RE: PROJECT #KC -1801 PIER 60 BAIT HOUSE AND 6 PAVILION ROOFING Rev.
(11-15-17)
Dear Mr. Wojtkiw,
As requested, enclosed is the proposal for re -roofing and siding of 6 pavilions and
the bait house on Pier 60 submitted in accordance with technical
specs/plans/study/clarifications of this letter/attached line item work, etc., for a
Guaranteed Maximum Price of ($375,267.19). Three hundred, seventy-five
thousand, two hundred, sixty-seven and 19/100 dollars
Scope of Work:
1. Scheduling and coordination with City Staff and Pier 60 Vendors.
2. Provide OSHA Approved scaffolding as required for our scope of work.
3. Removal and reinstallation of turnstile gate.
4. Demolition of all existing metal roofing on bait house and 6 pavilions.
5. Re -roofing utilizing 60 mil self adhered membrane roof underlayment.
6. Remove/replace existing P.T. 2 x 12 fascia and wrap with .032 Kynar standard color
aluminum.
7. Install Gulf Coast 12" 0.C. .032 Kynar standard color aluminum standing seam
roofing/trim with 25 year paint finish and 20 year watertight warranty.
8. Removal of siding material from ceiling elevation above.
9. Remove and replace all exterior soffits with James Hardi vented soffit
10. Provide new James Hardi Ceiling over existing.
11. Replace fire sprinkler heads in exterior ceiling.
12. All James Hardi Materials shall be color plus "Dove Grey".
13. All fasteners shall be stainless steel.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
Ars
CONSTRUCTION, INC.
CGC1508668
14. All are non -egress windows.
15. Recoat structural metal connectors on 6 Pavilions to include: Hand -tool clean, grind to
remove loose rust scale. Spot prime bare metal with Amercoat 1 component Epoxy.
Apply 1 full coat of Amercoat Epoxy Apply 2 top coats of Durethane DTM Urethane
Mastic.
16. Prepare, concrete and steel substrates and stucco 40 concrete columns with color
entrained synthetic stucco.
17. Remove existing light fixtures on ceiling and replace with HALO H7RICAT remodel
recessed cans, Halo 30wat white baffle trims and LED R30 12 watt amber turtle friendly
lamps. 11 new cans total. 9 (see cut sheets attached)
18. Replace existing wall mount fixture with 1 Progress P5712-30 white cylindrical fixtures
with LED R30 12 watt amber turtle friendly lamp. (see cut sheet attached)
19. Deposit all demolition materials in dumpsters provided by City to be located in parking
lot in ADA spaces South of Pier to be temporarily fenced by City for laydown yard.
Add Alternate Scope of Work:
1. Demolition and removal of 1st level vinyl siding up to the soffit and patio ceiling level.
Supply and install Color Plus Dove Grey, Hardi-lap siding with 60 mil peel and stick
underlayment. Exterior grade plywood and window replacement. Hardi Wrap all wood
columns, trim windows, doors, corners and wall to soffit intersect with Hardi-Board
Trim. See detailed cost breakdown below.
Exclusions:
1. Concrete repairs.
2. Replacement of any structural connectors.
3. Replacement of structural framing, plywood or sheathing.
4. Plumbing or Mechanical Work.
5. Electrical work beyond what is described above.
6. Removal or replacement of low voltage mounted to building.
7. Termite or pest control.
8. Painting other than structural connectors on Pavilions.
9. Doors.
10. Temporary fencing at laydown yard in parking lot.
11. Permitting or permitting fees.
12. Materials testing.
13. Dumpsters or debris haul -off.
14. Warranty of any materials, fixtures or equipment supplied by owner.
15. Permitting or fees.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
CONSTRUCTION, INC.
CGC1508668
16. Engineering or architectural work.
17. Builder's Risk Insurance.
Cost Detail:
12222 Anne Kenia Drive, Thonotosassa, FL 33592
Pier 60 Roofing, soffits and fascia siding
2
GENERAL CONDITIONS
Scaffolding (8 weeks included)
$20,707.46
6
TRIM AND ROUGH
CARPENTRY
Hardi Board Labor
$29,375.00
6
TRIM AND ROUGH
CARPENTRY
Replace 2x12 Fascia on
Pavilions
$2,856.00
6
TRIM AND ROUGH
CARPENTRY
James Hardi Package
$8,544.14
6
TRIM AND ROUGH
CARPENTRY
Plywood/Lumber/Peel and stick
$4,418.19
7
THERMAL AND
MOPISTURE
Roofing Metal and Install
$108,265.00
8
OPENINGS
Removal and Reinstall Turn
style
$1,120.00
9
FINISHES
Synthetic Stucco Columns (X40)
$10,400.00
9
FINISHES
Surface Prep and connector
treatment.
$12,000.00
15
MECH
Fire Sprinklers
$3,765.00
16
Elec
All
$3,156.00
SUB -SUBTOTAL
$204,606.80
General Conditions,
Supervision, Insurance,
Bond
$30,907.75
Owner Contingency
$30,600.00
OH&P
15.00%
$39,917.18
COST TOTAL AMOUNT
$306,031.73
Add Alternate 1st floor
6
TRIM AND ROUGH
CARPENTRY
Hardi Board/Window Labor
$22,500.00
12222 Anne Kenia Drive, Thonotosassa, FL 33592
CONSTRUCTION, INC.
CGC1508668
6
TRIM AND ROUGH
CARPENTRY
Hardi Board Column Wraps
(X10) (Lab. and Mat.)
$1,892.30
6
TRIM AND ROUGH
CARPENTRY
James Hardi Package
$4,788.03
6
TRIM AND ROUGH
CARPENTRY
Plywood/Lumber/Peel and stick
$5,758.87
8
OPENINGS
Windows Materials
$8,822.54
SUB -SUBTOTAL
$43,761.74
General Conditions,
Supervision, Insurance,
Bond
$9,543.01
Owner Contingency
$6,900.00
OH&P
15.00%
$9,030.71
COST TOTAL AMOUNT
$69,235.46
Grand Total with Add Alternate for 1st floor siding and
windows
$375,267.19
Project Duration shall be 90 calendar days from the date of the Notice to Proceed. Onsite
Construction base contract is estimated at 8 weeks, add 4 weeks for 1st floor alternate. We will
require periodic shut downs of baithouse.
Existing Contract: This proposal is submitted in conjunction with the existing Construction
Manager at Risk Services Continuing Contract entered into with the City of Clearwater on June
15, 2016, based on RFC) #24-16.
If GMP Exceeds $150,000: Per Section III, Article 5.1 of the Contract Specifications, the
contractor shall provide to the public entity a certified copy of the recorded bond. Once the City
receives a certified copy of the recorded bond, a Notice to Proceed may be issued. Include the
attached bond form as well as the Power of Attorney.
For work performed, invoices shall be submitted to the City of Clearwater, Engineering
Department, Attn: Veronica Josef, Senior Staff Assistant, P.O. Box 4748, Clearwater, Florida,
33758-4748. Contingency services may be billed only after written authorization is provided by
the City to proceed with those services.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
1
1
CONSTRUCTION, INC.
CGC1508668
Appro ed as to fo
M.' 'ew M. S &h
Assistant City • orney
Countersigned:
.-Cteof‘Q 4Cft t'Os
George N. Cretekos
Mayor
J-1-1/4/ 7
Date
KHORS
By:
,INC
Kori Khorsandi
President
Date
CITY OF CLEARWATER, FLORIDA
Attest:
By: 4.4-0yL
Rosemarie Call
City Clerk
ISHED
ul,eL:AlH,w�
William B. Horne II
City Manager
/.2//3/.2J17
Date
12222 Anne Kenia Drive, Thonotosassa, FL 33592
SECTION V — Contract Documents
Bond No.:
PUBLIC CONSTRUCTION BOND
(1).
This bond is given to comply with § 255.05, Florida Statutes, and any action instituted by a claimant under this bond for
payment must be in accordance with the notice and time limitation provisions in subsections (2) and (10).
Pursuant to § 255.05(1)(b), Florida Statutes, "Before commencing the work or before recommencing the work after a
default or abandonment, the contractor shall provide to the public entity a certified copy of the recorded bond.
Notwithstanding the terms of the contract or any other law governing prompt payment for construction services, the
public entity may not make a payment to the contractor until the contractor has complied with this paragraph."
CONTRACTOR
Khors Construction, Inc.
12222 Anne Kenia Dr.
Thonotosassa, FL 33592
SURETY
FCCI Insurance Group Surety
6300 University Parkway
Sarasota, FL 34240
OWNER
City of Clearwater
Engineering Department
100 S. Myrtle Avenue
Clearwater, FL 33756
(727) 562-4747
PROJECT #KC -1801
PROJECT DESCRIPTION: PIER 60 BAIT HOUSE AND 6 PAVILION ROOFING
BY THIS BOND, We Khors Construction, Inc. as Contractor, and FCCI Insurance Group Surety, a corporation, as Surety, are
bound to the City of Clearwater, Florida, herein called Owner, in the sum of $375,267.19 Three hundred, seventy-five
thousand, two hundred, sixty-seven and 19/100 dollars for payment of which we bind ourselves. our heirs, personal
representatives, successors, and assigns, jointly and severally.
THE CONDITION OF THIS BOND is that if Contractor:
1. Performs the proposal dated November 15, 2017, between Contractor and Owner for construction of PROJECT #KC -
1801 PIER 60 BAIT HOUSE AND 6 PAVILION RE ROOF the contract documents being made a part of this bond by reference
(which include the Advertisement for Bids, Proposal, Contract, Surety Bond, Instructions to Bidders, General Conditions, Plans,
Technical Specifications and Appendix, and such alterations as may be made in said Plans and Specifications as therein
provided for), at the times and in the manner prescribed in the contract; and
2. Promptly makes payments to all claimants, as defined in Section 255.05(1), Florida Statutes, supplying Contractor with
labor, materials, or supplies, used directly or indirectly by Contractor in the prosecution of the work provided for in the contract;
and
3. Pays Owner all losses, damages, expenses, costs, and attorney's fees, including appellate proceedings, that Owner
sustains because of a default by Contractor under the contract; and
Bond No.:
PUBLIC CONSTRUCTION BOND
(2)
4. To the limits of § 725.06(2), Florida Statutes, shall indemnify and hold harmless Owner, their officers and
employees, from liabilities, damages, losses and costs, including, but not limited to, reasonable attorney's fees, to the
extent caused by the negligence, recklessness, or intentional wrongful misconduct of Contractor and persons employed or
utilized by Contractor in the performance of the construction contract; and
SECTION V
Page 1 of 17 Updated 2/11/2016
SECTION V — Contract Documents
5. Performs the guarantee of all work and materials furnished under the contract for the time specified in the
contract, then this bond is void; otherwise it remains in full force.
6. Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time
limitation provisions in Section 255.05(2), Florida Statutes.
7. Any changes in or under the contract documents and compliance or noncompliance with any formalities
connected with the contract or the changes does not affect Surety's obligation under this bond, and Surety does hereby
waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to
the specifications.
IN TESTIMONY WHEREOF, witness the hands and seals of the parties hereto this day of
, 20_
(If sole Ownership or Partnership, two (2) Witnesses required).
(If Corporation, Secretary only will attest and affix seal).
Khors Construction, Inc.
By:
Title: President
Print Name: Kori Khorsandian
WITNESS: WITNESS:
Corporate Secretary or Witness Print Name:
Print Name:
(affix corporate seal) FCCI Insurance Group Srety
(Power of Attorney must be attached)
SECTION V
Bv:
ATTORNEY-IN-FACT
Print Name:
(affix corporate seal)
Page 1 of 17 Updated 2/11/2016
Proposal
November 13, 2017
TO: Tom Wojtkiw CBC, CFM
City of Clearwater — Building Maintenance Supervisor
1900 Grand Avenue
Clearwater, FL 33765
RE: PIER 60 ROOF BAIT HOUSE AND 6 PAVILION ROOFING Rev. 11-13-17)
Dear Mr. Wojtkiw,
As requested, enclosed is the proposal for re -roofing and siding of 6 pavilions and
the bait house on Pier 60 submitted in accordance with technical
specs/plans/study/clarifications of this letter/attached line item work, etc., for a
Guaranteed Maximum Price of ($375,267.19). three hundred, seventy-five thousand,
two hundred, sixt-seven and 19/100 dollars
Scope of Work:
1. Scheduling and coordination with City Staff and Pier 60 Vendors.
2. Provide OSHA Approved scaffolding as required for our scope' of work.
3. Removal and reinstallation of turnstile gate.
4. Demolition of all existing metal roofing on bait house and 6 pavilions.
5. Re -roofing utilizing 60 mil self adhered membrane roof underlayment.
6. Remove/replace existing P.T. 2 x 12 fascia and wrap with .032 Kynar standard color
aluminum.
7. Install Gulf Coast 12" O.C..032 Kynar standard color aluminum standing seam
roofing/trim with 25 year paint finish and 20 year watertight warranty.
8. Removal of siding material from ceiling elevation above.
9. Remove and replace all exterior soffits with James Hardi vented soffit
10. Provide new James Hardi Ceiling over existing.
11. Replace fire sprinkler heads in exterior ceiling.
12. All James Hardi Materials shall be color plus "Dove Grey".
13. All fasteners shall be stainless steel.
14. All are non -egress windows.
15. Recoat structural metal connectors on 6 Pavilions to include: Hand -tool clean, grind to
remove loose rust scale. Spot prime bare metal with Amercoat 1 component Epoxy.
Apply 1 full coat of Amercoat Epoxy Apply 2 top coats of Durethane DTM Urethane
Mastic.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
16. Prepare, concrete and steel substrates and stucco 40 concrete columns with color
entrained synthetic stucco.
17. Remove existing Tight fixtures on ceiling and replace with HALO H7RICAT remodel
recessed cans, Halo 30wat white baffle trims and LED R30 12 watt amber turtle friendly
lamps. 11 new cans total. 9 (see cut sheets attached)
18. Replace existing wall mount fixture with 1 Progress P5712-30 white cylindrical fixtures
with LED R30 12 watt amber turtle friendly lamp. (see cut sheet attached)
19. Deposit all demolition materials in dumpsters provided by City to be located in parking
lot in ADA spaces South of Pier to be temporarily fenced by City for Iaydown yard.
Add Alternate Scope of Work:
1. Demolition and removal of 1st level vinyl siding up to the soffit and patio ceiling level.
Supply and install Color Plus Dove Grey, Hardi-lap siding with 60 mil peel and stick
underlayment. Exterior grade plywood and window replacement. Hardi Wrap all wood
columns, trim windows, doors, coreners and wall to soffit intersect with Hardi-Board
Trim. See detailed cost breakdown below.
Exclusions:
1. Concrete repairs.
2. Replacement of any structural connectors.
3. Replacement of structural framing, plywood or sheathing.
4. Plumbing or Mechanical Work.
5. Electrical work beyond what is described above.
6. Removal or replacement of low voltage mounted to building.
7. Termite or pest control.
8. Painting other than structural connectors on Pavilions.
9. Doors.
10. Temporary fencing at Iaydown yard in parking lot.
11. Permitting or permitting fees.
12. Materials testing.
13. Dumpsters or debris haul -off.
14. Warranty of any materials, fixtures or equipment supplied by owner.
15. Permitting or fees.
16. Engineering or architectural work.
17. Builder's Risk Insurance.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
Cost Detail:
12222 Anne Kenia Drive, Thonotosassa, FL 33592
Pier 60 Roofing. soffits and fascia siding
2
GENERAL CONDITIONS
Scaffolding (8 weeks included)
$20,707.46
6
TRIM AND ROUGH
CARPENTRY
Hardi Board Labor
$29,375.00
6
TRIM AND ROUGH
CARPENTRY
Replace 2x12 Fascia on
Pavilions
$2,856.00
6
TRIM AND ROUGH
CARPENTRY
James Hardi Package
$8,544.14
6
TRIM AND ROUGH
CARPENTRY
Plywood/Lumber/Peel and stick
$4,418.19
7
THERMAL AND
MOPISTURE
Roofing Metal and Install
$108,265.00
8
OPENINGS
Removal and Reinstall Turn
style
$1,120.00
9
FINISHES
Synthetic Stucco Columns (X40)
$10,400.00
9
FINISHES
Surface Prep and connector
treatment.
$12,000.00
15
MECH
Fire Sprinklers
$3,765.00
16
Elec
All
$3,156.00
SUB -SUBTOTAL
$204,606.80
General Conditions,
Supervision, Insurance,
Bond
$30,907.75
Owner Contingency
$30,600.00
OH&P
15.00%
$39,917.18
COST TOTAL AMOUNT
$306,031.73
Add Alternate 1st floor
6
TRIM AND ROUGH
CARPENTRY
Hardi Board/Window Labor
$22,500.00
6
TRIM AND ROUGH
CARPENTRY
Hardi Board Column Wraps
(X10) (Lab. and Mat.)
$1,892.30
6
TRIM AND ROUGH
CARPENTRY
James Hardi Package
$4,788.03
12222 Anne Kenia Drive, Thonotosassa, FL 33592
6
TRIM AND ROUGH
CARPENTRY
Plywood/Lumber/Peel and stick
$5,758.87
8
OPENINGS
Windows Materials
$8,822.54
SUB -SUBTOTAL
$43,761.74
General Conditions,
Supervision, Insurance,
Bond
$9,543.01
Owner Contingency
$6,900.00
OH&P
15.00%
$9,030.71
COST TOTAL AMOUNT
$69,235.46
Grand Total with Add Alternate for 1st floor siding and
windows
$375,267.19
Project Duration shall be 90 calendar days from the date of the Notice to Proceed. Onsite
Construction base contract is estimated at 8 weeks, add 4 weeks for 1st floor alternate. We will
require periodic shut downs of baithouse.
Existing Contract: This proposal is submitted in conjunction with the existing Construction
Manager at Risk Services Continuing Contract entered into with the City of Clearwater on June
15, 2016, based on RFQ #24-16.
If GMP Exceeds $150,000: Per Section III, Article 5.1 of the Contract Specifications, the
contractor shall provide to the public entity a certified copy of the recorded bond. Once the City
receives a certified copy of the recorded bond, a Notice to Proceed may be issued. Include the
attached bond form as well as the Power of Attorney.
For work performed, invoices shall be submitted to the City of Clearwater, Engineering
Department, Attn: Veronica Josef, Senior Staff Assistant, P.O. Box 4748, Clearwater, Florida,
33758-4748. Contingency services may be billed only after written authorization is provided by
the City to proceed with those services.
12222 Anne Kenia Drive, Thonotosassa, FL 33592
Camilo A. Soto
Assistant City Attorney
Countersigned:
€fJt!tC?tLk(
George N. Cretekos
Mayor
Date
KHORS C
By:
ori Khorsandian
President
126/7
Date
CITY OF CLEARWATER, FLORIDA
Attest:
B
Lam C
Rosemarie Call
City Clerk
iiiLazi4A 1,44v,4 -
William B. Horne II
City Manager
Date
12222 Anne Kenia Drive, Thonotosassa, FL 33592