REHABILITATION OF LIFT STATIONS 28 AND 39 - 15-0033-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1&Final
PROJECT:
Rehabilitation of Lift Stations
28 & 39
CONTRACTOR:
RTD Contractors, Inc.
PO Box 2439
Zephyrhills,FI 33539
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
to decrease and increase items in accordance with field conditions -see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 & Final - City Manager
NEW CONTRACT AMOUNT
APPROV)IS TO F(;RM:
$ 452,116.54
$ (29,495.01)
$ 422,621.53
Owen Kohler,
ATTEST:
Lia? %nta
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
City Manager
March 1, 2018
15 -0033 -UT
ST114227
August 3, 2017
August 21, 2017
0327-96217-563800-5357900-0000
ED BY: RTD Contras o
By:
Rusty A. Haug
Date:
Recommended By:
City of Clearwater
Todd Kuhnel
Project Manager
D. Scott Rice, PE,
Administrative Change Order 1 & Final Rehabilitation of Lift Staions 28 & 39
ITEM
Decreases:
3 Bypass pumping and piping, critically silenced
6 Bypass pumping and piping, critically silenced
7 Contingency 10%
DESCRIPTION
Increases:
2 Lift Station 28 Rehabilitation
5 Lift Station 39 Rehabilitation
UNIT QTY
WK
WK
LS
LS
LS
0.28571545 $
1.428573176 $
1 $
City Engineer
UNIT COST TOTAL COST
2,453.21
2,453.21
41,101.50
Total (Decreases): $
0.047297305 $ 207,009.68
0.044681419 $ 134,754.00
Total Increases:
(700.92)
(3,504.59)
(41,101.50)
(45,307.01)
9,791.00
6,021.00
15,812.00
Total Net (Decreases)/Increases: $ (29,495.01)