WATER TREATMENT FLUORIDE ADDITION WTP 1 AND WTP 2 - 16-0031-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1&Final DATE: June 30, 2019
PROJECT: PROJECT NUMBER: 16 -0031 -UT
Water Treatment Plant Fluoride CONTRACT: 900005
Addition - WTP 1 and WTP 2
CONTRACTOR: COUNCIL AWARD: April 19, 2018
KAT Construction & Materials Inc. DATE OF CONTRACT: April 27, 2018
6541 Industrial Ave
Port Richey, F134668 CODE: 3217321-563800-96764 A
3217321-563800-96767 B
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
to decrease and increase items in accordance with field conditions and adds 50 calendar days to the
contract -see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 552,036.20
Admin Change Order 1&Final-City $ (25,620.11) By:
NEW CONTRACT AMOUNT $ 526,416.09 >atr;Ye i�rsidih;
ACCEPTED BY:
Kat Construction & 1a'tei'tais" luc.
O FORM:
ATTEST:
;„,.1-t-/1 l a. 2_ (.4..
Rosemarie Call,
er, Assistant Cit
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
cv1�._b,U.9w)-
William B. Horne, II
Date: "2- 3/
Witnesses:
724— etc
N13 re d %'t ooy-
Recommended By:
City of Clearwater
Duy Project Manager
7c1kJ
City Manager Tara Kivett, PE,
City Engineer
Page 2 of 2 Administrative Change Order 1&Final Water Treatment Plant Fluoride Addition WTP 1&2
ITE DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Code A Decreases:
7 Contingency LS 0.5 $ 50,185.11 $ (25,092.56)
Code A Increases:
3 AODD Pump Replacement LS 0.023 $ 85,000.00 $ 1,952.50
5 Electrical and Instrumentation LS 0.0689 $ 150,000.00 $ 10,330.00
Total Increases Code A: $ 12,282.50
Total Net (Decreases)/Increases Code A: $ (12,810.06)
Code B Decreases:
7 Contingency LS 0.5 $ 50,185.11 $ (25,092.56)
Code B Increases:
3 AODD Pump Replacement LS 0.023 $ 85,000.00 $ 1,952.50
5 Electrical and Instrumentation LS 0.0689 $ 150,000.00 $ 10,330.00
Total Increases Code B: $ 12,282.50