SOLID WASTE TRANSFER STATION REPLACEMENT PROJECT - 15-0007-SW - ADMINISTRATIVE CHANGE ORDER #2 & FINALAdministrative Change Order 2&Final
PROJECT:
Solid Waste Transfer Station
CONTRACTOR:
Kokolakis Contracting
202 East Center Street
Tarpon Springs, FL 34689
DATE: May 1, 2020
PROJECT NUMBER: 15 -0007 -SW
CONTRACT: 900292
COUNCIL AWARD: November 16, 2017
DATE OF CONTRACT: November 20, 2017
CODE: SRTS180001-CONS-CNSTRC
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
decrease and increases items in accordance with field conditions to close the contract - see attached
STATEMENT OF CONTRACT AMOUNT
Original Contract $ 17,832,010.00
Admin Change Order 1&Final-City Mgr 9/19/2019 $ (1,062,684.96)
Admin Change Order 2&Final-City Manager $ 55,867.49 0.003
New Contract Amount $ 16,825,192.53
P
D AS TO.FQRM:
L /
Owen Kohler,
(
ATTEST: nn
L- Wks.
Rosemarie Call,
Date: ' G(. ce_ J-0
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
/ JL i . /6644A -Q a t t
William B. Horne, II City Manager Tara Kivett, P , City Engineer
Assistant City Attorney
ACCEPTED BY: Kokolakis Contracting
Date: zoyv. es -;z0
III%IIIIII1///j//
Project• /-COOONRTARE/\
0
Q• `' SEAL T
1988
o
k\
t o OR'O`P����\���
#1111
Recommended By:
City of Clearwater
Catherine Corcoran, Project Manager
Administrative Change Order 2&Final Solid Waste Transfer Station
ITEM
DESCRIPTION
Decreases:
17 Contingency
Increases:
2 Existing Conditions
3 Concrete
5 Metals
8 Openings
9 Finishes
11 Equipment (crane, CNG filling station, pit
13 Special Conditions (metal blg., leachate tat
15 Mechanical
16 Electrical
UNIT UNIT COST TOTAL COST
LS 1 $ 350,000.00 $ (350,000.00)
Total (Decreases): $ (350,000.00)
LS 0.05 $ 4,443,854.00 $
LS 0.002 $ 3,930,839.45 $
LS 0.085 $ 734,837.00 $
LS 0.01 $ 194,319.00 $
LS 0.031 $ 181,735.00 $
LS 0.109 $ 540,991.59 $
LS 3E-04 $ 1,172,669.00 $
LS 0.043 $ 686,097.00 $
LS 0.013 $ 1,393,076.00 $
220,651.20
7,547.40
62,710.63
1,998.43
5,643.75
58,800.78
322.02
29,441.20
18,752.08
$ 405,867.49
Total Net (Decreases)/Increases: $ 55,867.49