CLEARWATER PASS SOUTH SEAWALL REPAIR - 17-0044-EN - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1
PROJECT:
Clearwater Pass South Seawall Repair
CONTRACTOR:
Castco Construction, Inc.
9001 126th Avenue North
Largo, Fl 33773
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
February 23, 2018
17 -0044 -EN
ST114552
November 16, 2017
January 3, 2018
CODE: 0315-93412-563800-539-000-0000
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
adjusting seawall cap width to match existing, eliminating well points and increasing quantity
grouting to entire seawall length - see attached
of cleaning and
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Administrative Change Order 1 - City Manager
NEW CONTRACT AMOUNT
APPROVES TO F M:
cue
$ 829,098.73
$ 67,842.40
$ 896,941.13
Owen ohler
ATTEST:
Jc uuvc.a..aw
Rosemarie Call,
Assistant City Attorney
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
ACCEPTED BY:
nstruction, Inc
Israel Castro
Date: 5
nesses:
Lt
Recommended By:
City of Clearwater
2ssier'
Project Manager
D( _ ?((4((
City Manager D. Scott Rice, PE, City Engineer
Administrative Change Order 1 Clearwater Pass South Seawall Repair
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
2 Replace 20" seawall cap and anchors LF 401 $ 214.67 ($86,082.67)
3 Replace 20" seawall cap (notched for LF 880 $ 214.67 ($188,909.60)
sidewalk) and anchors
9 Clean and grout appropriate joints and EA 75 $ 171.74 ($12,880.50)
install well points
Total (Decreases): ($287,872.77)
Increases
16 Contingency 10% LS 0.0818 $ 75,372.61 $6,167.49
Additions
17 Replace 24" seawall cap and anchors LF 401 $ 235.14 $94,291.14
18 Replace 24" seawall cap (notched for LF 880 $ 235.14 $206,923.20
sidewalk) and anchors
19 Clean and grout appropriate joints EA 341 $ 141.74 $48,333.34
Total Increases: $349,547.68
Total Net (Decreases)/Increases: $67,842.40