ADMINISTRATIVE CHANGE ORDER #1 & FINAL - DAVID AVENUE PROPERTY STORMWATER IMPROVEMENTS - 20-0002-ENAdministrative Change Order 1 & Final DATE:
PROJECT: PROJECT NUMBER:
David Avenue Property Stormwater Improvements PO REFERENCE:
CONTRACTOR:
Keystone Excavators
371 Scarlet Blvd
Oldsmar, FL 34677
September 30, 2020
COUNCIL AWARD:
DATE OF CONTRACT
20 -0002 -EN
20000848
April 16, 2020
April 20, 2020
CODE: ENST 180005-CONS-CNSTRC
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
decreasing, increasing and adding items in accordance with field conditions to close the contract -see attache;;
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY Keystone Ex,a ators•
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 & Final - City Manager
NEW CONTRACT AMOUNT
APPROVED AS TO FORM:
Owen Kohler,
ATTEST:
0 ac.
Rosemarie Call,,p ,,
Date: 2)i Y` 4 .2-P0-)"()
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
$ 1,025,378.20
$ (57,912.20)
$ 967,466.00
Assistant City Attorney
By:,Z4/� ' ' a SEi i:)
Robert Fornwali 4sid'et t
(7¢ �! e
Date:r,-- ,
Witnesses:
ecommended By:
ity of Clearwater
Ivan Dimitrov, Project Manager
William B. Horne, II
City Manager
Tara Kivett, PE,
City Engineer
Administrative Change Order 1& Final David Ave Property Stormwater Improvements
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
10 Demolish Manhole (at North End) LS 1 $ 5,400.00 $ (5,400.00)
17 Modify/Connect to Existing Manhole at LS 1 $ 6,514.00 $ (6,514.00)
South End
27 Contingency 1 $ 89,437.20 $ (89,437.20)
Total (Decreases): $ (101,351.20)
Increases:
18 Replace Tops at Storm structure EA 1 $ 2,200.00 $ 2,200.00
20 Sabilized Roadway, Access For Liner Sub SY 627 $ 8.00 $ 5,016.00
22 Fence, gates -- Take Down, RE -Set At End LF 100 $ 22.00 $ 2,200.00
26 Liner Sub, See Attached Quote From LS 0.0412 $ 759,792.00 $ 31,273.00
Granite Inliner
Total Increases: $ 40,689.00
Additions:
28 Headwall EA 1 $ 2,750.00 $ 2,750.00
Total Additions: $ 2,750.00
Total Net (Decreases)/Increases/Additions: $ (57,912.20)