CLEARWATER GAS SYSTEM FACILITY REDEVELOPMENT - 15-0043-GA - ADMINISTRATIVE CHANGE ORDER #1ADMINISTRATIVE CHANGE ORDER 1 DATE: November 26, 2018
PROJECT: PROJECT NUMBER:
Clearwater Gas System
Facility Redevelopment CONTRACT REFERENCE:
CONTRACTOR: COUNCIL AWARD:
Walbridge Aldinger LLC
100 S. Ashley Drive, Suite 350 DATE OF CONTRACT:
Tampa, FL 33602
CODE:
15 -0043 -GA
900293
December 7, 2017
December 12, 2017
3237323-563600-96384
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
decreasing the contract by Owner Direct Purchases (ODP) and funding scope modifications resulting from design
revisions to the 100% construction documents. GMP was based on 90% documents, see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 23,359,100.00
Admin Change Order 1 -City Manager- $ (2,512,849.46)
$ 20,846,250.54
APP VED A
TO FORM:
Owen Kolher,
ATTEST:
utuyuka-
Assistant City Attorney
Rosemarie Call,
Date: %& n/4 iq1 6A'
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
City Manager
ACCEPTED BY: Walbridge Aldinger LLC
By:
Caleb Westfall,
Date: j7f i1 II
Project Manager
Witnesses:
y:
ity of Clearwater
Tar14*I4i41). vet Assstant Eng Director
74FJhuM
D. ScoRice, PE, City Engineer
Page 2 of 2
Administrative Change Order 1 - Clearwater Gas System Facility Redevelopment
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
31 Sitework & Utilities LS 0.0123 $ 3,314,380.00 $ (40,835.00)
38 Final detailing/permit requirement LS 1 $ 181,200.00 $ (181,200.00)
allowance (1% of SDC)
Total (Decreases) $ (222,035.00)
Increases:
3 Concrete LS 0.0251614 $ 2,121,742.00 $ 53,386.00
4 Masonry LS 0.01137965 $ 1,649,875.00 $ 18,775.00
5 Metals LS 0.0747179 $ 1,357,747.00 $ 101,448.00
6 Wood, Plastics, Composites LS 0.06566482 $ 61,220.00 $ 4,020.00
7 Thermal Moisture Protection LS 0.09082882 $ 1,036,444.14 '$ 94,139.00
8 Openings LS 0.04094954 $ 794,026.00 $ 32,515.00
9 Finishes LS 0.03888741 $ 1,630,939.00 $ 63,423.00
10 Specialties LS 0.07150962 $ 209,762.00 $ 15,000.00
23 HVAC LS 0.06480021 $ 2,559,251.00 $ 165,840.00
26 Electrical LS 0.05431504 $ 3,379,782.00 $ 183,573.00
90 CM Fee LS 0.07228872 $ 873,857.00 $ 63,170.00
Total Increases: $ 795,289.00
Total Net (Decreases)/Increases to PO: $
573,254.00
Decreases for ODP:
5 Metals LS 0.24095896 $ 1,357,747.00 $ (327,161.30)
7 Thernal & Mositure Protection LS 0.13534759 $ 1,198,683.00 $ (162,238.86)
8 Openings LS 0.39270691 $ 794,026.00 $ (311,819.50)
9 Finishes LS 0.19500412 $ 1,630,939.00 $ (318,039.82)
23 HVAC LS 0.30056874 $ 2,559,251.00 $ (769,230.85)
26 Electrical LS 0.27845493 $ 3,379,782.00 $ (941,116.97)
31 Sitework & Utilities LS 0.077389 $ 3,314,380.00 $ (256,496.16)
Total (Decreases) for ODP: $ (3,086,103.46)
Total Net (Decreases) to Contract: