Loading...
MARSHALL WASTE ACTIVATED SLUDGE RAGGING ISSUES - 17-0053-UT e CERTIFICATE OF SUBSTANTIAL COMPLETION Project: Marshall Waste Activated Sludge Ragging Issues Contract Number: 17-0053-UT Location: Marshall Street WRF 1605 Harbor Drive, Clearwater, FL Contract Date: 03/01/18 Notice to Proceed Date: 03/07/2018 Substantial Completion Date: 06/19/18 Warranty Expiration Date: 06/19/2019 The work performed under this Contract has been inspected by authorized representatives of the Owner and Contractor, and the Project(or specified part of the Project, as indicated above) is hereby declared to be substantially completed on the above date. DEFINITION OF SUBSTANTIAL COMPLETION Substantial completion is the stage in construction when a project or designated portion thereof is sufficiently complete in accordance with contract documents so that the Owner can use the work or portion thereof for its intended use. Items that affect operational integrity and function of the work must be capable of continuous use. The Contractor accepts the above Certificate of Substantial Completion of the outlined project area and agrees to cora lete and core the items on the tentative list within the time indicated. By � x/Cce 9w� Gc7/nom 7_ __ '. Whar on=Smith; Inc. Print Name ofAuthorized Representative V w Date The Owner accepts the Project as Substantially Complete and will assume full possession of the specified area of the Project on June 19, 2018. The responsibility for utilities, security, and insurance under the Contract cuments shall A5e as set forth in the Contract Documents. x -- City a ater Print Name of thorized Representative Date Certificate of Substantial Completion,Page 2 of 2 PROJECT ONE YEAR WARRANTY Contract Section Ill, 13.5 WARRANTY/CORRECTION PERIOD If within one year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any Work is found to be defective, Contractor shall promptly, without cost to the Owner and in accordance with the Owner's written instructions; (i) correct such defective Work, or, if it has been rejected by the Owner, remove it from the site and replace it with Work that is not defective and(ii)satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom... Where defective Work(and damage to other Work resulting therefrom) has been corrected, removed or replaced under this paragraph the correction period hereunder with respect to such Work will be extended for an additional period of one year after such correction or removal and replacement has been satisfactorily completed. Substantial Completion Date: 06/19/2018 Warranty Expiration Date: 06/19/2019 A copy of this signed and executed document should be provided to the following parties: Project Owner Project Contractor Project Consultant(if applicable) City Construction Office Specialist Project File