MARSHALL STREET WRF MOTOR CONTROL CENTER NO. 9 ELECTRICAL SYSTEMS UPGRADES - 16-0033-UT - ADMINISTRATIVE CHANGE ORDER #2 & FINALAdministrative Change Order 2 & Final Date: August 15, 2019
PROJECT:
Marshall St WRF MCC9 Electrical
Systems Upgrade
CONTRACTOR:
B.L. Smith Electrical, Inc.
29252 US Hwy 27
Dundee, FL 33838
PROJECT NUMBER:
PURCHASE ORDER:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
16 -0033 -UT
18001051
August 14, 2018
August 31, 2018
3217321-563800-96213
SCOPE OF CHANGE: THIS CHANCE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decrease and increase items due to unforseen electrical condition and to close the contract - see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Change Order 1 - City Council 8/14/2018
Admin Change Order 2&Final - City Manager
NEW CONTRACT AMOUNT
ezlejvOhw sae
Rosemarie Call,
ACCEPTED BY:
B.L. Smith Electrical, Inc.
$1,300,908.75
S (186,788.75) By: �1:a (Seal)
5 (99,452.88) Curtis Barnhill, Vice President of Operations
$1,014,667.12
Date:
Date: ((1 ./ ,1 3-0
APPROVED AS TO FORM:
O
Owen Kohl r, Assistant City Attorney
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, I1
City Manager
g151an19
itnesses: (two)
Wm/A_
LL((c
Reco ended By: Ciof Clearwater
lker, PE,
x'
Project Manager
DrSeett-Rice, PE,
1aatK;.q
City Engineer
Page 2 of 2
Administrative Change Order 2&Final: Marshall St WRF MCC9 Electrical Systems Upgrade
ITEM
DESCRIPTION
UNIT Qty UNIT COST TOTAL COST
Decreases:
6 CITY'S INTEGRATOR ALLOWANCE LS 0.0 $ 35,000.00 S (1,500.00)
FOR SCADA INTEGRATION ONLY
9 Contingency 15% LS 1.00 $ 145,320.00 S (145,320.00)
Total (Decreases): S (146,820.00)
Increases:
3 ELECTRICAL LS 0.0720477 $ 632,890.00 $45,598.25
7 MISCELLANEOUS LS 0.0110554 $ 160,000.00 $1,768.87
ARCHITECTURAL
Total Increases: $47,367.12
Total Net (Decreases)/Increases: S (99,452.88)