MARSHALL STREET WRF DIGESTER DEMOLITION - 09-0024-UT - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1
PROJECT:
Marshall WRF Digester Demolition
CONTRACTOR:
GHD Services, Inc.
5904 Hampton Oaks Parkway, Suite F
Tampa, FL 33610
Date: September 15, 2019
PROJECT NUMBER:
PURCHASE ORDER:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
09 -0024 -UT
19000330
November 1, 2018
December 4, 2018
3217321-546700-96213
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases result from further evaluation of bid and specification by Engineer of Record and Contractor -
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: GHD Services, Inc.
ORIGINAL CONTRACT AMOUNT $ 960,575.83 `°DOSE"���e.:Fis%-
Change Order 1 - City Manager $ (879,964.40) By:4A-- ARO __
NEW CONTRACT AMOUNT $ 80,611.43 Brian Moore, PE Vice rg$dept,S
�IAW� ,
Date: /6) 361—/5'
Owen Kohler,
Assistant Ci
/a u: ae,a(
Rosemarie Call,
Witnesses: (two)
Xt..
Date: Oli1G(.1 .17 /3/-2-°
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
tuazmA124444Aczt.
Recommended By: City of Clearwater
Duy Nguyen, Project Manager
414g;ite
William B. Horne, II City Manager Tara Kivett, City Engineer
•
Page 2 of 2
Administrative Change Order 1: Marshall WRF Digester Demolition
ITEM DESCRIPTION UNIT Qty UNIT COST TOTAL COST
Decreases:
2 Remove and Return Digester Liquids to LS 0.562369675 $ 26,645.00 $ (14,984.34)
WRF Headworks
3 Remove and Dispose of Digester GAL 1500000 $ 0.30 $ (450,000.00)
Liquids Offsite
4 Temporary Solids Dewatering Facilities LS 0.9 $ 21,395.00 $ (19,255.50)
5 Remove and Dispose of Digester Solids DRY 200 $ 102.41 $ (20,482.00)
8 Demolish, Remove and Disposal of TON 50 $ 52.80 $ (2,640.00)
Additional Hazardous Materials
9 Demolish, Remove and Dispose of LS 1 $ 175,538.72 $ (175,538.72)
Nonhazardous Materials
10 Excavate and Survey Foundation Piles LS 1 $ 5,155.00 $ (5,155.00)
11 Import and Place Structural Fill CYD 3600 $ 19.27 $ (69,372.00)
Materials
12 Miscellaneous Work and Site LS 1 $ 36,574.75 $ (35,111.76)
Restoration
13 Indemnification LS 1 $ 100.00 $ (100.00)
6 10% Contingency LS 1 $ 87,325.08 $ (87,325.08)
Total (Decreases): $ (879,964.40)