / Irrigation $1,465,077 32d Site Furnishings (Benches, Chairs, Bike Racks, Table Sets, Trash Rec.) $269,613 32e Synthetic Turf $304,800 SUBTOTAL (Direct Cost): $40,160,801 Page 3 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Alternates 01 02A 026 Alternates Summary GMP 3 (Flatwork & Vertical Construction) June 28, 2021 ** Alternate pricing indicated below represents total costs and include direct and indirect cost ***Alternate pricing good until 8/15/21 and reties on a Notice to Proceed by 7/22/21 for pricing to still be valid Alternates: Direct Cost Status OWNER REQ. ALTERNATE 1: Art Wall- Add Art Walls @ N. Bluff (Add Art Walls & Up Lights) 79,086 Accepted OWNER REQ. ALTERNATE 2A: Add Gateway Water Feature (Upper Gateway Plaza -4 Basin Water Feature) - (Cannot be accepted with Alternate 02B) OWNER REQ. ALTERNATE 2B: Add Gateway Water Feature (Full Original Design- 7 Basin Water Feature) w/ Vaults for equipment - (Cannot be accepted with Alternate 02A) $ 430,346 $ 725,620 Accepted 03A SEE PLAYGROUND OPTIONS BELOW 03B SEE PLAYGROUND OPTIONS BELOW 04 05 OWNER REQ. ALTERNATE 4: Add Coachman Garden Trees, Shrubs (w/ Irrigation), Pathways, Site Furniture & 1 Shade Structure $ 220,577 OWNER REQ. ALTERNATE 5: Add (4 EA) "Bamboo Trees" Water Features (Model VOR 7725) @ Splashpad (Assumes use of same pump as IWF- no separate pump) $ 83,895 06A SEE PLAYGROUND OPTIONS BELOW 06B SEE PLAYGROUND OPTIONS BELOW 06C SEE PLAYGROUND OPTIONS BELOW 07A 07B OWNER REQ. ALTERNATE 7A: Add Picnic Pavillions and associated furniture (This option includes lighting as indicated on plans but no solar) $ 177,121 OWNER REQ. ALTERNATE 7B: Add Poligon Solar Lighting System © the Picnic Pavilions (Stand-alone solar panel by $ Poligon. Does NOT indude equipment for distribution of power back to the grid) 8,000 08 NOT USED 09 NOT USED Accepted Accepted Accepted Accepted 10 OWNER REQ. ALTERNATE 10: Theatrical Luminaires Package (Provide a price to provide the Theatrical Luminaires $ 396,586 Accepted Package as outlined in Section 11 61 53 Theatrical Luminaires and Accessories. 11A OWNER REQ. ALTERNATE 11: DEDUCT Alternate to delete 2 EA Torchiers reducing the Torchiers count from 5 ea $ (208,419) to 3 ea - (Cannot be accepted with Alternate 11B) 11B DEDUCT VE ALTERNATE 11B: Change from stainless steel to Aluminum Torchier Cladding - Credit is based on 5 $ (115,699) Torchiers- (Cannot be accepted with Alternate 11A) DEDUCT VE ALTERNATE 12: Deduct to eliminate the custom form -liners at the Gateway Plaza North, South and $ (240000) Accepted West Retaining walls 13 NOT USED 14 ADD ALTERNATE 14: Third party testing company to perform monitoring/ reporting during roof installation per $ 20,000 specification section 07 5423 paragraph 3.9 A 15 DEDUCT VE ALTERNATE 15: Provide 60 MIL TPO roofing membrane w/ 20 year warranty ilo 80 MIL $ (7,354) 16A ADD ALTERNATE 16A: Provide G90 Galvannealed HM Frames and Door Slabs on all doors (better for coastal $ 13,357 Accepted environments)- Can be accepted with 16B or 16C but not both. 1613 ADD ALTERNATE 1613: Graintech factory finish doors in place of painted finish (Does not include STC Rated Doors $ 19,569 which are not available in Graintech finish) - Cannot be accepted with Alt. 16C 16C ADD ALTERNATE 16C: Provide factory pre -finished Doors in Standard Color in place of field painted finish - $ 2,410 Cannot be accepted with Alt. 1613 17 DEDUCT ALTERNATE 17: Provide galvanized ramp rails at Audience Seating Platform ramps in place of aluminum $ (27,450) Accepted (Requested per RFI No. 146) 18 ADD ALTERNATE 18: Bandshell Canopy Steel to be AESS (Including Mockups) in accordance with RFI Nos. 46 & 153 $ 46,000 (Provides Grade III AESS Steel from 0'-0" - 20'-0" and Grade I from 20'-0" and above at columns only) 19 ADD ALTERNATE 19: Provide Bandshell Canopy with 80-85% PTFE Membrane ilo 67-70% (Base Bid) $ 181,000 Page 4 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 20 ADD ALTERNATE 20: Provide Coal Tar Epoxy Coating at the Micropile casings as indicated in Specification in place $ 530,000 of the 1/16" added sacrificial wall thickness at steel casing 21 DEDUCT ALTERNATE 21: Provide tension test only ilo compression test for the Micropiles $ (10,000) Accepted 22A DEDUCT VE ALTERNATE 22A: Micropiles -VE option 1 reduce pile diameter based on engineering efficiencies by $ (320,000) pile contractor - (Cannot Be accepted if 22B is accepted) 226 DEDUCT VE ALTERNATE 22B: Micropiles - VE option 2 revised pile layout/ quantities based on engineering $ (520,000) Accepted efficiencies by pile contractor - (Cannot be accepted if 22A is accepted) 23 ADD ALTERNATE 23: Provide 1 year Landscape maintenance after substantial completion. (This is a direct option $ 230,736 for the Owner. This work will not be contracted through Skanska). 24 ADD ALTERNATE 24: Add to provide additional soil amendment for groundcover areas only (to comply with detail $ 29,430 10/LP-501) 25 ADD ALTERNATE 25: Add to provide additional soil amendment for shrub areas only (to comply with detail 10/LP- $ 321,238 501) 26 ADD ALTERNATE 26: Add to provide 8" Depth of 80/20 mix soil for use under the Bermuda Sod at the Green $ 311,590 27 ADD ALTERNATE 27: Upgrade turf for Bandshell and Bluff Walk North to DuPont ForeverLawn Select HD (w/ 15 $ 52,000 yr. warranty) in place of ForeverLawn Xerigrass CL58 (w/ 8 yr warranty) 28 29 30 31 ADD ALTERNATE 28: Add 5 Shade Structures by Birdair (Quasar) $ 242,500 ADD ALTERNATE 29: Add ALLOWANCE for Solar Panels @ Buildings (Bandshell, Event RR, IWF RR, Dockmaster, Picnic North & Picnic South) $ 250,000 ADD ALTERNATE 30: Add ALLOWANCE for Moveable Seating $ 1,300,000 ADD ALTERNATE 31: Add ALLOWANCE for INSTALLATION ONLY of Underground trash receptacles (Allowance provided by CoC based on 7 pair Trash/Recycle). Trash / Recycling receptacle and precast box to be furnished by $ 650,000 City of Clearwater for installation by Skanska. 32 ADD ALTERNATE 32: Deduct to provide alternate manufacturer (Roman Fountain) for fountain equipment (in place of Crystal Fountains) $ (247,700) PLAYGROUND OPTIONS Base Bid Playground Layout and Surfacing (LH -208A): Landscape Structures in place of Kompan DEDUCT VE ALTERNATE 613: Provide alternate playground design by Landsacape Structures in similar 'Ship 06B Theme" BASE BID LAYOUT in place of Kompan Base Bid Layout - (Cannot be accepted if Alternate 3A, 38, 6A or $ (94,596) 6C is accepted) Base Bid Playground Layout w/ Alternate Surfadng (LH -208A): Rubber Surfacing in place of Eng. Mulch 03A OWNER REQ. ALTERNATE 3A: Rubber Safety Surfacing in place of Engineered Mulch @ Playground (Base Bid $ 123,865 Layout)- BASED ON KOMPAN PRICING - (Cannot be accepted concurrently with Alternates 6A, 6B or 6C). OWNER REQ. ALTERNATE 36: Rubber Safety Surfacing in place of Engineered Mulch @ Playground (Base Bid 038 Layout) - BASED ON LANDSCAPE STRUCTURES PRICING - (Cannot be accepted concurrently with Alternate 6A, 68 $ 120,335 or 6C). Accepted Accepted Accepted Accepted Alternate Playground Layout & Surfacing (LH -208B): Enhanced playground w/ Rubber, Synthetic & Sand 06A OWNER REQ. ALTERNATE 6A: Add for Alternate Playground Layout per LH -208B (More Equipment w/ Revised $ 771,482 Accepted Surfacing as shown)- BASED ON KOMPAN PRICING - (Cannot be accepted if Alternate 3A, 38, 6B or 6C is accepted) ADD ALTERNATE 6C: Provide alternate playground design by Landsacape Structures in similar "Ship Theme" 06C ALTERNATE LAYOUT (LH -208B) - BASED ON LANDSCAPE STRUCTURES PRICING - (Cannot be accepted if $ 670,994 Alternate 3A, 3B, 6A or 613 is accepted) Total Accepted Alternates (Direct Cost): $ 4,120,774 Page 5 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 This section of the Guaranteed Maximum Price Proposal describes exclusions, assumptions, and clarifications. For those items that are identified as excluded, no cost or time has been accounted for in the GMP 3 to address the issue. For those items that are clarified, qualified or based on an assumption, the GMP 3 reflects only the cost and time of the element as assumed or clarified. Any differences to the following exclusions, clarifications and/or assumptions will result in a change to the GMP 3. Cost Basis of GMP 3: Flatwork and Vertical Construction Skanska USA's GMP 3 Flatwork and Vertical Construction Proposal is based upon the following: 1. Plans, specifications, and RFI responses 2. Skanska USA's Guaranteed Maximum Price Proposal (dated June 28, 2021) 3. The Project Agreement dated December 19, 2019 4. These Exclusions, Qualifications and Assumptions 5. The following documents: a. The Package Specific Assumptions and Clarifications dated June 28, 2021 b. Document Log dated June 28, 2021 c. Owner, Contractor Responsibility Matrix dated June 28, 2021 d. Project Schedule with Data Date June 10, 2021 e. Bid Documents for GMP 3 dated March 29, 2021 as amended by Addendums 1-4 included in Document Log referenced in item B above Changes or revisions to the foregoing information will result in a modification to the GMP 3 and require modifications to the Overall Project Schedule. Documents, communications and information not included in the foregoing list, including for instance, any third -party agreements are not accounted for in the GMP 3 Proposal. As such, the Owner must carefully review all of the criteria used to develop this GMP 3 Proposal and request any revisions to the same, so that a modified GMP 3 proposal can be prepared. Page 6 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 General Qualifications 1. GMP 1 (Enabling Work) and GMP 2 (Sitework, Earthwork, Utilities & CLOMR wall & Revetment) is not included in this GMP 3. For the total project scope value covered by GMP's you would add GMP1, GMP 2 and this GMP 3. All GMP 1 and GMP 2 qualifications and assumptions remain. 2. The GMP 3 is based upon materials with color and configuration from the manufacturer's standard selections, unless specifically noted otherwise in this document. 3. Use of union labor/prevailing wage is not mandatory and has not been considered in this GMP 3. 4. The GMP 3 does not include the cost of a professional engineer's stamp on any subcontractor's or vendor's shop/fabrication drawings. Where contract documents require that design information be provided by the Construction Manager, design information (including calculations and certifications) will be provided by trade contractors. The Construction Manager will rely on the trade contractor's in so doing. The Guaranteed Maximum Price does not include any costs and expenses to conduct an independent review of such design information, and does not include costs and expenses resulting from any deficiencies or inaccuracies in these calculations or certifications. 5. GMP 3 does not include any costs associated with reviews, design changes or delays by insurance underwriters such as IRI or FM. Labor, materials and equipment, and the related cost thereof, and impacts to the Project Schedule arising from or in connection with, inspections or requirements imposed by Factory Mutual or similar insurance underwriters, and not expressly set forth in the Drawings and Specifications, are excluded. 6. Sales tax on materials is included. 7. GMP 3 proposal assumes unfettered legal access to the project site at all times, limited to areas identified on the Project Logistics Plan. 8. GMP 3 excludes costs and/or schedule implications related to handling, removing, and/or abating any hazardous materials (including but not limited to, asbestos, lead, petrochemicals, etc). 9. GMP 3 excludes costs and/or schedule implications related to handling, removing, and/or abating any contaminated ground water or unsuitable soils. Skanska will stockpile any unsuitable materials associated with our work for handling and removal by the City of Clearwater. Page 7 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 10. During GMP 1 Skanska and Owner through its Architect -Engineer performed some limited site investigation. This included potholing exiting utilities shown on the Contract Drawings when installing the Enabling Conduit Work. By way of example the following investigations were conducted: a) Stantec potholing and physically locating in horizontal and vertical elevations the existing utilities shown on drawings to discover that they are conflict with the IWF location as shown on the documents. Stantec is currently modifying the IWF design to accommodate located existing utilities. b) Potholing to locate existing subaqueous water force main near the Boathouse that was found to not be located as indicated on the drawings. c) Skanska located an unforeseen storm sewer conflict structure next to Duke manhole #22, (currently not indicated on the documents) while installing the Duke Energy Conduits. Skanska coordinated a no cost resolution that Duke Energy is implementing. d) While installing the Duke energy conduit at the South Bluff Skanska located an existing unforeseen sanitary line. This line will be in direct conflict with the current design. Stantec will need to provide a new sketch showing the rerouting of this lateral, Skanska has carried an allowance to account for resolving this unforeseen condition. Additional utility investigations will be performed as to identify the actual location of existing utilities shown on the documents. The work required to locate these utilities is within GMP 2. However, if existing utilities shown in the documents are found in significantly different locations and / or if unforeseen / unknown utilities are discovered and the unforeseen conditions impact installation of new Work, the cost of any work required to address the unforeseen condition is not included in GMP 2 or this GMP 3. Note 8 on C-001 is excluded. GMP 2 and this GMP 3 excludes costs and/or schedule implications related to any unforeseen conditions. 11. GMP 3 does not include construction activities outside of the defined project limits. 12. No costs have been included for materials testing and / or inspections except as noted below. No testing or inspections anticipated with the exception of compaction of soils, load testing of micropile test piles, micropiles, concrete, masonry, steel, fireproofing, low voltage conductive testing of TPO roofing. Threshold inspections are excluded and are to be completed by the City of Clearwater. 13. Refer to Owner -Contractor Responsibility Matrix for additional clarifications as it relates to the scope of work included within the GMP 3. 14. A phased construction schedule is not included for GMP 3. GMP 3 assumes that the Work can happen without interruption. Page 8 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Constniction June 28, 2021 15. This is not a LEED project. Cost to meet LEED requirements that may be included in the specifications are not included in GMP 3. 16. The GMP 3 assumes participation in the Owner's Direct Purchase (ODP) program given timely approvals are provided to allow release of materials per scheduled completion. Should approval of the Owner Direct Purchase delay release of materials, it will require a schedule extension at additional cost to the Project. Upon reconciliation of all purchase order amounts, a final change order may be executed to finalize the amounts for all Subcontractor deductions and sales tax savings. Following reconciliation, any unspent material costs remaining in the Owner's purchase order will be returned to the Contractor by a Change Order. 17. Neither the GMP 3 nor the project schedule upon which GMP 3 is based contemplate any project delays, suspensions, disruptions, cost escalations or other impacts caused, directly or indirectly, by the coronavirus disease, or any other epidemic or pandemic or any resulting government action. 18. This GMP 3 Proposal is valid until August 15, 2021 but subject to cost and schedule adjustments if the Notice to Proceed is delayed, as discussed in paragraph 23. If Owner does not accept this GMP 3 Proposal within such validity period, Skanska reserves the right to further adjust the GMP 3 and Project Schedule to account for changes in market and other conditions that impact cost and/or the Project Schedule. 19. For those items that are excluded, no cost or time has been included in this GMP 3 Proposal to account for such items. For those items that are clarified, qualified or based on an assumption, this GMP 3 Proposal reflects only the cost and time associated with the items as assumed, qualified or clarified. All content in this Section 2 is intended to more clearly define and/or limit Skanska's scope of responsibility under the Contract regardless of whether or not any specific sub -item in this Section 2 may not use terms such as "assume", "qualify", "clarify" or similar terms or derivations thereof. 20. Changes to or deviations from any aspect of the Basis of GMP 3 Documents that impact cost and/or schedule may entitle Skanska to a change order, subject to its compliance with the notice provisions within the Agreement, equitably adjusting the GMP 3 and/or Project Schedule. 21. Documents, third -party agreements, commitments to third parties, design criteria and any other information not expressly included in the Basis of GMP 3 Documents are all excluded. Page 9 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 22. Coordination with Others. This GMP 3 Proposal is based on the assumption that the members of the Design Team and Owner's other contractors and personnel performing work or services in connection with the Project will: a) Comply with Skanska's site-specific safety program and maintain an injury free environment when work or services are performed at the Project site. b) Perform work and services, including without limitation installation of Owner - furnished equipment and materials and issuing timely responses to RFIs and submittals, in accordance with the Project Schedule (as such schedule may be amended from time -to -time). c) Perform work and services so as to not impact Skanska's ability to perform its Work in accordance with the Logistics Plan. d) Perform work and services (including inspections), so as to not impact Skanska's ability to maintain or accelerate the Work under the Project Schedule. e) Provide detailed schedule, logistics, and technical information when and as requested by Skanska so as to enable Skanska to timely coordinate interfaces with the Design Team and other contractors and to maintain or accelerate elements of the Project Schedule so as to achieve necessary progress and milestone completion dates. f) Be solely responsible for coordinating rough -ins to be provided by Skanska and for making final connections of all Owner -furnished equipment to the rough -ins provided by Skanska. 23. Notice to Proceed. This GMP 3 Proposal is based on the assumption that Owner will issue a notice to proceed ("NTP") (with all conditions precedent identified below, if any, satisfied) on or before July 22, 2021 ("Notice to Proceed Date") and that Substantial Completion will be achieved on or before May 17, 2023, as such duration may be modified in accordance with the Contract. If Owner has not issued an effective NTP by the Notice to Proceed Date, Skanska shall have no obligation to commence any part of the Work, until Skanska and Owner: (a) reach agreement on the scope and nature of equitable adjustment to GMP 3 and Project Schedule, including full compensation to Skanska and its Subcontractors and Sub -subcontractors for the delay in issuing NTP and; (b) Owner satisfies all conditions precedent to the effectiveness of the NTP set forth below. 1) Applicable Permits must be issued 2) All permit Fees Paid 3) Owners Builders Risk Policy must be in place as reviewed & agreed to by Skanska 4) GMP Amendment or Purchase Order issued and fully executed Page 10 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 24. Contingency. An Owner contingency allowance of $2,690,795 has been included in GMP 3 to address issues such as, by way of example and not limitation, Design Team's completion of design, enlarging the size of the Project, unforeseen conditions, comments from authorities having jurisdiction, commodity and/or material price escalation, modifications to or acceleration of the Project Schedule, increased quality or quantity of Project components not currently reflected in the Drawings or Specifications, or other conditions/circumstances for which Skanska would be entitled to a Change Order under the Contract. In preparing this GMP 3 Proposal, Skanska included a contractor contingency in the amount of $1,793,863 for Skanska's exclusive use (hereinafter the "Construction Contingency") to cover those costs considered reimbursable as the Cost of the Work but not included in a Change Order. Construction Contingency shall be available for Skanska's exclusive use at any time, including at the time of final payment, for reimbursement of costs and expenses: (1) reasonably incurred by Skanska in performing the Work, (2) of a type that are reimbursable under the Contract as a Cost of the Work, and (3) that are not otherwise the basis for a Change Order (it being understood that the Construction Contingency shall not be used to fund any Work which would otherwise be subject to a Change Order); including, by way of example, but not limited to, (a) Work items inadvertently omitted during the estimating and bidding process, (b) schedule recovery costs, (c) cost increases due to unanticipated local labor and material market conditions, (d) interfacing omissions between and from the various categories of Work; (e) additional costs incurred due to the withdrawal or disqualification of a Subcontractor bid forming the basis for the GMP 3 prior to signing of a written subcontract, and (f) excess Subcontractor completion costs arising from Subcontractor default. Skanska shall furnish to Owner a monthly Contingency Log showing all reimbursements from the Construction Contingency. This is not a Line item GMP. The Construction Contingency shall be increased automatically by the net savings, if any, realized through subcontract and/or purchase order buyout or due to other under runs against the various amounts and allowances that compose the overall GMP 3. Any amount remaining in the Construction Contingency at final payment shall be counted as savings for purposes of determining any shared savings, if applicable. 25. Retainage is included at 5% in GMP 3 through Project Substantial Completion at which time a reduction to 2.5% is expected. 26. Confirmation by the Engineer that all or part of the Work is Substantially Complete shall establish the start of the Warranty/Correction Period and will be final acceptance of the Work for the purpose of warranty and maintenance obligations as the Owner will take possession of the Project at that time. Page 11 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 27. GMP 3 includes a Fee of 3.5% on the Direct Cost of Work plus lump sum GC's / GR's. This includes all costs of any ODP credits that goes back to the Owner to facilitate sales tax savings. No fee is calculated on top of insurances & bonds. Fee to be charged on contingency only when contingency is utilized and will be taken out of contingency at that time. Fee Markup on Add Changes to the Work is qualified in GMP 3 to be: 1. For Labor - 15% broken down as follows - 10% to self -performing subcontractors and 5% to the contractor 2. For Materials - 10% by subcontractor and 5% to the contractor 28. The Contractor General Conditions / General Requirements are based on a Lump Sum Basis in GMP 3 to be billed equally monthly for the duration of the project. 29. Escalation. Skanska has not included any contingency to account for price escalation resulting from any change in law or tariffs that may be enacted by a governing body. The proposed GMP 3 excludes any additional cost resulting from price escalation arising out of a change of law or tariff. The Guaranteed Maximum Price (GMP 3) assumes a Notice to Proceed of July 22, 2021 and the Guaranteed Maximum Price Proposal as submitted is good until August 15, 2021. 30. This GMP 3 Proposal is based on the assumption that materials and equipment are from the applicable suppliers/manufacturer's standard selections and configurations, unless expressly noted otherwise in the Drawings or Specifications. 31. Sole -Sourcing. All Project components and third -party services to be furnished by Skanska are assumed to be nonproprietary and available from multiple sources. In the event of any component or third -party service is specified on a sole -source basis, this GMP 3 Proposal assumes that Skanska's liability arising out of the performance by the sole -source subcontractor or supplier shall be limited to and in no event exceed the liability assumed by any such sole -source subcontractor or supplier in connection with the Project. 32. Specified Performance Criteria. Any manufacturers referenced in the Specifications are for basis of design only and shall not preclude Skanska from offering an "or equal" manufacturer. If the Design Team specifies "performance criteria" for any components to be included in the Project, Skanska assumes that the named component manufacturer(s) are deemed to comply with all specified performance criteria and that Skanska shall only be obligated to demonstrate that a proposed "or equal" component complies with the specified performance criteria. Page 12 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 33. Special warranties, certifications and other requirements that exceed manufacturer standard warranties, and implied warranties, are all excluded except to the extent expressly specified in the Contract Documents. 34. All warranties included in the Contract Documents that survive beyond Skanska's one year repair/replacement obligation time period set forth in the Contract shall be assigned to Owner following the expiration of such one year time period. Thereafter, Skanska's sole obligation and Owner's exclusive remedy shall be for Skanska to reasonably assist the Owner in enforcing such warranties provided by Subcontractors. 35. If contractual terms and conditions are included in the Division 1 specifications or other sections of the Specifications provided by the Design Team, such terms and conditions shall be inapplicable and only the terms and conditions set forth in the Contract and/or this GMP 3 Proposal shall apply. Skanska GMP 3 specifically excludes all Division 1 specifications issued by the Design Team. 36. This GMP 3 Proposal is based on the assumption that the Drawings and Specifications prepared by the Design Team comply in all respects with all applicable building code requirements, applicable laws, and the programming, aesthetic, quality and other Project requirements prescribed by Owner orally or in its existing standards, guidelines or Project -specific documents as well as City development standards and codes such as by example, the Downtown Development Code. 37. All Owner -furnished material and equipment, and any related required submittals and/or design information, shall be furnished and installed by or on behalf of Owner in accordance with the Project Schedule. As part of its obligations, Owner shall provide detailed design, location, dimension, sizing and other technical information detailing all required rough -in and final connections to the Owner - furnished equipment. All Owner -furnished equipment and final connections shall be coordinated to the rough -ins provided by Skanska. 38. This GMP 3 Proposal is based on the assumption that "time is of the essence" or similar provisions in the Contract, if any, shall only apply to Substantial Completion of all Work and/or specified milestone dates mutually agreed upon by Owner and Skanska in GMP 3 Section 1 Table 1-1. 39. This GMP 3 Proposal is based on the assumption that, outside of City ordinances, (i) there are no applicable limits, restrictions or constraints on work hours, noise generation and/or vibration generation with respect to Skanska's performance of the Work on the Project site, and (ii) only customary limits, restrictions and constraints consistent with industry standards apply. 40. This GMP 3 Proposal excludes costs and/or schedule impacts arising from or in any way related to (i) handling, removing, and/or abating any hazardous wastes/materials, (ii) handling, removing, and/or abating any contaminated groundwater, and (iii) any unforeseen conditions at the Project site or in connection with the performance of the Work. If hazardous or contaminated materials are identified during construction Skanska will notify Owner immediately for Owner's investigation, survey and determination of plan for handling and removal by the City of Clearwater. Page 13 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 41. Contractor Controlled Insurance Program. Skanska will furnish and directly or indirectly administer a Contractor Controlled Insurance Program ("CCIP") providing for General Liability, Worker's Compensation and Excess/Umbrella coverage required to be furnished by Skanska and its Subcontractors and Sub -subcontractors under the Contract. The CCIP shall only cover and apply to on-site exposures for participants enrolled in the CCIP. Invoicing by Skanska for furnishing the CCIP will be as set forth below. The cost of CCIP will be added to all Change Orders though final completion. Skanska and all Subcontractors and Sub -subcontractors that perform any part of the Work on the Project site are expected to be covered, excluding Subcontractors/Sub-subcontractors performing or supplying architectural or engineering services, waste management/hauling services, temporary toilets, field offices and related incidental services/supplies, surveying, materials testing, elevators, structural demolition and/or abatement, if any. Owner's separate contractors and the Design Team and other professionals of any tier retained by the Owner or Design Team shall not be enrolled in or covered by the CCIP. The Owner is required to obtain insurance similar in scope and coverage limits as required from Skanska from those unenrolled/uncovered parties and to require from those parties that Skanska is listed as an Additional Insured on all of applicable policies. 42. Invoicing for Insurance and Bonds. Premiums for insurance and bonds are part of the Cost of the Work and shall be paid by Owner to Skanska as set forth below. The entire estimated value of all such insurance and bond costs shall be included in and paid by Owner as part of Skanska's first monthly Application for Payment after execution of the GMP 3 Amendment and after execution of each Change Order increasing such insurance and bond costs. Premium for Bonds and Insurance. Premiums for bonds and insurance will be provided at the rates specified in this section. Owner acknowledges that all specified rates have all been negotiated, will be charged by Skanska under the Contract and are auditable only to determine the proper application of the rates under the Contract and not the composition of such rates. 1) Subcontractor Default Insurance ("SDI") at the rate of 1.42% multiplied by the actual Cost of the Work & Contingency. 2) Subcontractor Performance and Payment Bonds at actual cost invoiced by Subcontractor's surety for Subcontractors that do not prequalify for enrollment in SDI. 3) Contractor Controlled Insurance Program ("CCIP") at the rate of 2.58% multiplied by the approved GMP 3 amount. Thereafter the CCIP rate will be added to and included in the cost of any Change Orders that increase the value of the GMP 3. 43. Skanska Performance and Payment Bonds (P & P Bonds) at the rate of .41% multiplied by the approved GMP 3 amount. Thereafter the P&P Bonds rate will be added to and included in the cost of any Change Orders that increase the value of the GMP 3. Page 14 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 44. Review of Skanska Insurance Policies. Skanska assumes that the furnishing of a Certificate of Insurance will demonstrate that Skanska has obtained insurance compliant with its obligations under the Contract. This insurance is provided through the Skanska's proprietary corporate insurance program and if Owner wants to review such insurance policies, Skanska will afford the Owner an opportunity to do so at a time and place mutually agreed upon with Skanska's Vice President, Insurance and Surety. If Owner requires Skanska to furnish a copy of any such policy, to avoid disclosure of proprietary information Skanska must purchase a Project -specific policy at additional cost that excluded from the GMP 3. 45. Owner Direct Purchase Program. Skanska acknowledges that Owner is implementing a direct purchase program pursuant to Florida Statute Section 212.08(6) to avoid sales tax on materials incorporated into the Project (the "ODP Program"). Owner acknowledges and agrees that (i) all deductive change orders issued by Skanska to its Subcontractors participating in the ODP Program and corresponding deductive Change Orders issued by Owner to Skanska under the ODP Program (collectively the "ODP Change Orders") include the costs of materials and the applicable Florida state sales tax, (ii) the value of the ODP Change Orders will be based on estimated quantities and costs, except when the ODP Change Order expressly involves the purchase of a single item with a predetermined fixed value, and (iii) the actual costs incurred for materials under the ODP Program will be reconciled with the estimated costs and if the aggregate cost actually incurred by Owner to purchase the materials is less than the value of the ODP Change Order minus applicable sales tax (the "Underrun"), then Owner will issue to Skanska an additive Change Order in the amount of the Underrun plus the applicable sales tax on such Underrun value, and Skanska will issue a corresponding additive change order to the applicable Subcontractor. Table 2-3 presents an illustration of the foregoing calculation. Skanska reserves the right to exclude participation in the direct material purchase program in order to mitigate escalation premiums beyond August 15, 2021. Table 2-3 ODP Additive Change Order Illustration Descnpban of Purchase Pretax Value 6% Saks Tax Deductive ODP Change Order Value Final Value of Purchase Pretax Value of Underrun 6% Tax on Underrun Additive Reconciliation Change Oar Value Paint $100,000 $6000 $106,000 S75.000 $5,000 $1,500 $26,500 46. General Conditions Section 6.5 - Skanska wishes to clarify its understanding that the indemnification requirements of this section applies to third party claims of adjacent property owners or occupants. 47. General Conditions Section 6.6 - the GMP 3 Proposal is submitted based on the understanding that this section does not apply to material or equipment specified by the design, unless Skanska or the subs knew or should have known of the obligation to purchase a license. Page 15 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 48. GMP 3 (Flatwork and Vertical Construction) is based on and includes the following additional documents: 1) The Package Specific Assumptions and Clarifications dated June 28, 2021 2) Document Log dated June 28, 2021 3) Owner, Contractor Responsibility Matrix (Site Work) dated June 28, 2021 4) Site Work Schedule with Data Date June 10, 2021 5) Bid Documents for Site Work dated March 29, 2021 and as amended by Addendum 1-4 49. GMP 3 excludes any site security beyond the temporary fencing and gates. 50. GMP 3 does not anticipate any conflicts between the Work and any existing seawall tie backs or deadmen as the design does not indicate any as existing and has not anticipated any on the documents. 51. GMP 3 excludes any project webcam. 52. Alternate pricing is good until August 15, 2021 and relies on a Notice to Proceed by July 22, 2021. 53. Skanska has included an allowance for materials testing to be used for (GMP 3 Limited Scope) and includes the following (excludes threshold testing and inspections): 1) Soil Compaction 2) Deep Foundations 3) Concrete 4) Masonry 5) Steel 6) Fireproofing 54. The buyout of bid packages will be performed in compliance with the Contract with the understanding that Skanska will conduct post -bid interviews and that all bids will be reviewed and leveled by Skanska before the lowest responsive proposal is accepted. Page 16 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 55. GMP 3 does not account for permit set drawing changes unless those changes were clouded and labeled on the sheets with the Addendum Nos. 3 & 4 tag with a revision Date. GMP 3 includes allowances for costs associated with multiple issuances of the permit drawings that were received by Skanska after the bid date and prior to GMP 3 delivery. Due to the quantity of drawings received with no breakout for only revised Addendum 4 documents, and permit drawings being issued in multiple revisions / deliveries Skanska has assigned allowances to cover costs that have been identified associated with Addendum 4 documents that were received and identified too late in the process to be priced by bidders prior to GMP 3 assembly. Skanska has reconciled the drawings received from Stantec and identified those drawings that we believe represent changes captured in Addendum 4 and those final costs will be reconciled. A final reconciliation of those costs associated with Addendum 4 documents is in process and will be an adjustment to the Owner Allowance. 56. GMP 3 includes an allowance for amphitheater seating below canopy per accepted Alternate No. 30. 57. GMP 3 includes an allowance for solar panels at the buildings as per accepted Alternate No. 29. 58. GMP 3 excludes permit review comment changes and potential impacts. 59. GMP 3 excludes Addendum 5 sheets provided for permit review comments prior to formal issuance of Addendum 5. 60. GMP 3 assumes payment for stored materials on and off-site will be made, pricing is contingent on payment of stored materials. GMP 3 anticipates monthly progress billings for delegated design engineering. 61. GMP 3 assumes that Skanska will be able to bill for deposit payments for material including but not limited to: • Mill Order Steel and Fabrication • Playground Equipment & Surfacing • Elevators • Theater Stage Equipment • Picnic Pavilions (if incorporated via accepted alternate) Page 17 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Allowances Cost allowances have been established for certain items, as outlined below. These allowances are intended to provide compensation for all direct costs associated with each of these items including, without limitation, materials, equipment, labor, taxes, fees, etc. 1. Secondary concrete pour @ Bandshell curved stair to the rooftop terrace (03A) $ 20,000 2. Early purchase & storage of reinforcing steel & formwork material (03A) $ 20,000 3. Early purchase & storage of reinforcing steel & formwork material (03G) $ 35,000 4. New Artwork foundations (Item 9.9 from Hardscape Plans) (03H) $ 15,000 5. Anticipated escalation allowance to hold masonry rebar pricing up to 8/25/21 (04A) $ 3,300 6. Anticipated escalation allowance to hold structural steel pricing up to 8/25/21 (05A) $ 65,000 7. Barn Door & Hardware (05C) $ 73,168 8. Anticipated escalation allowance to hold decorative metals pricing up to 8/25/21 (05C) $ 40,188 9. Anticipated escalation allowance to hold torchiers pricing up to 8/25/21 (05D) $ 46,700 10. Anticipated escalation allowance to hold waterproofing & caulking materials pricing up to 8/25/21(07A) $ 3,300 11. Early purchase & storage of roofing materials (07B) $ 8,400 12. Early purchase & storage of hollow metal door materials (08A) $ 3,000 13. Allowance for 3rd Party Inspections of Door & Frame assemblies per 08 11 13 (08A) $ 3,500 14. Anticipated escalation allowance to hold glass systems pricing up to 8/25/21 (08C) $ 31,219 15. Anticipated escalation allowance to hold overhead doors pricing up to 8/25/21 (08F) $ 500 16. Anticipated escalation allowance to hold drywall & framing pricing up to 8/25/21 (09A)$ 25,000 17. Mechanical equipment enclosure & louvers @ Bandshell (09B) $ 149,385 18. Anticipated escalation allowance to hold tile pricing up to 8/25/21 (09C) $ 15,000 19. Anticipated escalation allowance to hold carpet & resilient pricing up to 8/25/21 (09E) $ 7,000 20. Anticipated escalation allowance to hold signage pricing up to 8/25/21 (10B) $ 2,200 Page 18 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 21. Anticipated escalation allowance to hold aluminum walkway canopy pricing up to 8/25/21(10H) $ 8,700 22. Anticipated escalation allowance to hold monument & wayfinding sign pricing up to 8/25/21(10J) $ 27,181 23. Anticipated escalation allowance to hold loading dock equipment pricing up to 8/25/21(11D) $ 2,800 24. Anticipated escalation allowance to hold theater rigging & curtains pricing up to 8/25/21(11F) $ 28,100 25. Fiberglass Reinforced Plaster Grate (Item 1.6B) @ IWF (Addendum 4 revs) (13E) $ 15,000 26. Anticipated escalation allowance to hold HVAC pricing up to 8/25/21 (23A) $ 22,400 27. Allowance for security camera infrastructure (26A) $ 75,000 28. Cove lights, linear wall washers & RGBW film lights in the Bandshell Multipurpose Room (26A) $ 30,000 29. LED Light Sheet at the Bandshell Multipurpose Room (26A) $ 15,000 30. Two (2) conduits with multi -mode fiber cable to each Wayfinding sign 1 (26A) $ 100,000 31. Post mounted receptacles at vendor tents (per addendum 4 revisions) (26A) $ 15,000 32. CRP, PV and EP theatrical box/conduit (26A) $ 93,194 33. AV Allowance (26A) $ 1,000,000 34. Additional tree barricades and root pruning (per addendum 4 revisions) (31A) $ 25,000 35. Allowance for revised site fences and gates including eliminated chain-link fencing (per addendum 4 revisions) (32A) $ 140,000 36. Irrigation revisions (per addendum 4 revisions) (32C) $ 5,000 37. Allowance for Solar panels @ Buildings (Accepted Alternate 29) $ 250,000 38. Allowance for Moveable Seating (Accepted Alternate 30) $ 1,300,000 39. Allowance for Installation Only of Owner Furnished Underground Trash / Recycling Receptacles & Precast Boxes (Accepted Alternate 31) $ 650,000 Page 19 of 26 SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Schedule See attached Page 20 of 26 Imagine Clearwater_ CURRENT Summary Schedule Data Date: 10-Jun-21 Date Printed: 10-Jun-21 Activity ID Activity Name Remaining Start Finish Duration 2021 2022 2023 1x Ma Jun Jul Aug Sep Oct Nov lac Jan Feb Mar • . Ma Jun Jul A r 6` Oct Nov Dec Jan Feb Mar Apr May Jun Jul Imagine Clearwater_CURRENT 505d 20-Aug-19A 17-May-23 —; -ray- , n Coachman Park Renovation 505d 20-Aug-19 A 17-May-23 117-May-23, G 47-May-23, M Milestones 498d 18-Jun-20 A 17-May-23 MIL-003 Library 95% CD / VE Approval By City Council Od 18-Jun-20 A MIL-006 Park DD Estimate Issue To City Od 18-Jun-20 A MIL-020 Park/Bandshell 100% DD Set Issue Od 30-Sep-20A MIL-021 Park/Bandshell 100% CD Set Issue Od 29-Mar-21 A MIL-026 Notice To Proceed - GMP 2 Site, Demo, Fencing, Earthwork, Utilities Od 27-Apr-21 A MIL-027 CLOMR Wall Final Design / Permit Issue Od 04-May-21 A MIL-030 GMP 2 ERP Sitework Permit Issue Od 18-Jun-21 MIL-025 Start Of Construction - Early Release Package GMP 2 Od 21-Jun-21 MIL-007 Park/Bandshell 100% CD FINAL GMP 3 Issue To City Od 28-Jun-21 MIL-022 GMP 3 Park/Bandshell Building Permit Issue Od 08Jul-21 MIL-023 Park/Bandshell GMP City Council Approval Od 15-Jul-21 MIL-009 Notice To Proceed - GMP 3 Park/Bandshell Od 22-Jul-21 MIL-024 Site Demolition Complete Od 20-Sep-21 MIL-019 Force Main EOR Approval (In-Service) Od 24-Sep-21 MIL-032 Duke Energy Primary Power Scope Complete Od 05-Nov-21 MIL-016 New Sanitary System In Service Od 26-Nov-21 MIL-028 Bandshell Structure Start Od 29-Nov-21 j '.. MIL-031 GMP 2 Utilities Complete Od 10-Mar-220 1 MIL-015 Substantial Completion - Park/Bandshell Od 17-May-23* Design Od 20-Aug-19 A 29-Mar-21 A Permitting 20d 05-Oct-20 A 08-Jul-21 : uracil Set Issi'e Park/Bandyhell i Notice • CI.OMR 29M&21 • • • A, To Ppoceed W911 GMf? Start Pafk/Bendfihell • GMP • • Design 708-JuF21,Permitting 100% Final 2 PRP Of. ParkIBaridshell Notice CQ - Construction 0 Park/Bfand$hell;Building;Perr}1it ib • • Set GMP Desigl Sitework Proceed Site; Force Issue 2 $ite, / 100% GMP Demolition Main • Dike • 4 Permit Permit - l=ady CD - (MP,3 Nev,✓ Bandshell pemo, 15suei Issue release FINAL City Oomplete, EORApproval Energy Sanitary Fencing, Dourlcil Park/Bancisheli Primary StrudureStan t#ackage GMP Approval Systerh • C3MP Earthwork, 3 Issue I$sue (Int Ppwet -Service) In 2 Utilities GMII To Scepe Service Ui(litied 2 City Complete Complete I • Substant+al C Pre-Construction 31d 02-Dec-19A 22Jul-21 22�ul-2I, Pre-Construction `m.i� broctireMent Procurement 245d 28-Apr-21 A 26-May-22 V""•. 26-May.22, I t 3-Mar-29, Constructia Construction 458d 24-May-21 A 13-Mar-23 Overall she 25d 24-May-21 A 19-Jul-21 I"�1 19J01-21, OJ•erali? Sit$ Scope Of Work Duke Energy Scope Of Work 75d 22-Jul-21 05-Nov-21 0$-Nov-21 Duke Energy t3-Mar-22, Pierce Stre Pierce Street Parking Area 446d 09-Jun-21 A 13-Mar-23 I 01!-Mar-23, Lake & Play, Lake & Play Area 431d 01-Jun-21 A 01-Mar-23 r / 23-Feb-23, Gateway & Cl Gateway & Cleveland Street Drop Off Area 414d 26-Jul-21 23-Feb-23 II & lower Pie The Green & Lower Plaza Area 362d 20-Jul-21 20-Dec-22 ‘ . I p0-Qec-?2, The 014Mar-23, Green $andshelll & Bandshell & Event Area 448d 01-Jun-21 A 01-Mar-23 i% 13-Sep-24, i Demolition 64d 01-Jun-21 A 13-Sep-21 Demolkioni Newv Utilities New Utilities 256d 15-Jul-21 18-Jul-22 CLOMR Wall' 118-Jul-22, CLOMR WaI 45d 23-Sep-21 26-Nov-21 ••••11, 26-Nov-21, Bajldshell Bandshell Canopy 261d 29-Nov-21 06-Dec-22 M : : : : r 08-Dee-24 Qanopy Bandshell Bu Bandshell Building 280d 26-Jan-22 01-Mar-23 , ° '101-Mar-23, j Cveni Restroom Event Restroom 201d 15-Apr-22 20-Jan-23 : __ • 120-Jan-23, Hardseape 1 Landscape Hardscape / Landscape 306d 27-Sep-21 08-Dec-22 ♦ 108-15ec-22, Boathouse 30d 27-Jan-22 09-Mar-22 v!I 09-M8r-22i Boathouse Bleff North Bluff Walk Area 193d 30-A4-21 02-Jun-22 lr 02-Jun-22, Nor(h Walk Area P Project Closeout 323d 11-Feb-22 17-May-23117-May-23, Page 1 of 1 w �C V A SKA SKA SKANSKA Remaining Level of Effort ti Actual Work 1 I Critical Remaining Work . - Summary ..,,• Actual Level of Effort t 9 Remaining Work • • Milestone age zto SKANSKA 2 - Basis of Guaranteed Maximum Price Imagine Clearwater Guaranteed Maximum Price (GMP 3) Flatwork & Vertical Construction June 28, 2021 Logistics Plan See attached Page 22 of 26 SKANSKAt Skanska Gals TEMPORARY Seem*Grimm ! M PUO PUOUC Mame A cress Cvnala 1 f 1 .4";"-7 Old City Hall Parking - NO Construction Parking Skanska Fie:d Office Traikas Llnetype Legend --- E--- bd.B.ae Ln Typical Abbreviations o eft. coroon. on I. Mon Tree Legend Symbols Legend ormar A 'mu Now Mb ® as m w.re t r..r<...r v.w 1U., . ® c+trow.rr Xi 0 Legend Construction Fencing Construction Parking ConstructionTraffic Path Inbound PUBLIC Traffic Path El NO Construction Parking Outbound PUBLIC Traffic Path ft I l l e ` Sk ri ka Gale P 1 Main Entrance CITY OF CLEARWATER, FLORIDA ENGINEERING DEPARTMENT 100 3. MYRTLE AVE. CLEARWATER, FL 33756 Logistics Flan DATED 6/5/21 **FOR REFERENCE ONLY** CitrpWJLI 10.: ilaallel/an NAlnn.o_tulnz ' 1,a6 Miff/ 1'+6P /A Page 23 of 26 5KANSKA _- #) ✓i c1.i TEMPORARY Saclostimils itsr OraM,ai Maritsa PUBLIC alai ding r4 muscat* J 0 ft Central Deck FDC a co' 120' ',neat Dock IDC Fire Truck Turn Around MOST. I I ANOSHFI I I OSCEOIA AVE /NOM.* M Parte bra kIs2 )J. 7._ _ � , i'-4 ��, _ L '' § ) NICy� ice.. ..,,,,Ti ---11 r- z C1Ao;.L ;_rrT F 1 • 12' EMERGN Y COY OWN ?Pli Access Gate o 6o..N. _ 1 i 1 -ate-=_ " •_ �[e= FDC EnmN FOC. o Po . I I Weals Edge condo - 11iit I.. ire 11226 daau� ,L A PARKING LOT -- — F --- b W axaleu• 4.Arr•w� Typical Abbreviations Tree Legend A* GI. / e W._T- mqunbeeeq • tor Waren ruM x PARCEL N oamlSu:.tdils crry PROPERTY MAN LIBRARY Legend Construction Fencing EMERGENCY Vehicle Access Path r, �e.al=oe=. j CITY OF CLEARWATER, FLORIDA ENGINEERING DEPARTMENT 100 S. MYRTIE AVE. CIEARWATER FL 33758 ogistics Plan DATED 6/5/21 **FOR REFERENCE ONLY** OR 1ao2C1 ND.. i24WicN/prt PIM Sn No_anmx t 1f5514369 I'•BJ 0-170 N/A Page 24 of 26 SKANSKA II !,sirsing FIRE LAUF. i,13771 iTEMPORARs SKIewetla lot Con. manna PUBUC ACOEIBB during HuEsteucilon Manna Axess Junp - • , SOWS Dts..k .44-:". • - - Fire Truck T,Jrr Around . _ '1/4,rk 120' ;113ANDSH-, SU PARK NO LOT ' . 7s3 Acrs, /1' - c-- , -., it -- '.- --• -,, cr'i ;;; (TILL .1.___,.4..._,_!_!:-„, -I -. ,•'. !:-) iKIC. 1 , .--', .,, f KS RCNE CY ar vrEsOemom.... . ' ' ' i AO f l'-,.;'..,1•,•'''- ' ,, ') ;',, - 1-, Unelype Legend r.s.-row=4 Oa•Lvkioxa Typical Abbreviations TCV —rI tiW00,0.1ria 0, S OSCEOLA AVE MC PRINCE 5" iNice Ssrn 21 30 —1 • 1 F It Itri " (--„1 '11 P/31 JA,E PRT5PERTY11 vo,FP S FCGF CON/r0411,0JIVI NIC -44- .; I ! 1 _ 1 }- 1 4" I' 1 111, , f 3 i -,_ NORTH ZONE Tree Legend 0.• 0 — Symbols Legend ES • crest...F.. • N.,. •••••• crry P e—o—p e rl 'ULM pew! Legend Construction Fencing EMERGENCY Vehicle Access Path 0 1, I DATED 6/5/21 CITY OF CLEARWATER, FLORIDA ENGINEERING FL 33756 100 S. MYRTLE AYR L y▪ u istics Plan NG DEPARTMENT -ff;**FOR REFERENCE ONLY** CITrPNOECINO; Pim sT.0.:23.01.3 I 21561019 215614.01.0X,11.044 C-110 N/A Page 25 of 26 f0 NDMONS FOR REFERENCE ONLY** D 6/5/21 C- N/A SICANSICA I ) ,C; Manna Access r...... -- ........ _ r r ' SOU ti ZONE - Access from Pierce St O•^2,ola CENTRAL ZONE - Access from Cleveland St g Osceola NORTH ZONE - Access from Drew St Osceola Ono NIP,* Rai Noe COM Pomrtaer 1110.16....k. Tree Legend ca nee no. Symbols Legend , n. 2 =Ir. .611.0GuIralVP. 1= © ffl toffic <' 1.41•••••/...n.. Legend :z=, de.y. "re Copb. W,1Y%b,RSum. cum orvra Incr. OW conc.. by Pon:es fortecIden 11 II LS/A 1 Logistics Plan - Emergency Zones Page 26 of 26 Skanska USA Building Inc. usa.skanska.com SKANSKA ADDENDUM 1 GMP 3 SKANSKA & CITY OF CLEARWATER IMAGINE CLEARWATER GMP 3 is based upon the mutual understanding that it incorporates the following revised language into the Contract, in lieu of either party procuring additional insurance coverage: 5.2.6. BUILDER'S RISK INSURANCE The City will provide at its expense, Builder's Risk Insurance for the project to cover all risks of loss in the complete and full value of the project. Contractor agrees to cooperate in a timely manner with providing any information or documentation required for the application and by the carrier as the project proceeds. The City will be responsible for all deductibles. The City will be responsible for all costs ordinarily covered through Builder's Risk Insurance to the extent the costs are not actually covered by the insurance procured by the City. ADDENDUM 1 GMP 3 • SKANSKA & CITY OF CLEARWATER IMAGINE CLEARWATER Skanska USA Building, Inc. For Imagine Clearwater Flatwork and Vertical Construction (17 -0031 -EN) IN WITNESS WHEREOF, the parties hereto have made and executed this GMP Proposal on the date and year first above written. (Corporate Seal) v5A B4/4Q;; ,, °C`4`0$ oRAri.?0�,- SEAL Countersigned: Fr Hibbard Mayor Approved as to form: 0,4 ct.0,/ SKANSKA USA BUILDING, INC. By: (1, Print Name: Title: ciZ Ii/C_ P<Zc 41C Go."-) S t /Z '-)(...:77 DiA) WITNESS: B3te,..:6)1/101K0 Print Name: 1310,Vc. Acni,AnO t. A,ViLt�j CITY OF CLEARWATER Aft-frki--40—Zt" Owen Kohler Assistant City Attorney William B. Horne 11 City Manager Attest: Rosemarie Call City Clerk Page 27