2019 CITY SEAWALLS - 19-0021-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final Date:
PROJECT:
2019 City Seawalls
CONTRACTOR:
Waterfront Engineering, Inc
3940 Fountainebleau Dr
Tampa, FL 33634
PROJECT NUMBER:
PURCHASE ORDER:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
July 10, 2020
19 -0021 -EN
19001744
September 5, 2019
October 31, 2019
ENGF 180006-CONS-CNSTRC
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases, increases and additions in accordance with field conditions to close the project -see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1&Final-City Manager
NEW CONTRACT AMOUNT
APPROVED AS TO FORM:
L
4.7
Owen Kohler,
LC,a 'C,
Rosemarie Call,
ACCEPTED BY: Waterfront Engineering , Inc.
$ 254,710.50
$ 11,690.22 ; By: 1
41
$ 266,400.72 Jan A
Assistant City Attorney
Date:
",,,,, AMANDA ANSEEUW
'•��:Notary Public -State of Florida
•' Comm(pk# GG 362620
"�r....ice Pvks' ion Expires
»<ist)5, 2023
(0
Witnesses: (tw
a,'A
....
AiViANDA ANSEEUW
Notary Puotic-S'a 3 o! t lorida
umr issior 4 t_: , 61620
My Coma- :1r7), Expires
• 7_3
ttt
Recommended By: City of Clearwater
Date: l �G( L -3 I, ..)-Ox)
CffY
)-r-
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
Project Manager
Tara
7a/frit
� , City Engineer
Page 2 of 2
Administrative Change Order 1&Final: 2019 City Seawalls
ITEM DESCRIPTION UNH all UNIT COST TOTAL COST
Decreases:
38 Ground prep & sod. SF 225 $ 1.50 $ (337.50)
46 10% Contingency LS 1 $ 23,155.50 $ (23,155.50)
Total (Decreases): $ (23,493.00)
Increases:
4 NE, SE & SW Walls — Installation of PV EA 2 $ 150.00 $ 300.00
10 SW Wall — Vegetation Removal: (1) LS 0.4 $ 700.00 $ 280.00
Brazilian Pepper, (I) Oleander and (3)
Palm Trees.
11 Ground prep & sod. SF 761 $ 1.50 $ 1,141.50
16 SE Wall - Removal and disposal of all LF 1.5 $ 600.00 $ 900.00
debris of indicated seawall and seawall
cap along with installation of vinyl sheet
piles, filler concrete, cap tiebacks and
30" wide x 14" high concrete seawall
cap per plan specifications.
22 NE, NW & SE Walls — Installation of EA 3 $150.00 $ 450.00
PVC drains per plan specifications.
33 Removal and disposal of all debris of LS 18 400 $ 7,200.00
indicated seawall cap along with
repouring 19'3" +/- LF of 20" high x
16" wide seawall cap per plan
specifications.
42 North Side — Installation of sheet piles LF 37 $ 250.00 $ 9,250.00
per plan specifications.
43 North Side — Installation of tieback LS 0.318965 $ 8,000.00 $ 2,551.72
system per plan specifications.
44 North side — Filler concrete and capping LF 37 $ 180.00 $ 6,660.00
per plan specifications.
Additions:
47 Windward Passage Bridge 155518- LS
S.E.C.,Perform similar as 270 Skiff
Point: A depressed area behind the pipe
needs to be excavated about 4' below
cap for a visual inspection and check
pipe for a break. Istall pipe collar and
grouting along with any additional work
to restore the area including fill and or
sod
48 Vinyl Corner Sheet needed per revised plans. EA
49 12" Florida Lime Rock - 6' wide x 8' long x LS
18" Deep on Filter Fabric at Stormwater
Outfall per revised plans.
Total Increases: $
1 $ 2,500.00 $
1 $
1
28,733.22
2,500.00
1,200.00 $ 1,200.00
2,750.00 $ 2,750.00
Total Additions: $
6,450.00
Total Net (Decreases)/Increases/Additions: $ 11,690.22