2018 SEWER POINT REPAIRS AND IMPROVEMENTS PROJECT - 17-0060-UT - ADMINISTRATIVE CHANGE ORDER #1To: Kristen Parete, Legal Staff Assistant to Owen Kohler, Assistant City ttor From: Laura Davis, Engineering Con CC: Project File Date: 12/18/2019 CLEARWATER BRIGHT AND BEAUTIFUL*BAYTO BEACH Interoffice Correspondence Sheet ntracts & Procurement Specialist RE: Administrative Change Order 1 — ioi8 Sewer Point Repair & Improvements Section D4 Manhole Surfacing Polyurethane (17-oo6o-UT) Attached for Owen's signature are two (2) originals of the above referenced Change Order. Please forward to the City Manager's Office for the Manager's signature at your earliest convenience. Thank you, Laura Davis (727) 562-4509 CLEARWATER BRIGHT AND BEAUTIFUL • BAY TO BEACH Interoffice Correspondence Sheet To: William B. Horne, II, City Manager From: Tara Kivett, City Engineer d'w CC: Lori Vogel, Interim Procurement Manager; Kayleen Kastel, Budget Manager; Jeff Walker, PE, Project Manager; Stephanie Sansom, Controller; Laura Davis, Engineering Construction Contracts Specialist Date: December 17, 2019 RE: Administrative Change Order 12018 Sewer Point Repair & Improvements Section D4 Manhole Surfacing Polyurethane (17 -0060 -UT) RECOMMENDED ACTION: Approve Administrative Change Order 1 to Engineered Spray Solutions LLC, of Lakeland, FL, for 2018 Sewer Point Repair & Improvements Section D Manhole Surfacing Polyurethane (17 -0060 - UT) with an Increase of $40,000 for a new contract total of $440,000. BACKGROUND: Administrative Change Order 1 increases items in accordance with field conditions. PURCHASING OFFICE AND OFFICE OF MANAGEMENT AND BUDGET DEPARTMENT REVIEW I recommend approval based on the administrative change order criteria: 1. Increases do not exceed 10% of the Council approved amount on a cumulative basis. 2. Change does not change the scope of the project. 3. Price increases do not require additional appropriation to the project. 4. Contract price decreases may be approved without limitation. 5. Completion date is not extended more than 60 days. Lori Vogel (aI «Ic9 Date Admininstrative Change Order 1 DATE: November 15, 2019 PROJECT: PROJECT NUMBER: 2018 Sewer Point Repair & Improvements Section D4 Manhole Surfacing -Polyurethane PURCHASE ORDER: CONTRACTOR: COUNCIL AWARD: Engineered Spray Solutions,LLC 1306 Banana Rd. DATE OF CONTRACT: Lakeland, FL 33810 CODE: 17 -0060 -UT 19000740 January 17, 2019 February 11, 2019 3277327-546900-96665 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONT increases in accordance with field conditions -see attached STATEMENT OF CONTRACT AMOUNT Original Contract Admin Change Order 1 - City Manager New Contract Amount APP VED ASt" 'O FORM: Owen Kohler, ATTEST: Rosemarie Call, Date: —3/ -- CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA $ 400,000.00 $ 40,000.00 $440,000.00 ACCEP D BY: En Assistant City Attorney CI) I wt 45.4A Witnesses: (AAASID dilka 7YosiX Recommended By: City of Clearwater L 4Jeff �a , PE, Project Manager 7/f William B. Horne, II City Manager Tara Kivett, P , City Engineer Page 2 of 2 Administrative Change Order 1: 2019 Sewer Point Repair&Improve Section D4 Manhole Surfacing ITE DESCRIPTION UNIT QTY UNIT COST TOTAL COST Increases: la Mobilization/Demobilization including ' LS/WO 1 $ 1,150.00 $ 1,150.00 lc Liner system for 4' diameter manhole -1: VF 9 $ 309.00 $ 2,781.00 2c Liner System for 4' diamenter manhole-: VF 8 $ 416.00 $ 3,328.00 Id Liner system for 5'diameter manhole -12 VF 9 $ 380.00 $ 3,420.00 2d Liner System for 5' diamenter manhole-. VF 7 $ 521.00 $ 3,647.00 le Liner system for 6'diameter manhole -12 VF 9 $ 466.00 $ 4,194.00 2e Liner System for 6' diamenter manhole-. VF 6 $ 605.00 $ 3,630.00 f Bench/invert Repair - Replacement EA 3 $ 250.00 $ 750.00 g Injection grouting as required to stop ini GAL 11 $ 105.00 $ 1,155.00 h Manhole clean/jet-vac EA 9 $ 50.00 $ 450.00 i Remove existing liner for 4' diameter n VF 4 $ 50.00 $ 200.00 j Remove existing liner for 5' diameter m VF 4 $ 60.00 $ 240.00 k Remove existing liner for 6' diameter m VF 3 $ 70.00 $ 210.00 1 Reset/Adjust Frame and Cover EA 6 $ 950.00 $ 5,700.00 m Replace Frame and Cover EA 5 $ 1,140.00 $ 5,700.00 n Seal manhole frame to corbel connectioi EA 7 $ 385.00 $ 2,695.00 o Rear easement access EA 3 $ 250.00 $ 750.00 Total Increases: $ 40,000.00 ,+ Admininstrative Change Order 1 DATE: November 15, 2019 PROJECT: PROJECT NUMBER: 2018 Sewer Point Repair & Improvements Section D4 Manhole Surfacing -Polyurethane PURCHASE ORDER: CONTRACTOR: COUNCIL AWARD: Engineered Spray Solutions,LLC 1306 Banana Rd. DATE OF CONTRACT: Lakeland, FL 33810 CODE: 17 -0060 -UT 19000740 January 17, 2019 February 11, 2019 3277327-546900-96665 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRA increases in accordance with field conditions -see attached STATEMENT OF CONTRACT AMOUNT Original Contract Admin Change Order 1 - City Manager New Contract Amount APV D ASO FORM: $ 400,000.00 $ 40,000.00 ACCE ' ED BY: 4 Owen Kohler, Assistant City Attorney ATTEST: Ga Rosemarie Call, Date: & C h't 30 , JO CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA W1L ate: i" :. eered : ollie Witnesses: V.v./66 yojk Solutions,LLC General Manager Recommended By: City of Clearwater a er, PE, Project Manager 20/1A--/ 141)A William B. Horne, II City Manager Tara Kivett, PE, City Engineer Page 2 of 2 Administrative Change Order 1: 2019 Sewer Point Repair&Improve Section D4 Manhole Surfacing ITE DESCRIPTION UNIT QTY UNIT COST TOTAL COST Increases: la Mobilization/Demobilization including' LS/WO 1 $ 1,150.00 $ 1,150.00 lc Liner system for 4' diameter manhole -1: VF 9 $ 309.00 $ 2,781.00 2c Liner System for 4' diamenter manhole-: VF 8 $ 416.00 $ 3,328.00 ld Liner system for 5'diameter manhole -12 VF 9 $ 380.00 $ 3,420.00 2d Liner System for 5' diamenter manhole-: VF 7 $ 521.00 $ 3,647.00 le Liner system for 6'diameter manhole -12 VF 9 $ 466.00 $ 4,194.00 2e Liner System for 6' diamenter manhole-: VF 6 $ 605.00 $ 3,630.00 f Bench/invert Repair - Replacement EA 3 $ 250.00 $ 750.00 g Injection grouting as required to stop ini GAL 11 $ 105.00 $ 1,155.00 h Manhole clean/jet-vac EA 9 $ 50.00 $ 450.00 i Remove existing liner for 4' diameter n VF 4 $ 50.00 $ 200.00 j Remove existing liner for 5' diameter m VF 4 $ 60.00 $ 240.00 k Remove existing liner for 6' diameter m VF 3 $ 70.00 $ 210.00 1 Reset/Adjust Frame and Cover EA 6 $ 950.00 $ 5,700.00 m Replace Frame and Cover EA 5 $ 1,140.00 $ 5,700.00 n Seal manhole frame to corbel connectioi EA 7 $ 385.00 $ 2,695.00 o Rear easement access EA 3 $ 250.00 $ 750.00 Total Increases: $ 40,000.00