PROPOSAL FOR ROSS NORTON RECREATION CENTER MAIN POOL, PLUNGE POOL AND ACTIVITY WADE POOL RENOVATIONPROPOSAL
May 26, 2021
TO: Leroy Chin
City of Clearwater
100 S. Myrtle Ave., Suite 200
Clearwater, FL 33756
RE: Ross Norton Recreation Center Main Pool, Plunge Pool and Activity Wade Pool
Renovation
Dear Mr. Chin,
I am pleased to submit the following Construction Management Proposal for the renovation of
the existing Ross Norton Aquatic Complex 1426 S Martin Luther King Jr. Ave, Clearwater, FL 33756 as
more specifically outlined below for a Guaranteed Maximum Price of (S449,077.51) four hundred,
forty-nine thousand, seventy-seven and 51/100 dollars.
Scope of Work:
We will provide all bonding, supervision, labor, materials, and equipment to complete the
scope of work as described on the plans and specifications prepared by G.B. Collins Engineering
P.A., Titled Ross Norton Recreation Center Main Pool, Plunge Pool and Activity Wade Pool
Renovation, Sheets 1 to 13 dated 12/3/2020 and more specifically outlined in the bid tabulation
signed and submitted on 5-17-21, titled Phase 2 Request for Proposal Ross Norton Pool
Renovations, bid Items 1 thru 68 (attached).
Exclusions:
1. Permitting fees.
2. Design, engineering, or architectural work.
3. Warranty of any materials, fixtures, or equipment supplied by owner.
4. Builder's Risk Insurance.
Substantial completion shall be within 120 calendar days from the date of the Notice to Proceed.
Existing Contract This proposal is submitted in conjunction with the existing Construction Manager
at Risk Services Continuing Contract entered into with the City of Clearwater on 08/24/2020 based
on RFQ #40-20.
1
I
sNSN
tf GMP Exceeds $150,000: Per Section III, Article 5.1 of the Contract Specifications, the contractor
shall provide to the public entity a certified copy of the recorded bond. Once the City receives a
certified copy of the recorded bond, a Notice to Proceed may be issued. Include the attached bond
form as well as the Power of Attorney. (If GMP is less than S150,000 a bond is not required)
For work performed, invoices shall be submitted to Leroy Chin, City of Clearwater—Parks and
Recreation Department 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756. Contingency services
may be billed only after written authorization is provided by the City to proceed with those services.
KHORS CONSTRUCTION, INC.
By: 7-"L
�2C2(
an, President
Countersigned:
CITY OF CLEARWATER, FLORIDA
Mayor
&2L—�
William B. Home II
City Manager
Approved as to form: Attest:
C61/41
-453-4; Owen Kohler
City Attorney
Rosemarie Call
City Clerk
2
Bond No.:
f (`f3LIC C'O.\,STRI (TION MAD
(1)
This bond is given to comply with § 255.05, Florida Statutes, and any action instituted by a claimant under this bond for
payment must be in accordance with the notice and time limitation provisions in subsections (2) and (10).
Pursuant to § 255.05(1)(b), Florida Statutes, "Before commencing the work or before recommencing the work after a default
or abandonment, the contractor shall provide to the public entity a certified cony of the recorded bond. Notwithstanding
the terms of the contract or any other law governing prompt payment for construction services, the public entity may not make
a payment to the contractor until the contractor has complied with this paragraph."
CONTRACTOR SURETY OWNER
Kbors Construction, Inc.
6251 44th St N. Ste 1909
Pinellas Park, FL 33781
813-728-3689
FCCI Insurance Group Surety
6300 University Parkway
Sarasota, FL 3424o
RE: Ross Norton Aquatic Complex Phase II Pool Renovations
City of Clearwater
Parks & Recreation Dept.
100 S. Myrtle Ave. Suite 120
Clearwater, FL 33756-5520
PROJECT DESCRIPTION: Pool resurfacing, the replacement, selective equipment replacement, deck coating and painting.
BY THIS BOND, We Khors Construction, Inc., as Contractor, and FCC! Insurance Group Surgery, a corporation, as Surety,
are bound to the City of Clearwater, Florida, herein called Owner, in the sum of (5449,077.51) four hundred, forty-nine
thousand, seventy-seven and 51/100 dollars for payment of which we bind ourselves, our heirs, personal representatives,
successors, and assigns, jointly and severally.
THE CONDITION OF THIS BOND is that if Contractor.
1. Performs the proposal dated May 26, 2021, between Contractor and Owner for construction of the Ross Norton
Recreation Center Main Pool, Plunge Pool and Activity Wade Pool Renovation, the contract documents, being made a part of
this bond by reference (which include the Contract, Surety Bond, Plans and Technical Specifications, and such alterations as
may be made in said Plans and Specifications as therein provided for), at the times and in the manner prescribed in the contract
and
2. Promptly makes payments to all claimants, as defined in Section 255.05(1), Florida Statutes, supplying Contractor
with labor, materials, or supplies, used directly or indirectly by Contractor in the prosecution of the work provided for in the
contract; and
3. Pays Owner all losses, damages, expenses, costs, and attorney's fees, including appellate proceedings, that Owner
sustains because of a default by Contractor under the contract; and
Bond No.:
PUBLIC CONSTRUCTION BOND
(2)
4. To the limits of § 725.06(2), Florida Statutes, shall indemnify and hold harmless Owner, their officers and employees,
from liabilities, damages, losses aid costs, including, but not limited to, reasonable attorney's foes, to the extent caused by the
negligence, recklessness, or intentional wrongful misconduct of Contractor and persons employed or utilized by Contractor in
the
performance of the construction contract; and
5. Performs the guarantee of all work and materials furnished under the contract for the time specified in the contract,
then this bond is void; otherwise it remains in full force.
6. Any action instituted by a claimant under this bond for
payment must be in accordance with the notice and time
limitation provisions in Section 255.05(2), Florida Statutes.
7. Any changes in or under the contract documents and compliance or noncompliance with
with the contract or the changes does not affect Surety's obligation under this bond, and Suretyany formalities connected
hereby waive notice of
any such change, extension of time, alteration or addition to the terms of the contract or to the work �orthele specifications.
IN TESTIMONY WHEREOF, witness the hands and seals of the parties hereto this day of
20
(Ifsole Ownership or Partnership, two (2) Witnesses required).
(!f Cor poration, Secretary only will attest and ex seal).
WITNESS:
latent Lica
By:
Title: Print Name:
WITNESS:
Corporate Secretary or Witness Print Name:
Print Name:
(affix corporate seal)
(Power ofAttorney must be attached)
fCCllnswrance Company
By:
ATTORNEY IN -FACT
Print Name:
(affix corporate seal)
Phase 2 Request for Proposal Ross Norton Pool Renovations 1426 S. Dr. Martin
Luther King Ave. Clearwater, FL 33756
ARMC name: Mors Construction. Inc. Contact Person: Kiat Kharsandi n
Address of AMC: 6251 44th Street N Ste.1909 City Pneles Park
State: FL zip Code:
Contact: Tet 727-470-7352 Mobile: 813-7283689
E-rnai- khorsconstjgmalcom Date: 5 7 2 I
Signature: L
LUMP SUM PRICE BID. IF THERE IS AN ERROR IN THE TOTAL BY IT SHALL B D AS ONLY
THE UNIT PRICES AND LUMP SUM PRICE SHALL GOVERN. THE CITY RESERVES THE RIGHT TO ELIMINATE ANY
LINE ITEM AM) May NOT ACCEPT PROPOSAL PROVIDED ARCM SHALL HOLD HS PRICES FROM DATE OF
SUBMISSION OF HIS PROPOSAL UNTIL CONTRACT AS BEEN AWARDED BY CITY COUNCIL THE CONTRACTOR
SHALL PROVIDE COPIES OF A CURRENT CONTRACTOR LICENSE/REGISTRATION WITH THE STATE OF FLORIDA
ANO PI ELLAS COUNTY IN TIE BID RESPONSE.
Item
No.
Descnpbon
Units
QT Y
Unit Cost
Total Cost
1
Bonding and Mobilization includes drawing al pool requrernents
n preparation of pool construction (see note on drawings regards
'
LS
1
S 30.317.04
S 30.317.04
to d .. • pool).
Removal
2
and renstal al pool furniture (ladders. hand rads bads
stroke poles ening board & platforms) remove bond wire anu
protect fox renstalatton of pool furniture Store and pro:ea onLS
site for reinstallation.
1
S 1.476.00
S 1,476.00
9
Remove and replace lap diving pool bean per delafs on page 7
of 13 Typ. Gutter Wall & Wall Detail and Mien pool Beam Desai
electrical pond renfordenrent per NEC code. Protect pool aeration
system on east sae of pool during construction of pool beam
water exit ports steal have continuous stream of water anc at shall
be matching
IF
322
S 116.85
S 37,625.70
Relever pool gutter web only 1/4" tolerance on aI sloes of pool
LS
1
S 3.874.50
S 3.874.50
5
r
Denaibon of pool al tis and pool existing surfaang of al
debnsnatng materials by sand biasing or mechanical means.
sound surface for hollow spot and remove. which includes stair
and handicap ramp. See instructions on sheet 4 of 13 Pool
Resurfadng Notes and Speaficatxins for preparation of existing
Poo► surface for Hydrazo surfacing material. Remove and replace
expansion pint see dated sheet 7 of 13.
LS
1
S 13.630.86
S 13,630.86
6
Remove and replace pool 2x4' gutter fillings with new Pentad
540063 - submit sample to Engneer and Owner review
EA
33
S 33.21
S 1,095.93
7
Remove and replace aro rope anchors - submi sample °
Engneerng & Owner review
EA
14
S 131 61
S 1,84254
Remove and replace floor returns mai new Pentar 1425 submit
sample to Engneer and Owner Review
EA
18
S 123.00
S 2.214.00
9
Remove and replace floor drain to meet ASME/ANSI A112 19
£2009 NSF50 64E-9 for anti -entrapment. Subrat sample to
Engneer & Owner:
EA
2
S 338.25
S 676.50
10
sample
"
Remove and replace vacuum Ttwitgs with new Hayward VAC LOC
vacuum safety fittings with spring loaded safety cover. prornde
to Engineer and Owner for review_
EA
2
S 123.00
S 246.00
11
requirements_
Rebuild stars as necessary o meet current pool code
See sheet 1 of 13
LS
I
S 738.00
S 738.00
12 Pool Crack reps, with Torque Lod; Gads Repair Kits as required - l
subink sample to ErgiOmer teer and Oer review. JI EA
New depth and no dive mediate non sfp yes per derma and
13 notes sheet 8 of 13 - submit samples for review by Engineer and
Owner.
Install al'squired porcelain ties as cal out on the drawngs, tie
color shall be black unless otherwise noted, which includes stairs
and handicap ramp. Non sip ties am required as noted on
arming sheets 6 of 13. 7 of 13.8 of 13. and 11 of 13 for entire
14
Mnptdiving mei poet AMC shat instal 6 tap lane markets
et Mit. nod hlsouth lane smokers have been eirinated from
main pool/clang awl. Inctide depth marker on pool gutter area 14
locations matching beam marker locations of pool gutter - submit
samples to Engineer and Owner for review:
15
16
Subini tiles for approval of non sip tie 'equivalent A tie
manufacase cannot provide documentation ARCM shat submit
ties to Product Performance Test rig Lab on street 8 od 13 is
oontaa nfomnation to test ties to meet Vet Dynamic Coefficient of
Friction (OCOF) to test lies report and sample ties shat be
provide to Engineer and Owner review and they MI submt to
DOH Pneflas County for ther review. Note approved lies shal be
use on all pool of this project.
EA
2
$ 1,230.00 $ 2.460.00
14
S 46.74
S 654.36
LS
1
$ 20.971.50
$ 20,971.50
LS
1
$ 6.15
S 6.15
17
18
19
20
1
Not Used
Remove and replace expansion joint material around pool beam.
Clean out existing expansion join: dean surface with cleaning
agent. instal backer rod to allow 314' depth cauk uti¢e vuikem
caulk to It etpanston joist and tool fresh to smooth concave pint.
Peonae sample for approval by Owner & Engineer prior to
pertumtng the work
Instal hydras pool surface of lap pool and diving wel
LF
322
S 4.66
$ 1.5010)7
Pahlin neat Chemical Feeder Board remove and replace lowlier
flow meter. Ph meter and Chlorine meter and replace wren new
total of 3 urdb
LS
1
$ 48,757.20
$ 48.757.20
Mechanical yard aeration system of maim pool dean and recoat
tanks check al pumps are operational and dismal feeds are
operational replace hair strainers basket and filter as necessary.
check al plumbing is n good wort order or replace as necessary
replace 3 ndn valve precoat and vacuum inns replace al
handles deteriorated.
EA
3
S 4,828.98
$ 14,486.94
ARMC snail fill pool upon completion of hydrazo slum mg is
complete Owner shall supply water meter for the hydrant. ARMC to
Provide necessity temporary pPng born provided water meter to
SI at pods. Upon completion of filing pool ARMC to brush pool to
remove bose material and vacuum loose debris. poiah pool
surface and dispose off site. ARMC to sten up pool equipment to
ensure al pool mednanit aUelectrrcal components including
chemical feeders are function's' property and make al necessary
repairs and &tiedments as required Check Aeration ext ports
that they are dear of any debits and are providing a continuous
!et stream of water. al stream of water shat be rra°.dhng existing
port ARMC shall balance pool chemistry to meet minimum pool
balancing five days pnor to requesting DOH Patellas County to
Certify Pool Operation ARMC shall take al necessary actions to
satisfy OOHPC to certify the pool of Operations as pan of the
contract at no additional expense to the Owner. Pool dhemicats
shall be provided by the Owner to balance the pool chemicals for
pool operation certificate Clean up site of any construction debris
dispose off site, dose out building permit and centred between
LS
1
LS
$ 1,845.00
$ 1.845.00
1 $ 4,345.00 $ 4.345.00
22
2 etch bendh drain remove gime and repeal - clean Wain remove
and sit and depose off site power wash drain and instal new
drain cover with staihiess steel 316 smuts_
IF
68
S 47.97
S 3.166.02
23
LINE 23 NOT USED
—
'
24
AIL
Men pool deddng remove al existing loose acrylic deddny
surface by power washing with 4.000 psi power washer. prepare
surface for installation of Polymer Modred Deck Spray material
1deconnire dedt coating) by LEWCREIE. see specifications.
provide 5' x 5' texture surface sample for Owner approval install
deck
deCoating and aiow to cure. apply exterior concrete soon
Penna- Crete both products by PPG Industry material located
local/ on Oevetand Street. Clearwater. FL provide stairs color for
approval by Owner.
SF
6.880
$ 7.40
S 50,795.58
25
AIL
Line 25 Not Used
26
27
Lie 26 Not Used
Removal and reinstall al pool furniture (ladder a hand rale)
remove bond wire and protect for reinstallation of pool furniture
Slave and protect on see for reinstallation
LS
1
$ 615.00
S 615 00
28
Oenoioon of pool al ties and pool exitorg surfacing of al
dearrwtatng materials by sand blasting or mechanical means.
sound surface for hoiow spot and ndudng stars rebuidng as
necessary. See nstrucoons on sheet 4 of 13 Pool Resurfacing
Nom and Specriicatons for preparation of existing pool surface
for Hydrazo surfacing material Note depth markers on pool beam
to remain and protected during pool renovations i damaged
cuing renovations it is the responsibly of the ARMC to replace at
his over expense and no additional funds shall be provided by the
Ls
1
$ 2.140.20
S 2,140.20
29
Check stammers are functionng property and replace Parts es
necessary provice new straner and top covers flush with pool
beam - submi sample to Engineer and Owner review
EA
2
S 123.00
$ 246.00
30
.—_
Remove and replace floor returns with new Pentair 1425 submitEA
sample to Engneer and Owner Review
6
S 123.00
S 738.00
31
_
Remove and replace floor Bran to meet ASIiE,'ANSI A112 19
42009 NSF50 64E-9 for aro-entrapment. Submit sample to
Engineer Owner.
Engr
EA
3
S 235.75
S 707.25
32
r
Remove and InPInce rope duo anchors submit samples for review
by Engineer and Parser.
EA
2
S 184 SO
$ 369.00
33
Remove and replace vacuum fittings with new Hayward VAC LOC
vacuum safety fangs with swig loaded safety cover.
EA
1
S 123.00
S 123.00
34
Instal al requwed porcelain ties as cal out on the drawings, tie
torr shill be dad unless otherwise noted. which indorses stars.
Non sip hies are required as noted on drawing sheets 6 of 13, 7
of 13. 8 of 13 and 11 of 13 for plunge poor tndude depth
marker on pool waterline tie 6 locations matching beam -worker
loclltons of waterline tie - submit samples to Engineer and
Owner for review.
IS
1
$ 6.368.94
S 8,368.94
35
r
Instal hydrate poo surface of plunge pod see sheet 4 of 13
LS
1
S 8,019.60
S 8.019.00
36 functioning
"----
Feature sive mechanical yard - pumping station at pool side
dean recoat tank as required. check electrxal components are
property and repace valve handles with new dean
mechanical yard of Wants. and provide additional crush shel revel
area within mechanical yard,
LS
1
S 3.075.00
S 3.075.00
Liec
37
valves
hani:al tiering yard: remove and replace DE filers ihauo.
leooat tanks as required: remove and replete al handles of
parr strainers baskets with new
LS
1
1
S 3,0! 3.50
S 3.013.50
38
Prof/mient Chemical Feeder Board remove and replace lower
flow meter. Ph meter and Chlorine meter and !spice win new
total of 3 units
EA
3
S 4,097.94
S 12,293.83
Remove and replace valve handles rh4k<nd_n Mair filtration tanks
n Mechanical yard,
EA
2
i 123.00
S 246.00
40
41
ARMC shall fir pool upon completion of hydtazp surfacig is
complete upon completion of filing pool ARMC to brush pool to
remove loose roto trial and vacuum boss debris, polish pool
surface and dispose off site. ARMC to start up pool equipment to
ensure al pool l components including
chemical feeders as functioning property and make al necessary
repairs and adjustments as required. ARMC shal balance pool
duality to meet minimum pool balancing live days prior to
1equessatg DOH Pinellas County to Centy Pool Operation ARMC
shall take of necessary actions to satisfy DOFPC to certify the
pool of operations as pan of this contract at no additional
expense to the Owner. Pool dxerrikals shall be provided by the
Owner to balance the pool chemicals for pool operation certificate.
Clean up site of any conduction debris dispose of sib, dose out
building permit and contract between ARCM & Owner.
Existing shade canopy over plunge pool (west side) ori conaete
6 inch wide both sines of metal shade canopy supports poles at
base at Iwo lantiona; remove concrete: prep base of post for
Paattng (see drawing sheet 4 of 13) prep metal of shade carloPY
and paint one coat of pruner and two coats of wilt high gloss
PPG paint: Arnemoat Mee TDS (Winer) PPG PSX able TDS
one pan epoxy or equal. painting specifications and preparation
for painting; provide paint color sanepie to Owner for approval.
Forth up comets opening and install 5.000 psi non slut* grout
penile medium broom bash.
LC
LS
1
1
S 1,30750
S 4,678.92
$ 1,307.50
S 4,676.92
42
Side tower staffs assembly remove rust to bare metal, prepare al
metal, repair star pan remove al must to bare metal. pine and two
omits of PPG Amercoat %tee TDS (primer) PPG PSX white TDS
one pad epoxy or equal, panting sped tions and preparation
for paining
LS
1
S 4,723 20
i 4,723 20
43
Feature side structure reprove rust to bare metal and repaint
feature slide structure as necessary - remove and replace rusted
bracket and paint same as tem 43 above
LS
1
$ 6,642.00
S 6,642.00
44
Remove and apace expansion joint material around pool beam
plunge pool (115 LF). dean out existing expansion joint dean
surface watt cleaning agent, install backer rod to allow 3/4' depth
Vukern caulk, utilize vacuum caulk to fir expansion pint and tool
tines' to smooth concave pit. Provide sample for approval by
Owner & Engineer prior to perforrrirtg the work
LF
115
S 4.68
S 536.10
45
Pool deck remove and replace expansion Ant nuterfels on
existing concrete flat work of as pool deck areas (main lap/diving
eel. qty and age pis- dean out existing pints. dean
su(includinrface g an agent. thrall backer rods as necessary
openings 1/4' 0 3/4" widths) iecat Sika ser
Lelvekng caulk to fir expansion joints and level to adjcent
concrete surfaces. Provide sample for approval by Owner &
E . -_. pnorto performing the work.
LF
IF
350
850
i 4.66
5 1,631.60
46 agent.
adjoent
&
Al pool deck cracks (twining urea activty plunge pools: some
areas have existing caulk installed) remove erasing musk, route
dean out exciting cracks of loose material dean with cleaning
uta cracks watt Sika Ser caulk cauand level with
conaete surfaces. Provide sample for approval by Owner
Engineer prof to per/owning the work.
i 4.66
S 3,962.45
47
48
Pool Deck surrounding plunge pod deck area and plungs pool
beam. power wash with 4.000 PSI power washer, instal Master
Protect BASF H 1000 water repellent sealer (see speafcadons)_
Provide sample area for Owner approval.
Power wash shade canopy and remove and store on she and
reinstall (by Owrnerk prep metal of shade canopy and pain one
coat of primer and two coats of with high gloss PPG paint:
Amerman Wile TDS (primer) PPG PSX while TDS one part epoxy
or equal, painting specifications and preparation for painting;
provide paint odor sample to Owner for approval. Reinstall shade
opy-
SF
EA
2,700
2
S 2.77
$ 2.199.24
S T.472 25
$ 4,39848
fRemove side panels and cargo netting, by paittirg or deanrg or
replacement store and protect on Me for reinstalblion. make
repairs to activity feature: north upper spray feature western two
water ports appear not provide same steam of water as others
dean ores as required. Ytfater feature valves win pul ropes
check if valves are sticking aund dean as necessary to function
49 properly. Instal three new ropes with rope pull handles. Provide
one extra rope as spare. Provide sample of rope for Owner
review. repaint play structure with high gloss paint prime and two
coats of PPG Amerioal Mite TDS (primer) PPG PSX white TDS
one part epoxy or equal, pantng specifications and preparation
for pairing: provide paint odor sample to Owner for approval. per
nw uratures recommendations - reinstall al parts-
LS
1
$ 4,324.68
S 4.324.88
Fiber glass play activity (tube side & ran drop waterfallfeature}
componet and Raindrop waterfall structure shall be leaned.
5() prepped and painted with Am bedodk 2 primer one coat and two
mats of Signracover 2 finch coats. follow manufactures
recommendations for fesurfattrtg f bergless commons.
LS
1
$ 2.027.04
r
S 2.027.04
51
,r Atioxideclier
52Remove
Oemoition at pool al Hes and pool existing surfacing of at
deamixating materiels by sand blasting or mechanical means.
sound surface for hollow spot and rodudi+g stars rebuilding as
necessary. See instructions on sheet 4 of 13 Pool Resurfacing
Notes and SPepool tions for preparation of existing surface
razo surfaaig material. Note depth natters on pool deck
to remain unless they are cracked replearaent is required and
those not cradced shal be protected during pool renovations if
damaged during renovations it e the responsibly of the ARMC to
replace at his own expense and no addlional funds shad be
theTh per
LS
1
S 3.129.12
S 3,129.12
and replace floor returns with new Pentak 1425 submit
sample to Engineer and Owner Review,
EA
16
S 123.00
S 1,888.00
53 Remove and replace pool rx4" gutter fittings with new Pentair
- subntt sample to Engineer and Owner review
EA
EA
16
S 29.52
S 47232
Remove and replace floor dram to meet ASfE/ANSI A112 19
54 &2009 NSF50 64E-9 for antientmapnenL Submit sample to
Engineer & Owner.
EA
4
S 233.70
S 934.80
Instal al mauled porcelain ties as cal out on the drawings. tie
color shall be black unless otherwise noted. Non slip ties are
55 Moused as noted on drawng sheets 6 of 13. 7 of 13.8 of 13.
and 11 of 13 ler activiy poop. - submit samples to Engineer and
Owner for review.
LS
1
S 17,183.10
S 17.183.10
56
Eir
Remove and replace vacuum fittings with new Heyward VAC LOC
vacuum safety fittings with sprig leaded safety rover.
EA
1
$ 123.00
$ 123.00
Instal Hydraso pool surface of activity pool see sheet 4 of 13
LS
1
S 10,617.36
S 10,617.36
58
ARMC ehal fit pool upon completion of hydraxo surfacing s
complete Upon completion of Sing pool MMC to brush pool to
remove loose material and vacuum loose debris. poiah pool
surface and depose off site. ARMC to start up pool equipment to
ensure al pool mechanical/electrical components including
chemical feeders are f u c long properly and make al necessary
repels and adjustments as required. ARMC shall balance pool
chemistry to meet minimum pool balencrig foe days prior to
',questing DOH Pinellas County to Ca* Pool Operation ARMC
shall take al necessary actions to satisfy DOHPC to coy the
pool of operations as part of this contras at no addaonal
expense to the Owner. Pool drenicals shat be prowled by the
Owner to mance the pool chemicals for pool operation certificate.
Clean up site of any construction debris dispose of site. dose out
building permit and control between ARCM & Owner.
LS
1
$ 1,307.50
S 1,307.50
59
Install maraca,* features by Owner
EA
10
S 553.50
S 5,535.00
play provided see sheet 13 of
13 installation details
60
Activity pool mechanical yard - pumping station dean recta: tank
as required. remove and replace DE filters r—kind. check elearcal
components ate functioning properly
LS
1
S 3,075.00
S 3.07500
61
62
Protirnent Chemical Feeder Board remove and replace tower
flow meter. Ph meter and Chlorin meter and replace with new
til of 3 units
Activity pool bads wash pump replace filler assembly
EA
EA
3
I
$ 4,097.94
S 3.013.50
S 12.293.83
S 3,013.50
63
Adevty pool No. 1 return valve and No 4 precool valve. playEA
feature valves replace handles mood
4
S 147.60
S 590.40
64
65
r ,
Pool Dedc surtounting activity pool dedt area power werh with
4.000 PSI power washer instal Mester Protect BASF H 1000
`eater repetarrt sealer (see spec icationsl Provide wrote area for
Owner approval.
Remove filters to instal valvfes and reinstall Seers. Remove three
existing 6 -inti butterfly valves for rnan drag and gutter and
piping through filter tank wag ano instal new valves and piping
and reseal around pipes to ensure no leaks. Rspkrmb netum line
node purr") mom and natal two new four m butterfly valves for
to heat and from heat Instal new 6 -inch butterfly valve for pre.
coat Reinstall existing flow meter and district.' injection ports in
proper location with new damps and Stenner tubng_ Install new
tempaerature guage. Al valves to have stainless steel hardware.
Reinatall 6' pipe support
SF
LS
2.550
1
s 2.77
S 18,566.85
s 7,057.13
S 18,566.85
66
Sub Total of Nems 1 -85
S 408,25228
67
—66�tirnud
`
10% Contingency of line 65
_
0.1
S 40,825.23
Contingency funds shell only be
utilized for Nacos not included in tate scope
of work (lines 1-57).
additional scope of work shall be provided in writing by the
Aid for approval by the Owner_ Owner must approve
additional scope of work in writing for utilization of
Contingency kinds. Any
contingency kinds remaining shall be
netnrned to the Owner by closing out purchase order short
total of lines 16 & 61 Includes
S 440.077.51
contingency.
CONSIMICIME,u
cc�s�ss
PROPOSAL
May 26, 2021
TO: Leroy Chin
City of Clearwater
100 S. Myrtle Ave., Suite 200
Clearwater, FL 33756
RE: Ross Norton Recreation Center Main Pool, Plunge Pool and Activity Wade Pool
Renovation
Dear Mr. Chin,
I am pleased to submit the following Construction Management Proposal for the renovation of
the existing Ross Norton Aquatic Complex 1426 S Martin Luther King Jr. Ave, Clearwater, FL 33756 as
more specifically outlined below for a Guaranteed Maximum Price of ($449,077.51) four hundred,
forty-nine thousand, seventy-seven and 51/100 dollars.
Scope of Work:
We will provide all bonding, supervision, labor, materials, and equipment to complete the
scope of work as described on the plans and specifications prepared by G.B. Collins Engineering
P.A., Titled Ross Norton Recreation Center Main Pool, Plunge Pool and Activity Wade Pool
Renovation, Sheets 1 to 13 dated 12/3/2020 and more specifically outlined in the bid tabulation
signed and submitted on 5-17-21, titled Phase 2 Request for Proposal Ross Norton Pool
Renovations, bid Items 1 thru 68 (attached).
Exclusions:
1. Permitting fees.
2. Design, engineering, or architectural work.
3. Warranty of any materials, fixtures, or equipment supplied by owner.
4. Builder's Risk Insurance.
Substantial completion shall be within 120 calendar days from the date of the Notice to Proceed.
Existing Contract This proposal is submitted in conjunction with the existing Construction Manager
at Risk Services Continuing Contract entered into with the City of Clearwater on 08/24/2020 based
on RFQ #40-20.
1
A
rs
C6RI11OC11011, ■G
cc5oessa
if GMF Exceeds $150,000: Per Section III, Article 5.1 of the Contract Specifications, the contractor
shall provide to the public entity a certified copy of the recorded bond. Once the City receives a
certified copy of the recorded bond, a Notice to Proceed may be issued. Include the attached bond
form as well as the Power of Attorney. (If GMP is less than $150,000 a bond is not required)
For work performed, invoices shall be submitted to Leroy Chin, City of Clearwater --Parks and
Recreation Department 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756. Contingency services
may be billed only after written authorization is provided by the City to proceed with those services.
KHORS CONSTRUCTION, INC.
By:
Date:
Kori Khorsandian, President
CITY OF CLEARWATER, FLORIDA
Countersigned:
e /(r
I Li iiitu-LA7-sr
Frank Hibbard
Mayor
Approved as to form:
en Kohler
City Attorney
William B. Horne II
City Manager
Attest:
Rosemarie Call
City Clerk
2
Bond No.:
PUBLIC CONSTRUCTION BOND
(1)
This bond is given to comply with § 255.05, Florida Statutes, and any action instituted by a claimant under this bond for
payment must be in accordance with the notice and time limitation provisions in subsections (2) and (10).
Pursuant to § 255.05(1)(b), Florida Statutes, "Before commencing the work or before recommencing the work after a default
or abandonment, the contractor shall provide to the public entity a certified conn of the recorded bond. Notwithstanding
the tenns of the contract or any other law governing prompt payment for construction services, the public entity may not make
a payment to the contractor until the contractor has complied with this paragraph."
CONTRACTOR SURETY OWNER
Khors Construction, Inc.
625144th St N. Ste 1909
Pinellas Park, FL 33781
813-728-3689
FCCI Insurance Group Surety
6300 University Parkway
Sarasota, FL 34240
RE: Ross Norton Aquatic Complex Phase II Pool Renovations
City of Clearwater
Parks & Recreation Dept.
100 S. Myrtle Ave. Suite 120
Clearwater, FL 33756-5520
PROJECT DESCRIPTION: Pool resurfacing, tile replacement, selective equipment replacement, deck coating and painting.
BY THIS BOND, We Khors Construction, Inc., as Contractor, and FCCI Insurance Group Surety, a corporation, as Surety,
are bound to the City of Clearwater, Florida, herein called Owner, in the sum of (8449,077.51) four hundred, forty-nine
thousand, seventy-seven and 51/100 dollars for payment of which we bind ourselves, our heirs, personal representatives,
successors, and assigns, jointly and severally.
THE CONDITION OF THIS BOND is that if Contractor:
1. Performs the proposal dated May 26, 2021, between Contractor and Owner for construction of the Ross Norton
Recreation Center Main Pool, Plunge Pool and Activity Wade Pool Renovation, the contract documents, being made a part of
this bond by reference (which include the Contract, Surety Bond, Plans and Technical Specifications, and such alterations as
may be made in said Plans and Specifications as therein provided for), at the times and in the manner prescribed in the contract;
and
2. Promptly makes payments to all claimants, as defined in Section 255.05(1), Florida Statutes, supplying Contractor
with labor, materials, or supplies, used directly or indirectly by Contractor in the prosecution of the work provided for in the
contract; and
3. Pays Owner all losses, damages, expenses, costs, and attorney's fees, including appellate proceedings, that Owner
sustains because of a default by Contractor under the contract; and
Bond No.:
PUBUC CONSTRUCTION BOND
(2)
4. To the limits of § 725.06(2), Florida Statutes, shall indemnify and hold harmless Owner, their officers and employees,
from liabilities, damages, losses and costs, including, but not limited to, reasonable attomey's fees, to the extent caused by the
negligence, recklessness, or intentional wrongful misconduct of Contractor and persons employed or utilized by Contractor in
the performance of the construction contract; and
5. Performs the guarantee of all work and materials furnished under the contract for the time specified in the contract,
then this bond is void; otherwise it remains in full force.
6. Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time
limitation provisions in Section 255.05(2), Florida Statutes.
7. Any changes in or under the contract documents and compliance or noncompliance with any formalities connected
with the contract or the changes does not affect Surety's obligation under this bond, and Surety does hereby waive notice of
any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.
IN TESTIMONY WHEREOF, witness the hands and seals of the parties hereto this day of
20
of sole Ownership or Partnership, two (2) Witnesses required).
(If Corporation, Secretary only will attest and affix seal).
Khors Construction. Inc.
BY:
Title:
WITNESS: WITNESS:
Corporate Secretary or Witness Print Name:
Print Name:
(affix corporate seal) FCCI Insurance Company
(Power ofAttorney must be attached)
Print Name:
BY:
ATTORNEY-IN-FACT
Print Name:
(affix corporate seal)
Phase 2 Request for Proposal Ross Norton Pool Renovations 1426 S. Dr. Martin
Luther King Ave. Clearwater, FL 33756
ARMC name: Khors Construction, Inc. Contact Person: Kori Khorsandian
Address of ARMC: 6251 44th Street N Ste.1909 City Pinellas Park
State: FL Zip Code:
Contact: Tel: 727470-7352 Moble: 813-728-3689
E-mail: khorsconst@gmai.com Date: 7 21
Signature: 7j1
LUMP SUM PRICE BID_ IF THERE IS AN ERROR IN THE TOTAL BY IT SHALL D AS ONLY
THE UNIT PRICES AN) LUMP SUM PRICE SHALL GOVERN_ THE CITY RESERVES THE RIGHT TO ELIMINATE ANY
LINE ITEM AND May NOT ACCEPT PROPOSAL PROVIDED. ARCM SHALL HOLD FNS PRICES FROM DATE OF
SUBMISSION OF HIS PROPOSAL UNTiL CONTRACT AS BEEN AWARDED BY CITY COUNCIL_ TFE CONTRACTOR
SHALL PROVIDE COPIES OF A CURRENT CONTRACTOR LICENSE/REGISTRATION MATH THE STATE OF FLORIDA
AND PiNELLAS COUNTY IN THE BID RESPONSE_
Item
No.
I Description
Units
QTY
Unit Cost
Total Cost
1
2
Bonding and Mobization incudes draining all pool requirements
in preparation of pool construction (see note on drawings regards
to draining pool).
Removal and reinstal al pool furniture (ladders, hand rails. back
stroke poles diving board & platforms) remove bond wire and
protect for reinstalation of pool furniture. Store and protect on
site for reinstallation_
LS
LS
1
1
$ 30,317.04
$ 1476.00
$ 30,317.04
$ 1.476.00
3
Remove and replace lap diving pool bean per details on page 7
of 13 Typ_ Gutter Wal & Wall Detail and Man pool Beam Detail
electrical pond reinforcement per NEC code. Protect pool aeration
system on east side of pool during construction of pool beam
water exit ports shall have continuous stream of water and all shall
be matching.
LF
322
S 116.85
5 37,625.70
4
Relevel pool gutter with only 114" tolerance on all sides of pool.
LS
1
$ 3.874.50
S 3,874.50
5
Demnoiition of pool all ties and pool existing surfacing of all
delarmatng materials by sand blasting or mechanical means,
sound surface for holow spot and remove, which incudes staff
and handicap ramp_ See instructions on sheet 4 of 13 Pool
Resurfacing Notes and Specifications for preparation of existing
pool surface for Hydrazo surfacing material. Remove and replace
expansion joint see detail sheet 7 of 13.
LS
1
$ 13,630.86
$ 13,630.86
6
Remove and replace pool 2`x4' gutter fittings with new Pentair
540063 - submit sample to Engineer and Owner review
EA
33
$ 33.21
$ 1,095.93
7
Remove and replace cup rope anchors - submit sample to
Engineering & Owner review
EA
14
$ 131.61
S 1,842.54
8
Remove and replace floor returns with new Pentair 1425 submit
sample to Engineer and Owner Review
EA
18
S 123.00
S 2,214.00
9
Remove and replace floor drain to meet ASME/ANSI A112 19
82009 NSF50 64E-9 for anti -entrapment_ Submit sample to
Engineer & Owner.
EA
2
$ 33825
$ 676.50
10
Remove and replace vacuum fittings with new Hayward VAC LOC
vacuum safety fittings with spring loaded safety cover, provide
sample to Engineer and Owner for review.
EA
2
$ 123.00
$ 246.00
11
Rebuid stairs as necessary to meet current pool code
requirements. See sheet 7 of 13
LS
1
S 738.00
$ 738.00
12
Pool Crack repair Invith Torque Lock Crack Repair Kits as required -
submit sample to Engineer and Owner review_
EA
2
$ 1,230.00
$ 2,460.00
13
New depth and no dive markers non sip ties per detail and
notes sheet 8 of 13 - submit samples for review by Engineer and
Owner
EA
14
S 46.74
S 654.36
14
Install all required porcelain ties as cal out on the drawings, tie
color shall be black unless otherwise noted, which incudes stairs
and handicap ramp_ Non sip ties are required as noted on
drawing sheets 6 of 13, 7 of 13, 8 of 13, and 11 of 13 for entie
lapldivug wel pool ARMC shal instal 6 lap lane markers
east/west, north/south lane markers have been eiminated from
main podldiving wet Include depth marker on pool gutter area 14
locations matching beam marker locations of pool gutter - submit
samples to Engineer and Owner for review.
LS
1
$ 20,971.50
$ 20.971.50
15
Submit ties for approval of non sip tie requiement; dile
manufacture cannot provide documentation ARCM shat submit
ties to Product Performance Testing Lab on sheet 8 od 13 is
contact information to test ties to meet Wet Dynamic Coefficient of
Friction (DCOF) to test ties report and sample ties shall be
provide to Engineer and Owner review and they wit submit to
DOH Pinellas County for their review. Note approved ties shall be
use on all pool of this project
LS
1
$ 6.15
$ 6.15
16
Not Used
17
Remove and replace expansion joint material around pool beam,
dean out existing expansion joint dean surface with cleaning
agent, instal backer rod to allow 3/4' depth cauic, uti¢e vutkpm
caulk to fir expansion join and tool finish to smooth concave joint
Provide sample for approval by Owner & Engineer prior to
perfomirg the work_
LF
322
$ 4.66
$ 1,501.07
18
Instal hydrazo pool surface of lap pool and diving well
LS
1
$ 48,757.20
$ 48,757.20
19
ProlAnnent Chemical Feeder Board remove and replace lower
flow meter, Ph meter and Chlorine meter and replace with new
total of 3 units
EA
3
$ 4,828.98
$ 14,486.94
20
Mechanical yard aeration system of main pool dean and recoat
tanks check all pumps are operational and chemical feeds are
operational replace hair strainers basket and titer as necessary,
check all pkrmbing is in good work order or replace as necessary
replace 3 inch valve precoat and vacuum teres replace al
handles deteriorated.
LS
1
$ 1,845.00
S 1,845.00
21
jet
contract
ARMC shall fir pool upon completion of hydrazo surfacing is
complete Owner shall supply water meter for fire hydrant. ARMC to
provide necessary temporary piping from provided water meter to
fil all pools Upon completion of fang pool ARMC to brush pool to
remove loose material and vacuum loose debris, polish pool
surface and dispose off site. ARMC to start up pool equipment to
ensure all pool mednanicallelectrical components indudng
chemical feeders are functioning properly and make all necessary
repais and adjustments as required. Check Aeration exit ports
that they are dear of any debris and are providing a continuous
stream of water, all stream of water shall be matching existing
port. ARMC shall balance pool chemistry to meet minium pool
balancing five days prior to requesting DOH Pinelas County to
Certify Pool Operation ARMC shat take al necessary actions to
satisfy DOI- PC to certify the pool of operations as part of this
at no additional expense to the Owner. Pool chemicals
shall be provided by the Owner to balance the pool chemicals for
pool operation certificate_ Clean up site of any construction debris
dispose off site, dose out budding permit and contract between
. air,.. •.:n
LS
1
$ 4,345.00
$ 4,345.00
22
2 inch trench drain remove grate and replace - clean drain remove
and sit and dispose off site power wash drain and instal new
drain cover will stainless steel 316 screws.
LF
66
$ 47.97
$ 3,166.02
23
LINE 23 NOT USED
24
Alt
Main pool decking remove al existing loose acryic decking
surface by power washing with 4,000 psi power washer, prepare
surface for instalation of Polymer Modified Deck Spray material
(decorative deck coating) by MERKRETE, see specifications,
provide 5' x 5' texture surface sample for Owner approval, instal
deck coating and allow to cue, apply exterior concrete stain
Perms- Crete both products by PPG Industry material located
iocay on Cleveland Street, Clearwater, FL_ provide stain color for
approval by Owner_
SF
6,860
$ 7-40
S 50,795.56
25
Alt
Lee 25 Not Used
26
27
Line 26 Not Used
Removal and renstal al pool furniture (ladder & hand rails)
remove bond wire and protect for reinstalation of pool fumiture_
Store and protect on site for renstafation_
LS
1
$ 615.00
$ 615.00
28
Demoition of pool al ties and pool existing surfacing of al
deaminatirg materials by sand blasting or mechanical means,
sound surface for holow spot and including staffs rebuidng as
necessary_ See instructions on sheet 4 of 13 Pool Resurfacing
Notes and Specifications for preparation of existing pool surface
for Hydrazo surfacing material. Note depth markers on pool beam
to remain and protected durng pool renovations i damaged
during renovations it is the responsibly of the ARMC to replace at
his own expense and no additional funds shal be provided by the
LS
1
$ 2,140.20
$ 2,140.20
29
Check skimmers are functioning properly and replace parts as
necessary provide new strainer and top covers flush with pool
beam. - submit sample to Engineer and Owner review
EA
2
$ 123.00
$ 246.00
30
Remove and replace floor returns with new Pentair 1425 submit
sample to Engineer and Owner Review
6
$ 123.00
$ 738.00
31
Remove and replace floor drain to meet ASME/ANSI A112 19
&2009 NSF50 64E-9 for anti -entrapment. Submit sample to
Engineer & Owner.
EA
3
$ 235.75
$ 707.25
32
Remove and replace rope cup anchors submit samples for review
by Engineer and Owner.
EA
2
$ 184.50
$ 369.00
33
Remove and replace vacuum fittings with new Hayward VAC LOC
vacuum safety fittings with spring loaded safety cover.
EA
1
$ 123.00
$ 123.00
34
Instal al required porcelain ties as cal out on the drawigs, tie
color shal be black unless otherwise noted, which includes stars.
Non sip ties are requited as noted on drawing sheets 6 of 13, 7
of 13, 8 of 13 and 11 of 13 for plunge pool. Include depth
marker on pool waterline tile 6 locations matching beam marker
locations of waterline tie - submit samples to Engineer and
Owner for review.
LS
1
$ 6,368.94
S 6,368.94
35
Instal hydrazo pool surface of plunge pool see sheet 4 of 13
LS
1
$ 8,019.60
$ 8,019.60
36
Feature slide mechanical yard - pumping station at pod side
clean recoat tank as requited, check electrical components are
functioning properly and replace valve handles with new, clean
mechanical yard of plants, and provide additional crush shel level
area within mechanical yard.
LS
1
$ 3,075.00
$ 3,075.00
37
Mechanical flerig yard: remove and replace DE filters in-kind,
recoat tanks as required; remove and replace al handles of
valves hair strainers baskets with new
LS
1
$ 3,013.50
$ 3,013.50
38
Prolainnent Chemical Feeder Board remove and replace lower
flow meter. Ph meter and Chorine meter and replace wih new
total of 3 units
EA
3
$ 4,097.94
5 12,293.83
39
Remove and replace valve handles b-kind.n Main titration tanks Mechanical yard.
in
2
$ 123.00
$ 246.00
40
41
ARMC shall fill pool upon completion of hydrazo surfacing is
complete Upon completion of filing pool ARMC to brush pool to
remove loose material and vacuum loose debris, poish pool
surface and dispose off site. ARMC to start up pool equipment to
ensure al pool mechanical/electrical components including
chemical feeders are functioning properly and make all necessary
repairs and adjustments as required. ARMC shall balance pool
chemistry to meet minimum pool balancing five days prior to
requesting DOH Pinellas County to Certify Pool Operation ARMC
shat take all necessary actions to satisfy DOHPC to oertgy the
pool of operations as part of this contract at no additional
expense to the Owner. Pool chemicals shat be provided by the
Owner to balance the pool chemicals for pool operation certificate_
Clean up site of any construction debris dispose of site, dose out
buiding permit and contract between ARCM & Owner.
Existing shade canopy over plunge pool (west side) cut concrete
6 inch %aide both sides of metal shade canopy supports poles at
base at two locations; remove concrete; prep base of post for
painting (see drawing sheet 4 of 13) prep metal of shade canopy
and pant one coat of primer and two coats of with high gloss
PPG pant Amercoat White TDS (primer) PPG PSX white TDS
one part epoxy or equal, painting specifications and preparation
for painting; provide paint color sample to Owner for approval.
Form up concrete opening and instal 5,000 psi non shrink grout
provide medium broom finish.
LC
lS
1
1
$ 1,307.50
$ 4,678.92
$ 1,307.50
$ 4,678.92
42
Side tower stairs assembly remove rust to bare metal, prepare all
metal, repair stair pan remove al rust to bare metal, prine and two
coats of PPG Amercoat White TDS (primer) PPG PSX white TDS
one part epoxy or equal, painting specifications and preparation
for painting
LS
1
$ 4,723.20
$ 4,723.20
43
Feature side structure remove rust to bare metal and repaint
feature side structure as necessary - remove and replace rusted
bracket and paint same as item 43 above
LS
1
$ 6,642.00
$ 6,642.00
44
Remove and replace expansion joint material around pool beam
plunge pool (115 LF), clean out existing expansion joint clean
surface with cleaning agent. instal backer rod to allow 3/4' depth
Vutkem caulk, utize vacuum caul to Si expansion joint and tool
finish to smooth concave joint. Provide sample for approval by
Owner & Engineer prior to performing the work.
LF
115
$ 4.66
$ 536.10
45
Pool deck remove and replace expansion joint materials on
existing concrete flat work of al pool deck areas (main lap/diving
wel, activity, and plunge pools dean out existing joints, dean
surface with cleaning agent Intal backer rods as necessary
(Including any deck openings 1/4' to 3/4' widths) install Sica self
Lelveing cauk to rill expansion joints and level to adjcent
concrete surfaces_ Provide sample for approval by Owner &
Engineer prior to perfonneng the work.
LF
350
5 4.66
$ 1,631.60
46
adjeent
Al pool deck cracks (lap/diving well, activty, plunge pools; some
areas have existing cauls installed) remove exisitng caul, route
dean out existing cracks of loose material clean with cleaning
agent, fir cracks with Sica Self Levefng cauls and level with
concrete surfaces Provide sample for approval by Owner
& Engineer pror to perforating the work
LF
850
$ 4.66
$ 3,962.45
•
47
48
Pool Deck surrounding plunge pool deck area and plunge pool
beam power wash with 4,000 PSI power washer, instal Master
Protect BASF H 1000 water repellant sealer (see specifications).
Provide sample area for Owner approval
Power wash shade canopy and remove and store on sae and
reinstall (by Owner; prep metal of shade canopy and pant one
coat of primer and two coats of with high gloss PPG paint
Amercoat White TDS (primer) PPG PSX white TDS one part epoxy
or equal, painting specifications and preparation for painting;
provide paint color sample to Owner for approval Reinstall shade
canopy.
SF
EA
2,700
2
; 2.77
$ 2,199.24
$ 7,47225
$ 4,398.48
49
Remove side panels and cargo netting. by painting or cleaning or
replacement store and protect on site for reinstalation, make
repairs to activity feature: north upper spray feature western two
water ports appear not provide same stream of water as others
clean offices as required. Water feature valves wih pull ropes
check if valves are sticking and dean as necessary to function
p1ope. Instal three new ropes with rope pull handles. Provide
one extra rope as spare_ Provide sample of rope for Owner
review_ Repaint play structure with high gloss paint prime and two
coats of PPG Amercoat White IDS (primer) PPG PSX white IDS
one part epoxy or equal, pairing specifications and preparation
for painting; provide paint color sample to Owner for approval. per
manuratures recommendations - reinstal all parts_
LS
1
$ 4,324.68
$ 4,324.68
50
Fiber glass play activity (tube side & rain drop material feature)
componet and Raindrop waterfall structure shall be leaned.
Prepped and painted with Arnberloclk 2 primer one coat and two
coats of Sigmracover 2 finish coats, follow manufactures
recommendations for resurfacing ngg fiberglass componets.
LS
1
$ 2,027.04
$ 2,027.04
51
Demolition of pool all ties and pool existing surfacing of all
dearnnatng materials by sand blasting or mechanical means,
sound surface for hollow spot and including stairs rebuidig as
necessary. See instructions on sheet 4 of 13 Pool Resurfacing
Notes and Speriications for preparation of existing pool surface
for Hydrazo surfacing material Note depth markers on pool deck
to remain unless they are cracked replaanaent is required and
those not packed shal be protected during pool renovations if
damaged during renovations it is the responsibly of the ARMC to
replace at his own expense and no additional funds shall be
ornvirled by the Owner
LS
I
$ 3,129.12
$ 3.129.12
52
Remove and replace floor returns with new Pentair 1425 submit
sample to Engineer and Owner Review
EA
16
$ 123.00
$ 1,968.00
53
Remove and replace pool 2'x4' gutter fittings with new Pentair
540063 - submit sample to Engineer and Owner review
EA
16
$ 29.52
$ 47232
54
Remove and replace floor drain to meet ASME!ANSI A112 19
82009 NSF50 64E-9 for anti -entrapment Submit sample to
Engineer & Owner.
EA
4
$ 233.70
S 934.80
55
Install all required porcelain ties as call out on the drawings, tie
color shall be black unless otherwise noted. Non sip ties are
required as noted on drawing sheets 6 of 13, 7 of 13, 8 of 13,
and 11 of 13 for activity pool. - submit samples to Engineer and
Owner for review.
LS
1
$ 17,183.10
$ 17,183.10
56
Remove and replace vacuum fittings with new Hayward VAC LOC
vacuum safety fittings with spring loaded safety cover.
EA
1
$ 123.00
$ 123.00
57 Install
Hydrazo pool surface of activity pool see sheet 4 of 13
IS
1
S 10.617.36
$ 10,617.36
58
ARMC shall ti pool upon completion of hydrazo surfacing is
complete Upon completion of filing pool ARMC to brush pool to
remove loose material and vacuum loose debris. poish pool
surface and dispose off site. ARMC to start up pool equipment to
ensure all pool mechanicallelectrical components including
chemical feeders are functioning properly and make all necessary
repairs and adjustments as required. ARMC shall balance pool
chemistry to meet minimum pool balancing five days poor to
requesting DOH Pinellas County to Cerny Pool Operation ARMC
shall take all necessary actions to satisfy DOHPC to certify the
pool of operations as part of this contract at no additional
expense to the Owner_ Pool chemicals shall be provided by the
Owner to balance the pool chemicals for pool operation certificate.
Clean up site of any construction debris dispose of site, dose out
buidng permit and contract between ARCM & Owner.
IS
1
$ 1,307.50
5 1,307.50
59
Install interactive play features provided by Owner see sheet 13 of
13 installation detail
EA
10
$ 553.50
S 5,535.00
60
Activity pool mechanical yard - pumping station clean recoat tank
as required, remove and replace DE filters in-kind, check electrical
components are functioning properly
LS
1
$ 3,075.00
$ 3,075.00
61
62
Prohinnent Chemical Feeder Board remove and replace lower
flow meter. Ph meter and Chlorine meter and replace with new
total of 3 units
Activity pool back wash pump replace filter assembly
EA
EA
3
1
S 4,097.94
$ 3,013.50
S 12,293.83
5 3,013.50
63
Activity pool No. 1 return valve and No. 4 precoat valve, playEA
feature valves replace handles in-kind
4
S 147.60
$ 590.40
64water
65
Pool Deck surrounding activity pool deck area power wash with
4,000 PSI power washer, instal Master Protect BASF H 1000
repeiant sealer (see specifications)_ Provide sample area for
Owner approval.
Remove titers to instal valvies and reinstall filters_ Remove three
existing 6 -inch butterfly valves for main drain and gutter and
piping through filter tank wall and install new valves and piping
and reseal around pipes to ensure no leaks_ Repturnb return ire
inside pump room and install two new four -inch butterfly valves for
to heat and from heat Install new 6 -inch butterfly valve for pre--
coat Reinstall existing flow meter and chemical injection ports in
proper location with new damps and Stenner tubing. Install new
tempaerature guage, Al valves to have stainless steel hardware.
Reinstall 6" pipe support_
SF
LS
2,550
1
S 2.77
$ 18,566.85
5 7,057.13
S 18.566.85
66Sub
Total of Items 1 - 65
$ 408,25228
67
10% Contingency of Line 65 Contingency funds shall only be
utilmed for items not included in the scope of work (lines 1-67),
additional scope of work shall be provided in writing by the
ARCM for approval by the Owner. Owner must approve
0.1
$ 40,825.23
additional scope of work in writing for utilization of
contingency funds. Any contingency funds remaining shall be
returned to the Owner by closing out purchase order short
68 IGrand
total of lines 66 & 67 includes contingency.
$ 449,077.51