NE WRF - EFFLUENT PUMP STATION VALVES AND SLIDE GATE REPLACEMENT - 16-0005-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1&Final
PROJECT:
NE WRF Effluent Pump Station Valves
& Slide Gate Replacement
CONTRACTOR:
Poole & Kent Company of Florida
1715 Lemon Street
Tampa, F133606
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
December 4, 2017
16 -0005 -UT
ST113642
December 15, 2016
December 15, 2016
0327-96664-5638105-000-0000
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract t"''��a,
increasing and adding items to redesign Hercules from Druid Rd to Gulf to Bay and add 250 calendar days to tii o aet I
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Poole &4�gni�`�6p�nylbrida
ORIGINAL CONTRACT AMOUNT
Admin Change Orde . Final - City Manager
NEW CONTRA ► O • T
APPROV AS T ►r`:�'%
Camilo Soto,
ATTEST:
i.4.-01/CL
Rosemarie Call,
$473,000.00
($9,257.61)
$ 463,742.39
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
jaj4A. . N-PAA12
William B. Horne, II
City Manager
B`� 4SiAL)
David B. BuShe : `'(i ice Piiiident
Date: /;(//1/Z f7
Witnesses:
Recommended By:
City of Clearwater
Lan-Anh Nguyen, PE
Project Manager
D. Scott Rice, PE, City Engineer
Administrative Change Order 1 & Final NE WRF Effluent Pump Station Valves & Slide Gate Replacement
ITEM
Decreases:
3 10% Owners Contingency
DESCRIPTION
Increases:
2 Mechanical, Electrical and Instrumentation
Work
UNIT
LS
LS
UNIT COST
1 $ 43,000.00
Total (Decreases):
0.080723421 $ 418,000.00
Total Increases:
Total Net (Decreases)/Increases:
TOTAL COST
($43,000.00)
($43,000.00)
$33,742.39
$33,742.39
($9,257.61)