RECLAIMED WATER BOOSTER PUMP STATION CHLORINE FEED SYSTEM IMPROVEMENTS - 16-0001-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdmin Change Order 1&Final DATE:
PROJECT: PROJECT NUMBER:
Reclaim Booster Pump Station Chlorine
Feed System Improvements CONTRACT:
CONTRACTOR: COUNCIL AWARD:
Kloote Contracting, Inc.
2423 Pinnacle Court N. DATE OF CONTRACT:
Palm Harbor, F1 34682
June 5, 2017
16 -0001 -UT
900335
March 1, 2018
March 16, 2018
CODE: 3217321-563800-96654
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Increases due to redesign for more effective improvements -see attached
STATEMENT OF CONTRACT AMOUNT
Original Contract $ 1,071,642.00
Admin Change Order 1&Final - City Manager $ (42,312.10)
New Contract Amount $ 1,029,329.90 Davi . Kloote, / President r •... •... • s� •
AC PTED BY: Kloote Contracting Inc:
3
7
By p (SEAL) c- J
Assistant City Attorney
Date: k 079
Witnesses:
ATTEST:
Rosemarie Call,
Date: f--4-0
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Recommended By:
City of Clearwater
Project Manager
William B. Horne, II City Manager
City Engineer
.,I•
RE: Administrative Change Order 1&Final Reclaim Booster Pump Station Chlorine Feed System Improvements
ITEM
DESCRIPTION
Decreases:
7 10% Contingency
Increases:
3 Chemical Storage and Feed System
4 Process Piping, Valves and Supports
5 Electrical and Instrumentation
6 All Other Work Not Included in Line
Items 1, 2, 3, 4 and 5 to Construct the
Pump Station Improvements for
Skycrest, Drew Street and Union Street
Pump Station
UNIT QTY UNIT COST
LS 1 $ 97,422.00
Total (Decreases):
LS 0.025 $
LS 0.066 $
LS 0.056 $
LS 0.299 $
TOTAL COST
$ (97,422.00)
$ (97,422.00)
125,160.00 $
453,812.00 $
176,000.00 $
40,313.00 $
Total Increase
Total Net (Decreases)/Increases:
3,176.21
30,042.79
9,847.95
12,042.95
$ 55,109.90
$ (42,312.0)