Loading...
EAST WRF RDT BUILDING CONDITIONS ASSESSMENT - 18-0016-UT - ADMINISTRATIVE CHANGE ORDER #3 & FINALAdministrative Change Order 3 & Final DATE: PROJECT: PROJECT NUMBER: East WRF RDT Building Repair PO REFERENCE: CONTRACTOR: May 5, 2021 18 -0016 -UT 20000694 Paramount Painting and Services Inc. DATE OF CONTRACT: January 15, 2020 4613 N. Hesperides St Tampa, FL 33614-6911 CODE: 3277327-546700-M1907 SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract decreasing and increasing items in accordance with field conditions to close the project -see attachment. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT Change Order 1 - City Council 6/4/2020 Change Order 2- City Council 9/17/2020 Administrative Change Order 3&Final- City Mgr NEW CONTRACT AMOUNT $ 59,435.00 $ 72,145.00 $ 98,814.00 ($14,862.81) $ 215,531.19 Assistant City Attorney Rosemarie Call, ACCEPTED BY: Paramount Painting & Services Ind' "' By: /f, , os .. ,j� ., .,... Jeff Hei IVV� Pr'eiid ' Date: 601Y/2oz/ WI/LW &Aize Recommended By: City of Clearwater CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA 11)3J 144 . " William B. Horne, II City Manager Ivan Dimitrov, Project Manager City Engineer Page 2 of 2: Administrative Change Order 3 & Final East WRF RDT Building Repair ITEM DESCRIPTION UNIT � UNIT COST TOTAL COST Decreases: 5 Vertical Concrete Crack Repair: at the FT 130 $ 8.00 $ (1,040.00) walls of the Chemical Feed Room via route and seal, refer to specification 07920 of the BillerReinhart Project Manual 6 Horizontal Concrete Crack Repair: in floor FT 30 $ 7.00 $ (210.00) slab, refer to specification 07920 of the BillerReinhart Project Manual 10 10% Contingency LS 1 $ 21,834.00 $ (21,834.00) 11 Installation of #5 steel reinforcing in LF 305 $ 9.00 $ (2,745.00) concrete repair 12 Labor Cost HR 5 $ 55.00 $ (275.00) 13 Material Cost % 5 $ 20.00 $ (100.00) 15 Removal and replacement of unsound SF 0.446 $ 26.00 $ (11.60) stucco at CMU wall Total (Decreases): $ (26,215.60) Increases: 4 Overhead Concrete Repair: delaminated CF 2 $ 450.00 $ 900.00 areas, spalls, and exposed reinforcement at 2nd floor underside, including adjacent beams where necessary 9 All Other Work Not Included in Line LS 0.00014 $ 20,407.79 $ 2.79 Items 1, 2, 3, 4, 5 6, 7, and 8 to Repair the East RDT Floor Slab 17 Structure Stabilization LS 0.13922 $ 33,400.00 $ 4,650.00 18 Horizontal Concrete Repair: delaminated CF 4 $ 325.00 $ 1,300.00 areas, spalls, and exposed reinforcement at 2nd floor slab surface 19 Full depth concrete repairs due to severity CF 10 $ 450.00 $ 4,500.00 of existing corrosion Total Increases: $ 11,352.79 Total Net (Decreases)/Increases: ($14,862.81)