KAPOK TERRACE SANITARY SYSTEM PROJECT - 15-0036-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1&Final
PROJECT:
Kapok Terrace Sanitary Sewer System
CONTRACTOR:
Suncoast Development of Pinellas County, Inc.
2340 Destiny Way
Odessa, Fl 33556
Date: March 3, 2020
PROJECT NUMBER:
CONTRACT:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
15 -0036 -UT
900339
October 19, 2017
November 14, 2017
3217321-563800-96630 A
ENST 180006-CONS-CNSTRC B
ENRD180005-CONS-CNSTRC C
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
decreasing, increasing and adding items in accordance with field conditions to close the project -see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1&Final- City Manager
NEW CONTRACT AMOUNT
ATTEST:
ACCEPTED BY:
Suncoast Development of Pinellas County, Inc.
$ 3,926,032.00
$ (306,781.76) By:
$ 3,619,250.24 Charles Cerullo,
ON ATP?
0 at_ 84„,::.;, ..... ,...7"4,$) .
,` a
` r , 148';'.914.: 'IS ; . ....)
Rosemarie Call,
Date: -4'I &L,.- -3-1,..)-0.3-0
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
IA) -LB Ipt A.ii,„-dr
William B. Horne, II
APP VED AS TO FORM:
City Manager
Owen Kohler,
Assistant City Attorney
Date:
Witnesses: (two)
(Seal)
President
ecommende
y of Clearwater
(41 -AI I)/ At (T(2_6' (/
Ivan Dimitrov Project Manager
-��,,``
Tara Kivett, PE, City Engineer
Page 2 of 3 Administrative Change Order l&Final Kapok Terrace Sanitary Sewer System
Item Description Unit Ouantity Unit Price Total Cost
Code A:
1)4.., rras.e�:
3 Furnish and Install 8" PVC SDR -35 Gravity LF 80 79.50 16, 360.1)1))
Sewer Pipe
13 Removal and Installation of Street Lateral to EA 2 1,000.00 12.000.1)0)
New Sewer Main
14 Furnish and Install 1 -inch of SP -9.5 Asphalt SY 3.20952381 8.40 126.06 )
(Phase 1 Restoration)
18 Furnish and Install Sewer Service Lateral 51' EA 14 3,800.00 453.200.00)
- 100'
23 Root Pruning LF 863 7.00 16.041.00)
24 Tree Removal Trunk Diameter 4 -inch to 12- EA 7 200.00 41.400.00 )
inch
29 Pinellas County Sewer Lateral Connection LS 0.819 15,000.00 412.285.0M
Building Permit Fee Allowance
31 Furnish and Install Relocated Water Main - LF 50 70.00 13.500.004
6" DIP
32 Furnish and Install Ductile Iron Fittings TON 1.434 15,000.00 121.510.00)
33 Replace Water Service Lateral Pipe EA 114 550.00 462.700 0444
34 4" MJ RWGV EA 2 650.00 1 1.3110.1H)1
35 6" MJ RWGV EA 2 920.00 41.840.004
36 Furnish and Install 4" Line Stop EA 2 3,000.00 16.000.004
37 Furnish and Install 6" Line Stop EA 2 5.000.00 410.000.004
38 10 % Contingency Sanitary Sewer System LS 1 249,424.00 C40.-124.004
)
Total i I )C . rea sv % ): (43'386.96)
Increases:
4 Furnish and Install 8" Ductile Iron Gravity LF 32 96.50 3,088.00
Sewer Pipe
5 Furnish and Install 14" Steel Casing Pipe LF 7 100.00 700.00
6 Remove Existing 8" PVC Sanitary Sewer LF 25 10.00 250.00
Pipe
16 Furnish and Install 1 -inch pf SP -9.5 Asphalt SY 3518 8.40 29,551.20
17 Fumish and Install Sewer Service Lateral EA 1 1,800.00 1,800.00
<50'
19 Furnish and Install Sewer Service Lateral EA 9 4,800.00 43,200.00
101'- 150'
20 Furnish and Install Sewer Service Lateral EA 4 6,100.00 24,400.00
151-200'
22 Furnish and Install Flowable Flow CYD 55 160.00 8,800.00
26 Tree Removal Trunk Diameter 25 -inch to 36- EA 3 2,500.00 7,500.00
inch
27 Tree Removal Trunk Diameter 37 -inch to 48- EA I 5,000.00 5,000.00
inch
Total Increases: 124,289.20
Additions:
70 3006 Merrill Ave. Street Lateral and LS I 2,829.00 2,829.00
Cleanout
71 Wolfe Rd. Water Main Relocation LS 1 19,270.00 19,270.00
72 Pipe Encasement LS 1 3,025.00 3,025.00
73 Concrete Pipe Supports LS 1 2,579.00 2,579.00
Page 3 of 3 Administrative Change Order I&Final Kapok Terrace Sanitary Sewer System
Item Description Unit Ouantitv Unit Price Total Cost
74 Lateral Connections through Septic Tanks EA 5 1,000.00 5,000.00
75 Valley Gutter Curb LF 1453 35.00 50,855.00
Total Additions: 83,558.00
Total Net 1I)cci,a,c.t/Increases/Additions Code A: (229:39.-6)
Code B:
Reerea,e.:
42 Furnish and Install 18" RCP Storm Sewer LF 6 69.50 , c ''11''
Pipe
43 Furnish and Install 24" RCP Storm Sewer LF 20 81.50 < i t * 1' "t 1
Pipe
44 Furnish and Install 30" RCP Storm Sewer LF 6 101.50 1600•04' t
Pipe
45 Furnish and Install 12"x18" RCP Storm LF 6 59.50 (:57.001
Sewer Pipe
46 Furnish and Install 24"x38" RCP Storm LF 112 110.00 112.321) ui1►
Sewer Pipe
47 Furnish and Install 8" Underdrain and LF 30 31.50 (945.00)
Cleanout
52 Furnish and Install FDOT Concrete Rubble SF 10 25.00 (25o iliii
Riprap
53 Existing Storm Structure Removal EA 1 1,200.00 1 1.2011.001
55 Existing Underdrain Removal LF 1909 6.00 01.4510w
56 10% Contingency Stormwater System LS 1 29,992.00 t 2'►.'►9' ' ►01
Total 1 Dec rca.e,1: (5').1'4.11(► I
Code B Increases:
41 Furnish and Install 15" RCP Storm Sewer Pip LF 24 59.50 1,428.00
54 Existing Storm Sewer Removal LF 44 15.00 660.00
Total Increases: 2,088.00
Additions:
76 Moss Avenue Valley Swale Curb LS 1 13,970.00 13,970.00
77 Moss Avenue Intersection LS 1 11,925.00 11,925.00
Total Additions: 25,895.00
Total Nett Decrea.e.)/Increases/Additions Code B:
t31.191.1I(0
Code C
Decreases:
62 Pavement Marking/Signage LS 1 11,500.00 t 1 1.501).110►
63 Fumish and Install Sidewalk ADA Ramp EA 1 2,700.00 12,700 (Hi)
69 10% Contingency Roadway Modifications LS 1 77,496.00 (77.-196•01)1
Total t Ilecrea.c,1: (91,696.1111)
Increases:
68 Merrill wall (AAR No.5) LS 0.032923077 162,500.00 5,350.00
Total Increases: 5,350.00
Additions:
69 Driveways on Merrill Ave SF 2430 6.00 14,580.00
79 Lake Vista & Moss Ave. Re -grading EA 1 21,775.00 21,775.00
69 Concrete Bewteen Wall And Curb SF 690 6.00 4,140.00
Total Additions Code B: 40,495.00
Total Net 11►crrra.c,►/Increases/Additions Code C: 145.851.0111
Total Net (11ccrimse.1/IncreasestAddtions to Contract: 13oh,"S 1: i