MEMORIAL CAUSEWAY SUBAQUEOUS PIPELINE PROJECT - 14-0041-UT - ADMINISTRATIVE CHANGE ORDER #1ADMINISTRATIVE CHANGE ORDER 1
PROJECT:
Clearwater Memorial Causeway
Subaqueous Pipelines
CONTRACTOR:
Andrew Sitework LLC
2511 Palm Ave
Fort Myers, FL 33916
DATE:
PROJECT NUMBER: 14 -0041 -UT
CONTRACT REFEREI 900217
COUNCIL AWARD: October 5, 2017
DATE OF CONTRACT November 3, 2017
CODE:
March 6, 2019
3277327-563800-96665
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
increasing and adding line items for a forcemain bypass due to unknown location of an existing gas'main
and encountering an 18" forcemain versus the 16" forcemain; and add 59 days to the contract -see
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 3,048,602.70
Admin Change Order 1 -City Manager- $ 289,870.96
$ 3,338,473.66
D T ORM:
Owen Ko er,
ATTEST:
Assistant City Attorney
ACCEPTED BY: Andr=
By: //Age►
Ralp d ,fr
Date: Z ---1
Witnesses:
Operations
0
Yt_ lb& 01,1 -e ----
Rosemarie Call,
Date:--)210c-ii,% _2-1olq
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
Kayl ce, Project Manager
City Manager D. Scott Rice, PE City Engineer
r
4
r
Page 2 of 2
Administrative Change Order 1 - Clearwater Memorial Causeway
ITEM
DESCRIPTION
Decreases
10A 16" Tapping Sleeve & Valve
11A 20" Tapping Sleeve & Valve
13A Flowable Fill
16A Temporary Asphalt Pedestrian
Trail, Access Drives and
Restoration
Additions:
19A Sound Attenuation Wall
20A Force Main By -Pass System
21A 18" Pipe and Fittings
22A 18" Tapping Sleeve & Valve
23A 16" Tapping Valve Restock Fee
18A Contingency
UNIT OTY UNIT COST TOTAL COST
LS 1 $ 23,416.00 $
LS 1 $ 31,375.00 $
CY 220 $ 242.00 $
LS 1 $ 27,407.77 $
LS
LS
LS
LS
LS
LS
(23,416.00)
(31,375.00)
(53,240.00)
(27,407.77)
Total (Decreases): $ (135,438.77)
1 $ 146,480.95
1 $ 176,549.38
1 $ 44,931.29
1 $ 29,683.71
1 $ 1,312.50
0.139 $ 189,298.30
Total Increases:
$ 146,480.95
$ 176,549.38
$ 44,931.29
$ 29,683.71
$ 1,312.50
$ 26,351.90
$ 425,309.73
Total Net (Decreases)/Additions to PO: $
289,870.96