EXTENSION - EAST GATEWAY STORMWATER AND SANITARY IMPROVEMENTS PROJECT - 13-0043-EN (2) Email Received 5/3/18
East Gateway—additional time granted
Shannon,Jennifer Reply
Snan'Syn,a,qsh cnsym3nskinelsoi7-cYistrju-ion.com,,>:Kurt,,Tir�v dTy M.,saw,Lau,a
-vl2019 addtltimegr-
12<R
6:'d ' '
D-,vnk,ad Ss%lc to Oner)rive-Gry of Cearvvter
Hi Brian,
Attached to this email is a table shoot ngtfie additional time ghat twill be granted to the East Gateway-Stormwater and Sanitary Sewer project..The newtotal time
granted tathe project is 279 days with completion date of NovernberM,2018.
Please ensure that new project schedules reflect this information.
Thank.you.
Jennifer
Jennifer W.Shannon,PE,CFM
Senior Professional Engineer
City of Clearwater
727-562-4773
East Gateway - Additional Days
Underground Conflicts Days Approved
Sanitary conflict at Pierce St and Stevenson Creek 10 days (previously approved)
12" Reclaimed Water Main Conflict with 7 days (previously approved)
stormwater on Pierce St
Existing water main in conflict with proposed 3 days (previously approved)
storm sewer on Pierce St
Changes to tie-in of proposed 20" water main at 18 days (previously approved)
Hillcrest and Court St
Endwall shift 18 days (previously approved)
Unknown pipe found on south side of Franklin St 6 days (previously approved)
east of Stevenson Creek
Existing reclaimed water main in conflict with 3 days (previously approved)
proposed 20"water main on S Hillcrest Ave
Hurricane Irma 8 days (previously approved)
Additional work:Added 6"water main on Hillcrest 28 days (previously approved)
Subtotal 101 days
Project delays due to utility conflicts Days Approved
Added sanitary sewer work for reclaimed water 4 days (previously approved)
main conflicts on Hillcrest
Conflict with fiber optic cable/conduit and sanitary 1 day(previously approved)
MH-315
Conflict with unmarked water main and storm 1 day(previously approved)
inlet 5121
Fiber optic pull box& cable/conduit and power 21 days
pole guy wire conflict with new storm sewer
outfall at Pierce and Lady Mary
Fiber optic cable/conduit conflict with new 21 days
sanitary sewer main from MH-307 to 310 at Pierce
and Fredrica
Power pole conflict with new storm sewer at 68 days
Franklin and Waverly
Subtotal 116 days
Additional Required Roadwork Days Approved
Concrete pavement removal on Park St and Betty 4 days (previously approved)
Lane
Mill and resurface San Juan from Hillcrest to San 1 day
Remo
Rebuild roadway on Franklin and De Leon east of 12 days
Hillcrest
Rebuild roadways west of creek in lieu of mill and 45 days
resurface
Subtotal 62 days
Grand Total 271days