EAST GATEWAY STORMWATER AND SANITARY IMPROVEMENTS PROJECT - 13-0043-EN - ADMINISTRATIVE CHANGE ORDER #3Administrative Change Order 3
PROJECT:
East Gateway Stormwater & Sanitary
Sewer Improvements
CONTRACTOR:
David Nelson Construction Co
3483 Alt 19
Palm Harbor, F134683
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
February 25, 2019
13 -0043 -EN
18001128
January 19, 2017
February 9, 2017
ENST 180009-CONS-CNSTRC A
3217321-563800-96742 B
3217321-563800-96212 C
3217321-563800-96739 D
ENRD 180004-CONS-CNSTRC E
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
Due to differences in existing pipes and unknown quantity of sewer laterals, line items are adjusted according -decreasing, increasing
and adding items in accordance with field conditions - see attached. / / q
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Ratify&Confirm Change Order 1 -City Council 5/17/2018
Admin Change Order 2 -City Manager -10/19/2018
Admin Change Order 3 -City Manager
NEW CONTRACT AMOUNT
APPROVE
Owen Koh
ATTEST:
x' C.:i-im' L.� �-��-
Rosemarie Call,
Date: a Z I 4 3C/'7
$ 11,409,143.90
$ 421,554.60
$ 11,830,698.50
Assistant City Attorney
City Clerk
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
,Q,u L '4e -Ir
William B. Horne, II
City Manager
A CEP
ED BY: Da
Nelson Co4tation C SS
Lt.a o'
(SEAT.
David L. Vekast
Date: ` 2.v - l 9
Vekc1Presldeht
Witnesses:
(\.cijr)ct
Recommended By:
City of Clearwater
Ivan Dimitrov, EI,
Project Manager
. Scott Rice, PE,
City Engineer
Page 2 of 2 Administrative Change Order 3: East Gateway Stormwater & Sanitary Sewer Improvements
ITEM
DESCRIPTION
UNIT QTY UNIT COST TOTAL COST
Code B Decreases:
323 REMOVE & REPLACE POTABLE WATER EA 83.389091 $ 550.00 $ (4.5,864.00)
SERVICE CONNECTION (ALLOWANCE)
Code B Additions:
301 F&I 6" DIP WM, RJ; INCLUDING POLY LF 626 $ 45.00 $ 28,170.00
WRAP, FITTINGS, & BENDS
308 F&I 6" GV W/ BOX (CITY 402) EA 3 $ 1,500.00 $ 4,500.00
(ALLOWANCE) (AS DIRECTED BY CITY)
316 F&I 2" AIR VALVE (VAL-MATIC VMC- EA 1 $ 5,750.00 $ 5,750.00
38VC), INCLUDING APPURTENANCES,
FITTINGS, BENDS, & CONC. PAD.
319 F&I TEMP B.O. / S. TAP (CITY 408); EA 2 $ 1,250.00 $ 2,500.00
INCLUDING APPURTENANCES, FITTINGS,
BENDS, & REMOVAL
320 F&I TEMP CL2 TAP (CITY 408); INCLUDING EA 2 $ 450.00 $ 900.00
APPURTENANCES, FITTINGS, BENDS, &
REMOVAL
321 DEMO & DISPOSE EXISTING WM; OTHER LF 337 $ 12.00 $ 4,044.00
THAN A -C WM
Total Increases: $ 45,864.00
Total Net (Decreases)/Additions Code B: $
Code C Decreases:
411 CONFLICT STRUCTURE (ALLOWANCE) EA 5 $ 5,000.00 $
405 DEMO & DISPOSE EXISTING SANITARY PIPI LF 362.22 $ 26.00 $
Total (Decreases) $
(25,000.00)
(9,417.72)
(34,417.72)
Code C Increases:
409 REMOVE & REPLACE SANITARY EA 23 $ 1,100.00 $ 25,300.00
LATERALS (CITY 305)
Code C Addition:
415 IDENTIFY, LOCATE, EXTEND & TIE-IN LS 1 $ 9,117.72 $ 9,117.72
EXISTING SANITARY SERVICE LATERAL
ON FRANKLIN ST
Total Net (Decreases)/Increases/Additions Code C: $
Code D Decreases:
502 F&I 16" RCWM OFFSET/DEFLECTION EA 0.5960 $ 20,000.00 $ (11,920.79)
(INCLUDES EXCAVATION, BACKFILL, PIPE,
POLY WRAP, RESTRAINTS, INSTALLATION,
FITTINGS, RESTRAINT OF EXISTING PIPE)
Code D Additions:
511 ADJUST/LOWER RCWM SERVICE LINES EA 13 $ 425.00 $ 5,525.00
512 OFFSET 12" RCWM IN CONFLICT W/NEW LS 1 $ 6,395.79 $ 6,395.79
20" WM
Total Additions: $ 11,920.79
Total Net (Decreases)/Additions Code D: $
Total Net (Decreases)/Increases/Additions: $