SOLID WASTE TRANSFER STATION REPLACEMENT PROJECT - 15-0007-SW - CONSTRUCTION MANAGER @ RISK SERVICESConstruction Manager @ Risk Services for Solid Waste Transfer Station
This CONTRACT made and entered into this --a° day of /JJVlh,.6).-Y, 2017 by and
between the City of Clearwater, Florida, a municipal corporation, hereinafter designated as the
"City" or "Owner", and Kokolakis Contracting , of Tarpon Springs, County of Pinellas
and State of Florida, hereinafter designated as the "Construction Manager". The contracting
entities shall collectively be known as the "Parties."
WITNESSETH:
WHEREAS, the Clearwater City Council has approved using the Construction Manager at Risk
approach on appropriate projects as determined by the City's Engineering Department; and
WHEREAS, the City desires that the Construction Manager perform the management of the
necessary construction, design, and preconstruction services (collectively referred to as the
Services) on an as -needed basis subject to the terms and conditions set forth in this agreement
and any agreement incorporated into this agreement by reference.
NOW, THEREFORE, IT IS AGREED BY THE PARTIES:
ARTICLE 1: SCOPE OF WORK AND CONTRACT DOCUMENTS
1.1 The Construction Manager and its successors, assigns, executors or administrators, in
consideration of the sums of money, as herein after set forth to be paid by the City to the
Construction Manager, shall and will at its own cost and expense perform all labor, furnish
all materials, tools and equipment for all individual projects assigned as a result of this
contract.
1.2 For each individual project assigned, in accordance with such proposal and technical
supplemental specifications and such other special provisions and drawings, if any, which
will be submitted by the City, together with any advertisement, instructions to bidders,
general conditions, proposal and bond, which may be hereto attached, and any drawings, if
any, which may be herein referred to, are hereby made a part of this contract, and all of said
work to be performed and completed by the contractor and its successors and assigns shall be
fully completed in a good and workmanlike manner to the satisfaction of the City.
1.3 Unless otherwise specified in this contract, all work shall be completed in accordance with
Section III and Section IV of the City of Clearwater Contract Specifications (the
Specifications). For the purposes of this contract, the term Contractor in Section III shall
include the Construction Manager. The Specifications, as may be supplemented and changed,
along with this Contract constitute the "Contract Documents." In the event there is any
conflict between this Contract and the Specifications, this Contract shall take precedence
except that the GMP PROPOSAL dated 10/13/17 (as revised 10/16/17) is expressly
incorporated and made part of this Agreement. Further, the GMP Proposal shall be
determinative and control in the event of any conflict, discrepancy, absence of information
and / or term or condition to the contrary.
ARTICLE 2: CONSTRUCTION MANAGER'S DUTIES AND STATUS
2.1 The Construction Manager recognizes the relationship of trust and confidence established
between it and the City by this Agreement, and agrees with the City to furnish its best skill
and judgment and the overall supervision of its executives; to furnish efficient business
administration and superintendence; and to use every effort to keep upon the project site at all
times an adequate supply of workforce and materials to secure its execution and completion
in the most expeditious and economical manner.
2.2 The Construction Manager represents that it has made a thorough examination of the premises
and is thoroughly familiar with the conditions under which it is to work.
2.3 The Construction Manager agrees to perform and complete the Services in accordance with
laws, rules, and regulations of all governmental authorities and departments thereof.
2.4 The Construction Manager agrees to cooperate with the City, Architect -Engineer, or any other
Design Professional in all respects, including, but not limited to, providing necessary
preconstruction services, such as evaluation of methods, availability and costs of the various
components of the Services while under design consideration; supervising the Services and
the progress thereof; the coordination of the Services and suggesting changes in the Services;
and supplying information as to costs and availability of materials and methods of
construction in order, amongst other things, to reduce costs wherever the same may be
practicably consistent with the quality of the Services presented in the Contract Documents.
2.5 The Construction Manager agrees to the following:
a) In connection with the performance of work under this Contract, the Construction
Manager agrees not to discriminate against any employee or applicant for employment
because of race, sex, religion, color, or national origin. The aforesaid provision shall
include, but not be limited to, the following employment:
- upgrading
- demotion or transfer
- recruitment or recruitment advertising
- lay-off or termination
- rates of pay or other forms of compensation; and
- selection for training, including apprenticeship
b) The Construction Manager agrees to post hereafter in conspicuous places, available for
employees or applicants for employment, notices to be provided by the contracting
officer setting forth the provisions of the non-discrimination clause.
c) The Construction Manager further agrees to insert the foregoing provisions in all
contracts hereunder, including contracts or agreements with labor unions and/or
worker's representatives, except sub -contractors for standard commercial supplies or
raw materials.
2
ARTICLE 3: SCOPE OF THE SERVICES
3.1 The services that the Construction Manager shall provide include, but are not limited to
those described in the following sections.
3.2 Reporting - Written reports shall be provided with the monthly pay requests as follows:
a) Monthly Executive Summary which provides an overview of current issues and
pending decisions, future developments and expected achievements, and any
problems or delays, including code violations found by any permitting agency.
b) A Monthly Construction Progress Report that includes a cost narrative, a scheduling
narrative and that summarizes the work of the various subcontractors. This report
shall include information from the weekly job site meetings as applicable such as:
- general conditions
- long lead supplies
- current deliveries
- safety and labor relations programs permits
construction problems and recommendations; and
- plans for the succeeding month
3.3 Scheduling
a) Upon award of this Contract, the Construction Manager shall submit a master project
schedule covering the planning and design approvals, construction and Owner
occupancy of the Project. This schedule will serve as the framework for the
subsequent development of all detailed schedules. The master project schedule shall
be produced and updated monthly throughout the project.
b) Within thirty (30) days after the date of the Owner's issuance of a Notice to Proceed,
the Construction Manager shall prepare and submit to the Owner two copies of a
Critical Path Method (CPM) construction schedule graphically depicting the
activities contemplated to occur as a necessary incident to performance of the work
required to complete the project, showing the sequence in which the Construction
Manager proposes for each such activity to occur and duration (dates of
commencement and completion, respectively) of each activity.
c) Following development and submittal of the construction schedule the Construction
Manager shall, at the end of each calendar month during the project, or at such earlier
intervals as circumstances may require, update and/or revise the construction
schedule to show the actual progress of the work performed and the occurrences of
all events which have affected the progress of performance of work already
performed or will affect the progress of the performance of the work yet to be
performed in contrast with the planned progress of performance of such work, as
depicted on the original construction schedule and all updates and/or revisions thereto
as reflected in the updated and/or revised construction schedule last submitted prior
to submittal of each such monthly update and revision. Each such update and/or
revision to the construction schedule shall be submitted to the Owner in duplicate.
3
d) The Construction Manager shall provide current scheduling information and provide
direction and coordination regarding milestones, beginning and finishing dates,
responsibilities for performance and the relationships of the Construction Manager's work
to the work of his subcontractors and suppliers to enable them to perform their respective
tasks so that the development of construction progresses in a smooth and efficient manner
in conformance with the overall project schedule. The schedule shall include all phases of
the construction work, material supplies, long lease procurement, approval of shop
drawings, change orders in progress, schedules for change orders, and performance testing
requirements. The Construction Manager shall advise the Owner, its representatives and
the Architect -Engineer of their required participation in any meeting or inspection giving
each at least one week notice unless such notice is made impossible by conditions beyond
his control. The Construction Manager shall hold job -site meetings at least once each
month with the Construction Team and at least once each week with the subcontractors
and the Architect -Engineer's Field Representative, or more frequently as required by work
progress, to review progress, discuss problems and their solutions and coordinate future
work with all subcontractors.
e) Twice per month corresponding as closely as possible with progress review meetings, a
"two week" look ahead report shall be prepared and submitted to Owner and Architect /
Engineer.
3.4 Design Review and Recommendations
a) The Construction Manager shall familiarize himself thoroughly with the evolving
architectural, civil, mechanical, plumbing, electrical and structural plans and specifications
and shall follow the development of design through Contract Documents. The
Construction Manager shall make recommendations with respect to the selection of
systems and materials, and cost reducing alternatives including assistance to the Architect -
Engineer and Owner in evaluating alternative comparisons versus long term cost effect.
The evaluation shall speak to the benefits of the speed of erection and early completion of
the project. The Construction Manager shall furnish pertinent information as to the
availability of materials and labor that will be required. The Construction Manager shall
submit to the Owner and Architect -Engineer such comments as may be appropriate
concerning construction, feasibility, and practicality. The Construction Manager shall
bring to the Owner and the Architect -Engineer's attention any apparent defects in the
design, drawing and specifications, or other documents. The Construction Manager shall
prepare an estimate of the construction cost at appropriate milestones during the design and
shall evaluate such estimate with the project budget. The Construction Manager shall
recommend cost saving alternatives, as appropriate, at each design milestone. At each
design milestone the Owner, Architect Engineer and Construction Manager shall conduct
a value engineering review.
b) After receiving the Construction Documents for each phase of the project, the Construction
Manager shall perform a specific review thereof. Promptly after completion of the review,
the Construction Manager shall submit to the Owner, with a duplicate to the Architect -
Engineer, a written report covering suggestions or recommendations previously submitted,
additional suggestions or recommendations as the Construction Manager may deem
appropriate, and all actions taken by the Architect -Engineer with respect to same, any
comments he may deem to be appropriate with respect to separating the work into separate
contracts and/or alternative materials.
4
c) At completion of the Construction Manager's review of the plans and specifications, except
only as to specific matters as may be identified by appropriate comments pursuant to this
section, the Construction Manager shall warrant, without assuming any architectural or
engineering responsibility, that the plans and specifications are consistent, practical,
feasible and constructible. The Construction Manager shall warrant that the work described
in the plans and specifications for the various bidding packages is constructible within the
scheduled construction time.
d) The Construction Manager shall review the design for the purpose of identifying long lead
procurement items (i.e. machinery, equipment, materials and supplies). When each item is
identified, the Construction Manager shall notify the subcontractors, the Owner, and the
Architect -Engineer of the required procurement and schedule. Such information shall be
included in the bid documents and made a part of all affected sub -contracts. As soon as
the Architect -Engineer has completed drawings and technical specifications and the
Construction Manager has obtained permitting approval, the Construction Manager shall
prepare invitations for bids. The Construction Manager shall keep informed of the progress
of the respective subcontractors or suppliers, manufacturing or fabricating such items and
advise Project Director, Owner and Architect -Engineer of any problems or prospective
delay in delivery.
3.5 Staffing - Key personnel assigned to City projects by the Construction Manager shall not be
removed from the project until alternate personnel acceptable to the City are approved in
writing by the City.
3.6 Soliciting Bids
a) Without assuming responsibilities of the Architect -Engineer, and unless waived in writing
by the Owner, the Construction Manager shall prepare invitations for bids, or requests for
proposal when applicable, for all procurements of long lead items, materials and services,
and for Subcontractor contracts. Such invitations for bids shall be prepared in accordance
with the following guidelines:
i) Contracts totaling $1,000 but not exceeding $10,000 may be entered into by the
Construction Manager with the firm which is qualified and submits the lowest verbal
quotation. The Construction Manager shall obtain a minimum of two (2) verbal
quotations. These quotations shall be entered on a bid tabulation sheet and a copy of
such tabulation sent to the Owner, Architect -Engineer and to each firm. The successful
quotation shall be confirmed by written contract or purchase order to the low bid firm
defining the scope and quality of work to be provided.
ii) Contracts totaling $10,000 but not exceeding $200,000 may be entered into by the
Construction Manager with the firm who is qualified and submits the lowest responsive
proposal. The Construction Manager shall request at least three (3) firms to submit
sealed written proposals based on written drawings and/or specifications. The written
proposals shall all be opened publicly at the location, date and time named by the
Construction Manager in his request for proposal. A tabulation of the results shall be
furnished to the Owner, Architect -Engineer and to each firm.
iii) Contracts totaling $200,000 but not exceeding $500,000 may be entered into by the
Construction Manager with the firm who is pre -qualified and submits the lowest
responsive proposal. The Construction Manager shall advertise these projects at least
once with the last advertisement appearing at least 21 calendar days prior to the
established bid opening date. These proposals shall be based on approved plans and
specifications. Bids shall be received and opened publicly at the location, date and time
established in the bid advertisement.
iv) Contracts totaling $500,000 or greater shall be treated the same as described under iii
above except that the advertisement shall be run for at least 30 days prior to the
established bid opening and at least 5 days prior to any scheduled pre-bid conference.
v) Individual purchases of materials or rentals or leases of equipment of up to $999.99
each may be made without bids or quotes when reasonably necessary to expedite work
on the project; however, the Construction Manager shall not divide or separate a
procurement in order to avoid the requirements set forth above.
vi) Site utilities may be acquired at market rates from the entity(ies) providing such in the
franchise area.
b) For each separate construction contract exceeding $35,000, the Construction Manager shall,
unless waived by Owner, conduct a pre-bid conference with prospective bidders, the Architect -
Engineer and the Owner. In the event questions are raised which require an interpretation of
the bidding documents or otherwise indicate a need for clarification or correction of the
invitation, the Construction Manager shall transmit these to the Architect -Engineer and upon
receiving clarification or correction in writing shall prepare an addendum to the bidding
document, and issue same to all of the prospective bidders.
3.7 Quality Control - The Construction Manager shall develop and maintain a program,
acceptable to the Owner and Architect -Engineer that assures quality control of the
construction. The Construction Manager shall supervise the work of all subcontractors
providing instruction to each when their work does not conform to the requirements of the
plans and specifications and shall continue to assert influence and control over each
subcontractor to ensure that corrections are made in a timely manner so as to not affect the
efficient progress of the work. Should disagreement occur between the Construction Manager,
the Owner or the Architect -Engineer over acceptability of work and conformance with the
requirements of the specifications and plans, the Owner shall be the final judge of
performance and acceptability.
3.7 Subcontractor Interfacing - The Construction Manager shall be the single point of interface
with all subcontractors for any work done under this Contract. The Construction Manager shall
negotiate all change orders, field orders and request for proposals, with all affected
subcontractors and shall review the costs of those proposals and advise the Owner and
Architect -engineer of their validity and reasonableness, acting in the Owner's best interest
prior to requesting approval of each change order from the Owner. Before any work is begun
on any change order, a written authorization from the Owner must be issued. When health and
safety are threatened, however, the Construction Manager shall act immediately to remove
such threat to health and safety. The Construction Manager shall also carefully review all shop
drawings and then forward the same to the Architect -Engineer for review and actions. The
Architect -Engineer will transmit them back to the Construction Manager who
6
will then issue the shop drawings to the affected subcontractor for fabrication or revision. The
Construction Manager shall maintain a record to promote expeditious handling. The
Construction Manager shall request the Architect -Engineer to make interpretations of the
drawings or specifications requested of him by the subcontractors and shall maintain a record
to promote timely response. The Construction Manager shall advise the Owner and Architect -
Engineer when timely response is not occurring on any of the above. The Construction
Manager shall collect, review and submit to the Owner, all project closeout documentation
including operation, maintenance and training manuals.
ARTICLE 4: MAXIMUM PROJECT COST AND FEES FOR SERVICES
4.1 Guaranteed Maximum Price for Construction
a) When the Construction Documents are sufficiently complete to establish the scope of work
for the project or any portion thereof, the Construction Manager will establish and submit
in writing to the Owner for his approval a Guaranteed Maximum Price (GMP) guaranteeing
the maximum price to the Owner, for the construction cost of the project or designated part
thereof. Such Guaranteed Maximum Price will be subject to modification for changes in
the project as provided in article 4.1(e) below. Actual price paid for the work by the Owner,
however, shall be the actual cost of all work subcontracts, supply contracts, direct labor
costs, direct supervision costs and direct job costs, plus the Construction Manager's fees
or the GMP, whichever is less when the work is complete. Invoicing shall occur monthly
for completed work with 5% retainage withheld until final completion and acceptance of
all work covered in the contract documents in accordance to the City's General Conditions.
b) At the time of submission of a Guaranteed Maximum Price, the Construction Manager will
verify the time schedule for activities and work which were adopted and used to determine
the Construction Manager's cost of work. In addition to the cost of work, a GMP will
include an agreed upon sum as the construction contingency which is included for the
purpose of defraying the expenses due to unforeseen circumstances relating to
construction. The Construction Manager will be required to furnish documentation
evidencing expenditures charged to the contingency prior to the release of funds by the
Owner. If bids are received below the applicable line items in the GMP, the surplus will be
added to the contingency.
c) If bids are received above the applicable line item in the GMP, the deficiency will be taken
from the contingency; however, such occurrence shall not be cause to increase the GMP.
d) If bids are not received for a portion of the work at or below the applicable line item amount
in the GMP, the Construction Manager reserves the right to perform that portion of the
work as acknowledged by the Owner or negotiate for its performance for the specified line
item lump sum amount or less.
e) The increase or decrease in the Guaranteed Maximum Price resulting from a change in the
Project shall be determined in one or more of the following ways:
7
i. By mutual acceptance of a lump sum properly itemized and supported by sufficient
substantiating data to permit evaluation by the Architect Engineer and owner;
ii. By unit prices stated in the Agreement or subsequently agreed upon;
iii. If none of the methods is agreed upon, the Construction Manager, provided it has
received a signed written order by the Owner, shall promptly proceed with the work
involved. The cost of such work shall then be determined on the basis of the
reasonable expenditures and savings of those performing the work attributed to the
change. In the event a Change Order is issued under these conditions, however, the
Architect -Engineer will establish an estimated cost of the work and the
Construction Manager shall not perform any work whose cost exceeds that estimate
without prior written approval by the Owner. In such case, the Construction
Manager shall keep and present, in such form as the Owner may prescribe, an
itemized accounting together with appropriate supporting data of the increase in the
Cost of the Project. The amount of decrease in the Guaranteed Maximum Price to
be allowed by the Construction Manager to the Owner for any deletion or change
which results in a net decrease in cost will be the amount of the actual net decrease;
iv. The Architect -Engineer will have authority to order minor changes in the Project
not involving an adjustment in the Guaranteed Maximum Price or an extension of
the Construction Completion Date and not inconsistent with the intent of the
Drawings and Specifications. Such changes shall be effected by written order.
Documentation of changes shall be determined by the Architect -Engineer. Changes
shall be approved by the Architect -Engineer.
4.2 Construction Manager's Fee - In consideration of the performance of the contract, the
Owner agrees to pay the Construction Manager as compensation for his services, fees as set
forth below:
a) Preconstruction Phase Fee - shall be based on design costs if applicable,
constructability review, value engineering and fee determination of Guaranteed
Maximum Price. The fee for this phase in the amount of $99,450 shall be paid at the
negotiated price upon receipt of the Guaranteed Maximum Price.
b) Construction Phase Fee - Prior to commencement of the Construction Phase, the Owner
will direct the Construction Manager in writing to proceed into the Construction Phase.
The Construction Manager's compensation for work or service performed during the
Construction Phase shall be a fee of $1,069,921. The Construction Phase Fee shall be
invoiced and paid in 22 months. Payments will be remitted monthly at the cost of
$ 48,632 each and one final monthly payment of $48,649.The first monthly payment shall
become due thirty days following the issuance of the first Construction Authorization and
the final monthly payment shall be paid only when construction of the project is completed
and occupancy of the project accepted by the Owner. If construction is authorized only for
a part of the project, the fee paid shall be proportionate to the amount of work authorized
by the Owner
8
ARTICLE 5: TERMINATION AND TIME OF THE ESSENCE
5.1 If the Construction Manager is adjudged bankrupt or makes a general assignment for the benefit
of creditors, or if a receiver is appointed on account of its insolvency, or if refuses or fails,
except in cases for which an extension of time is provided, to supply enough properly skilled
workmen or proper materials for the Services, or otherwise be guilty of a substantial violation
of any provision of this Agreement as determined by the certificate of the Architect, the Owner
may, without prejudice and reserving any other right or remedy the Owner may have, after
giving the Construction Manager seven (7) days' written notice, terminate the employment of
the Construction Manager and take possession of the premises and all materials, tools, and
appliances thereon and finish the Project in whatever manner the Owner may deem expedient.
5.2 It is mutually agreed between the parties hereby that time is of the essence of this contract, and
in the event that the Substantial Completion Date is not achieved within the time stipulated
herein, it is then further agreed that the City may deduct from such sums or compensation as
may be due to the Construction Manager, the sum of $1,000.00 per day for each day that the
work to be performed by the Construction Manager remains incomplete beyond the time limit
specified herein, which sum of $ 1,000.00 per day shall only and solely represent damages
which the City has sustained by reason of the failure of the Construction Manager to complete
the work within the time stipulated, it being further agreed that the sum is not to be construed
as a penalty but is only to be construed as liquidated damages for failure of the Construction
Manager to complete and perform all work within the time period as specified in this contract.
ARTICLE 6: INDEMNIFICATION
6.1The Construction Manager and his or its successors and assigns does hereby agree to assume
the defense of any legal action which may be brought against the City as a result of the
Construction Manager's activities arising out of this contract and furthermore, in
consideration of the terms, stipulations and conditions as contained herein, agrees to hold the
city free and harmless from any and all claims for damages, costs of suits, judgments or
decrees resulting from any claims made under this contract against the city or the contractor
or the contractor's sub -contractors, agents, servants or employees resulting from activities by
the aforementioned contractor, sub -contractor, agent servants or employees.
6.2 Nothing contained herein shall be construed as a waiver of any immunity from or limitation
of liability the City (Owner) may be entitled to under the doctrine of sovereign immunity or
section 768.28, Florida Statutes.
ARTICLE 7: TITLE TO THE PROJECT
7.1 The title of all work, completed portions of the Project and in the course of construction, and
of all materials on account of which payment has been made shall be in the Owner.
9
ARTICLE 8: ASSIGNMENT
8.1 This Agreement shall be binding upon and inure to the benefit of the Parties hereto and their
respective successors and assigns, except that this Agreement may not be assigned by either
party without the prior written consent of the other party. Any assignment made without such
prior written consent shall not vest rights in the assignee.
ARTICLE 9: ADDITIONAL PROVISIONS
9.1 This Agreement shall be governed by and construed in accordance with the laws of the State
of Florida, and the venue for any dispute under this Agreement shall be an appropriate court
of competent jurisdiction in Pinellas County, Florida.
9.2 Any notice required to be given by the terms and provisions of this Agreement or by any law
or governmental regulation, either by the Owner or Construction Manager, shall be in writing
unless otherwise required by such law or regulation and shall be deemed to have been served
and given when deposited in either Registered or Certified Mail in United States Branch Post
Office, addressed to the party hereto to whom directed, at the address specified in the
Specifications.
9.3 The language in this Agreement shall be construed according to its customary meaning
within the Florida building industry. Whenever used, the singular shall include the plural, the
plural the singular, and the use of any gender shall be applicable to all genders.
9.4 If any provision of the Contract Documents is invalid or unenforceable as against any person
or party, the remainder of the Contract Documents and the applicability of such provision to
other persons or parties shall not be affected thereby.
9.5 Nothing contained in this Agreement shall be construed to mean that the Construction
Manager and Owner are joint ventures or partners.
Public Records Requirements:
The successful bidder/contractor will be required to comply with Section 119.0701, Florida
Statues (2013), specifically to:
(a) Keep and maintain public records that ordinarily and necessarily would be required by
the City of Clearwater in order to perform the service;
(b) Provide the public with access to public records on the same terms and conditions that
the City of Clearwater would provide the records and at a cost that does not exceed the
cost provided in this chapter or as otherwise provided by law;
(c) Ensure that public records that are exempt or confidential and exempt from public
records disclosure requirements are not disclosed except as authorized by law; and
10
(d) Meet all requirements for retaining public records and transfer, at no cost, to the City of
Clearwater all public records in possession of the contractor upon termination of the
contract and destroy any duplicate public records that are exempt or confidential and
exempt from public records disclosure requirements. All records stored electronically
must be provided to the public agency in a format that is compatible with the
information technology systems of the City of Clearwater.
IN WITNESS WHEREOF, the parties to the agreement have hereunto set their hands and seals
and have executed this Agreement, in duplicate, the day and year first above written.
CITY OF CLEARWATER
IN PINELLAS COUNTY, FLORIDA
By: r/I%.IJ 4-4.,, „ 43- 9.444. :
William B. Horne II City Manager
Countersigned:
By: —CkW M1.e r\ci t\4OS
George N. Cretekos, Mayor
(Contractor must indicate whether
Corporation, Partnership, company
or Individual)
(The person signing shall, in his own handwriting
sign the Principal's name, his own name and his
title; where the person is signing for a Corporation
he must, by Affidavit, show his authority to bind the
Corporation).
11
Rosemarie Call, City Clerk
Camilo Soto, Assistant City Attorney
Corporation
Kokolakis Contracting
By:
c
Rod rick Voigt, Vice Pr
0 :' Go:;C
•
SE
19
• , F10Fee0p'
/471i1Ni11111110\\\\
mm 1)
R' -
BRIGHT AND BEAUTIFUL • BAY TO BEACH
Prepared for: City of Clearwater
Date: October 13, 2017
REVISED
1:33 pm, Oct 16, 2017
SOLID WASTE TRANSFER STATION REPLACEMENT PROJECT
PROJECT NO.: 15 -0007 -SW
FINAL GUARANTEED MAXIMUM PRICE
41K
KOKOLAKIS
Prepared by: Kokolakis Contracting
202 E. Center Street, Tarpon Springs, FL 34689
(727) 942-2211 • www.jkokolakis.com
TABLE OF CONTENTS
CITY OF CLEARWATER
SOLID WASTE TRANSFER STATION REPLACEMENT PROJECT
Section One:
Section Two:
Section Three:
Section Four:
Section Five:
Section Six:
Section Seven:
Section Eight:
CLEC"' R
BRIGHT ANI) BEAI.f I IFL'L • BAY TO BEACH
Summary of Work
GMP Estimate
Schedule of Allowances
Schedule of Alternates
Schedule of DPO Items
Clarifications
Construction Schedule
List of Documents
2
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOK0LAKIS
SECTION ONE
SUMMARY OF WORK
3
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKIS
Summary of Work
Preface
The projects consist of demolishing the existing waste transfer station to allow for the construction of a
new waste transfer station, administration building, new truck scales and scale house.
Perm its
Kokolakis Contracting, Inc. shall submit plans and specifications to the City of Clearwater Building
Department for review. The cost for the plan review fees, NOI permit fees, State Fire Marshal fees and
the building permit fee are not included.
Coachman Ridge Park
The Coachman Ridge Park scope consists of reconfiguring the existing park to enlarge the storm water
retention pond for floodplain compensation and wetland mitigation. The excess fill from the Coachman
Ridge Park site will be utilized at the Waste Transfer Station site. A pedestrian bridge is included across
the retention pond. Additionally, new reconfigured asphalt and concrete walkways are included.
Solid Waste Transfer Station
Exported fill from the Coachman Ridge Park site will be transported to the Solid Waste Transfer Station
site for preloading phase. Preloading consists of filling and compacting the area along the new ramp and
monitoring the settlement until the compaction and loading is sufficient for the new construction. This
method is anticipated as a six month process.
After preloading, the City will vacate the property to allow for reconstruction of the SWTS site. The SWTS
will remain closed for the duration of construction.
The replacement portion of this project consists of demolition of existing facilities. New 665sf Scale building
and scales, New 22,870SF top load Transfer Station building, and a New 1,576SF Administration building.
Site Improvements include: New asphalt roadways and parking areas for tractor trailers and employee
vehicles, storm water improvements including new box culvert at main entrance. 15,000 -gallon Leachate
storage tank, natural gas fueling station for City vehicles. stand-by generator, new water service, fire water
main, and diesel -powered fire booster pump system and rerouting of the sanitary and electrical services.
Schedule
The overall project duration is 22 months. The initial phase involves bringing in fill material for the
preloading soil densification process. After all soil is placed. the preloading duration is scheduled for 6
months. During this time, all existing transfer station activities will remain in operation. Upon acceptance
of the preloading settlement by the geo-technical engineer. transfer station construction will commence
and will require the shut -down of the existing transfer station for approximately 12 months.
The anticipated Notice to Proceed with construction is anticipated on or about 1/24/2018, this is based
on receiving Board approval 11/2/2017 and issuance of building permits. Site mobilization for both the
Coachman Ridge Park site and Solid Waste Transfer Station site is anticipated to begin 1/25/2018. The
completion of the Coachman Ridge Park work is anticipated on or about 9/21/2018. Preloading
settlement at the Transfer Station site is anticipated to be complete 10/21/2018: this date assumes
settlement to be reached within six months. Based on the preloading settlement date above, the
anticipated Substantial Completion date for the project is 10/2/2019 and Final Completion is 10/31/2019.
End of Section
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
SECTION TWO
GMP ESTIMATE
5
Project: Solid Waste Transfer Station Reconstruction
Location: 1005 Old Coachman Rd, Clearwater, FL
Est. Date: Friday, October 13, 2017
LEED In/al Permit Documents GMP
KO KOLAKIS
Div.
Description
Responsibility
Total
Division 1
General Requirements
General Conditions
SEE NEXT TAB
$1,580,908
01 32 23
Surveying - Site
Ferguson Surveyors
$68,000
01 32 23
Preloading Monitoring Allowance
Allowance
$45,000
01 45 29
Material Testing
Arehna
$74,630
01 54 23
Scaffolding
w/ Trades
$0
01 79 00
Closeout - Demonstration and Training
JKC
$2,500
NPDES Permits
JKC
$750
$0
Division 2
Existing Conditions
02 30 00
Subsurface Ing estigation
By Owner
$0
02 40 00
Demolition and Structure Moving
Crisdel
$37,740
02 50 00
Site Work
Crisdel
$3,534,767
MSE Walls
RWH Construction
$208,213
Geo -Web Soil Stabilization Allowance
Allowance
$150,000
Prefabricated Bridge
Bridge Builders
$173,196
Landscaping
Roush
$257,022
Landscaping Adjustment Allowance (Zoning)
Allowance
$15,000
Fencing
Bravo Fence
$67,916
$0
Division 3
Concrete
03 10 00
Concrete Forming and Accessories
In Concrete
$0
03 20 00
Concrete Reinforcing
In Concrete
$0
03 30 00
Cast -in -Place Concrete
Ervin Bishop
$3,261,478
Termite Treatment
In Concrete
$0
Dewatering Allowance
Allowance
$75,000
03 36 60
Chemically Stained Concrete Floor
Soutland
$8,700
03 60 00
Grouting
In Concrete
$0
03 80 00
Concrete Topping (Laticrete)
Cornerstone
$659,143
$0
Division 4
Masonry
04 22 00
Concrete Unit Masonry
Ervin Bishop
$45,900
04 27 00
Glass Unit Masonry
Glass Block Warehot
$13,249
$0
$0
Division 5
Metals
05 12 00
Structural Steel Framing
Morrow Steel
$734,837
05 12 00
Structural Steel
In Steel
$0
05 12 00
Armor Push Plates
In Steel
$0
05 21 00
Steel Joist Framing
In Steel
$0
05 31 00
Steel Decking
In Steel
$0
6
Project: Solid Waste Transfer Station Reconstruction
Location: 1005 Old Coachman Rd, Clearwater, FL
Est. Date: Friday, October 13, 2017
Eli)!i n/a I Permit Documents GMP
44K
KO KO LAKIS
Div.
Description
Responsibility
Total
05 51 00
Aluminum Stairs and Walkway
In Steel
$0
05 52 00
Aluminum Handrails
In Steel
$0
05 53 00
Aluminum Gratings
In Steel
$0
05 53 00
Miscellaneous Steel & Embeds
In Steel
$0
$0
Division 6
Wood, Plastics, and Composites
06 10 00
Rough Carpentry
w/ Trades
$0
06 40 00
Cabinets and Countertops
Distinct Designs
$9,775
$0
Division 7
Thermal and Moisture Protection
07 10 00
Dampproofing and Waterproofing
Above All
$40,400
07 21 00
Building Insulation
w/ Trades
$0
07 27 00
Air Barriers
In Dampproofing
$0
07 53 00
Membrane Roofing
Allied Roofing
$37,720
07 62 00
Flashing and Sheet Metal
In Roofing
$0
07 70 00
Roof and Wall Specialties and Accessories
In Roofing
$0
07 70 00
Roof Curbs for Roof -Top Package HVAC Units
w/ HVAC
$0
07 70 00
Roof Access Ladders
In Steel
$0
07 90 00
Joint Protection
In Dampproofing
$0
$0
Division 8
Openings
08 10 00
Doors and Frames
Integrated Doors
$66,232
08 33 00
Coiling Doors and Grilles
Overhead Door
$38,420
08 52 00
Aluminum Windows
Countryside Glass
$13,167
08 71 00
Hardware
In Doors
$0
08 80 00
Glazing
In Windows
$0
08 95 00
Translucent Panel Systems
Specified Architectur
$76,500
$0
Division 9
Finishes
A5.03
Plaster and Gypsum Board Assemblies
Cornerstone Lathing
$40,020
A2.04 - A3.05
Cement Stucco
Cornerstone Lathing
$33,450
Tile Allowance
Spectra
$3,535
Resinous Flooring
Allowance
$8,310
09 51 00
Acoustical Ceilings
Pardee
$9,460
09 90 00
Painting and Coating
B & G Painting
$86,960
$0
Division 10
Specialties
10 14 00
Signage
Environmental
$963
10 26 00
Wall and Door Protection
Watkins
$790
10 50 00
Lockers
Watkins
$3,130
10 52 00
Portable Fire Extinguishers
Watkins
$875
Project:
Location:
Est. Date:
LEED In/a]
Solid Waste Transfer Station Reconstruction
1005 Old Coachman Rd, Clearwater, FL
Friday, October 13, 2017
Permit Documents GMP
41K
KO KOLAKIS
Div.
Description
Responsibility
Total
10 80 00
Toilet Accessories
Watkins
$4,170
10 80 00
Knox Box
JKC
$846
$0
Division 11
Equipment (Crane, CNG Station, Pit Brushes)
11 15 00
Knuckleboom Cranes
Built -Rite
$594,544
11 30 00
CNG Packaged Pump Station
Allowance
$750,000
Pneumatic Teller System
Deleted
$0
Pit Brushes
JKC/SESCO
$11,000
$0
Division 13
Special Construction (Metal Bldg, Leachate Tank, Truck Scales, Operator Booth)
13 12 20
Pre -Engineered Metal Building Fabrication
Varco Pruden
$762,600
13 21 00
Double Wall Leachate Storage Tank
Highland Tank
$365,722
13 55 00
Truck Scales
FL Industrial Scale
$108,983
TBD
Operator's Booth
Panel Built
$70,550
$0
Division 15
Mechanical
15 30 00
Fire Suppression Sprinkler System
Cox Fire
$245,315
15 18 30
Refrigerant Piping
In HVAC
$0
15 41 00
Plumbing
R Carr Plumbing
$215,489
P0.02/P1.01-02
Eyewash and Shower
In Plumbing
$0
P0.02/P1.01-02
Hose Reels
In Plumbing
$0
V0.04
Drywell
In HVAC
$0
15 73 00
HVAC
Aircom
$264,758
15 95 00
HVAC Systems Testing
In HVAC
$0
$0
Division 16
Electrical
16 01 00
Electrical
All -Phase
$1,393,076
16 08 00
Electrical Testing
In Electric
$0
16 50 00
Lighting
In Electric
$0
13 10 00
Lightning Protection System
In Electric
$0
$0
Bare Costs
$16,270,709
Contingency
CM Fee
SUBTOTAL
P&P Bond Premium
GL Insurance Premium 2014-2015 (factored for 2016)
Builders Risk
Potential Sales Tax Savings
1.963%
$350,000
6.00% $1,069,921
7.96%
0.632%
0.5200%
By Owner
-0.36%
$17,690,629
$112,718
$92,726
$0
($64.063)
TOTAL
8.76% $17,832,0109
8
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
SECTION THREE
SCHEDULE OF ALLOWANCES
r
KOKOLAKIS
9
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
Schedule of Allowances
4NK
KOKOLAKIS
Allowance
Number
Description
Amount
1
Preloading Monitoring
$45,000
2.
Dewatering
$75,000
3.
Resinous Flooring
$8,310
4.
CNG Packaged Pump Station
$750,000
5.
Additional Geo -Web Soil Stabilization
$150,000
6.
Landscaping Adjustment (Zoning)
$15,000
End of Section
10
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
SECTION FOUR
SCHEDULE OF ALTERNATES
.8K
KOKOLAKIS
11
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKIS
Schedule of Alternates
Alternate
Number
Description
Amount
1.
Provide small missile impact Kalwall panels in lieu of large
missile impact.
$(5,300)
End of Section
12
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOL_AKIS
SECTION FIVE
SCHEDULE OF DPO ITEMS
13
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKIS
Schedule of Direct Purchase Order (DPO) Items
Item #
Description
1.
Truck Scales
2.
Leachate Tank
3
Knuckleboom Cranes
4.
CNG Skid Mount Pump Station
5.
Fire Pump
End of Section
14
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
SECTION SIX
CLARIFICATIONS
ar<
KOKOLAKIS
15
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
Clarifications and Assumptions
esisK
KOKOLAKIS
Preface
The proposal incorporates a number of assumptions regarding the project that further explains the scope,
program, or quality of construction. The following are a summary of these assumptions. These
assumptions and clarifications take precedence over all contract documents.
General Clarifications
1. This proposal is based on:
• Interim Report of the Geotechnical Investigation issued by Driggers Engineering Services,
Inc., dated September 24, 2014.
• Addendum to Interim Report of the Geotechnical Investigation issued by Driggers
Engineering Services, Inc., dated October 9, 2015.
• Estimate Normal Season High Groundwater Levels, Coachman Ridge Park Test Borings
issued by Driggers Engineering Services, Inc., dated December 8, 2015.
• Permit drawings and specifications issued by King Engineering Associates, Inc., dated
August 11, 2017.
• Addendum 01, issued by King Engineering Associates, Inc., dated August 30, 2017.
• Addendum 02, issued by King Engineering Associates, Inc., dated September 18, 2017.
• Addendum 03, issued by King Engineering Associates, Inc., dated September 27, 2017.
The cost for Builder's Risk Insurance and related deductibles for any and all perils, are not included
in the contract price. If the Sales Tax Savings Program is implemented; Owner shall purchase and
maintain the Builder's Risk Insurance Policy including assuming responsibility for all deductibles
throughout the life of the project and will comply with State Procurement Regulations for Owner
Purchases. Kokolakis Contracting, Inc. shall be listed as an additional insured on the Builder's Risk
Policy and a copy of the policy will be made available on request. If Owner elects not to procure
Builder's Risk Insurance for the project, then the Owner will act as the insurer for the protection of
both the Owner and Kokolakis Contracting, Inc. and its subcontractors and suppliers. In addition,
if Builder's Risk Insurance is not procured, then upon request Owner will execute a standard Hold
Harmless Agreement for the benefit of Kokolakis Contracting, Inc. which will confirm that the Owner
has assumed the responsibility of all claims which could have been covered by Builder's Risk
Insurance and all related deductibles.
To maintain cost efficiency, and to pass the savings on to our clients, our general liability is based
on estimated volume of annual revenue, and therefore is not calculated nor invoiced as a project
specific rate. The rate included within the GMP and agreed to by the parties is 0.52% and shall be
invoiced as part of the first pay application.
4. Building Permit and Impact Fee costs of any kind are not included as they are to be paid directly
by Owner. Permits associated with Water Management Districts, Florida Department of
Environmental Protection (including air quality. water. sanitary sewer, SWPPP, Asbestos
Abatement or Lead Abatement) are to be procured by Architect/Engineer or Owner. The cost for
NOI and NPDES permits is included.
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
41K
KOKOLAKIS
Coordination with local utility providers for new or existing utilities to be facilitated by
Architect/Engineer and all pre -construction and post -construction requirements to be listed on
Construction Documents.
6. All warranties commence on the date of project substantial completion or beneficial use.
7. The costs contained within the Proposal, unless specifically noted otherwise, are based upon
manufacturer's standard listings of colors, finishes, etc.
8. If Owner elects to participate in the Sales Tax Savings Program, materials available for purchase
shall exceed $5,000 in value each, savings to accrue to Owner Contingency. The sales tax savings
will be credited via deductive change order for all materials purchased within the program.
9. A credit is included in the GMP Estimate for anticipated sales tax savings. This credit is based on
the anticipated savings for large ticket items only. The credit will be reconciled at the end of the
project and will be adjusted via the DPO change order listed above. Please refer to Section 5 of
this GMP for the list of large ticket items that comprise the credit indicated.
10. The costs for temporary power and water use are not included as they will be furnished by the
Owner free of charge to the contractor.
11. Electronic copies of record drawings are not included. Two sets of record drawings will be provided
to Owner at completion of project indicating all modifications in colored ink. Kokolakis Contracting.
Inc. can provide the Architect / Engineer with record documents in a scanned PDF document.
CADD or REVIT as-builts are not included. Site survey data is included in AutoCAD as indicated
in specification 01720.
12. The costs for Asbestos Surveys, Hazardous Material Surveys or Lead Testing are not included.
Lead testing and removal requirements are listed on http://www.epa.gov/lead/.
13. The demolition, abatement, removal or disposal of any contaminated, hazardous materials
including but not limited to asbestos, lead, toxic saturated materials as well as any other unforeseen
subsurface conditions such as sink holes, radon gas, unsuitable soils and abandoned utilities are
not included. Hazardous materials surveys or engineering are excluded as well.
14. Costs for soil compaction, concrete and masonry quality control services, inspections of all
structural bolted and welded connections are included.
15. Threshold inspections are not included
16. Payment and Performance Bonds are included.
17. Work hours in accordance with City of Clearwater ordinances and as negotiated with Owner.
18. The aggregate amount of outstanding change directive shall be capped at 25% of the Construction
Manager's Fee.
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKIS
19. Unit rates and percentages listed within the contract are agreed to as Lump Sums and are therefore
not auditable.
20. The cost to provide a separate trailer with furnishings for the Owner / Engineer on site as indicated
in specification 01500, sections D, E, F, G and H is not included. Kokolakis Contracting, Inc. will
occupy the scale house during construction and will accommodate meetings and Owner / Engineer
site visits within this space.
Scope Clarifications
1. An Allowance is included for dewatering during foundation, site utility and leachate tank installation.
2. Laticrete Emery Aggregate Top 400 concrete 2" topping is included as indicated in specification
03350. The cost for the epoxy Drytek primer indicated as an option in specification 03350, section
2.02-F is not included.
3. Detail C/S5.06 is not included as trench drains are included as Zurn drains as indicated in the
plumbing schedule which utilizes a different detail.
4. A total of (53) concrete -filled pipe bollards are included at the Waste Transfer Station site.
5. Shop prime and paint finish is not included for the push plates and embeds.
6. Roofing for the Administration and Scale House buildings is included as a Johns Mansville TPO
roof system.
7. Roof copings, gutters and downspouts are included as 050 Kynar-finished aluminum.
8. Fluid applied air barrier is included for the exterior wall of the Administration and Scale House
buildings.
9. Kalwall translucent wall panels are included as large missile impact panels. An Alternate to reduce
the panels to small missile impact is included in the Schedule of Alternates section.
10 Overhead doors are included as a motor operated Series 625 doors manufactured by Overhead
Door Corporation.
11. PGT Level D aluminum windows with clear anodized frames are included in lieu of CGI Estate
Collection Series 410 windows.
12. Window glass is included as Solarban SB70 clear impact insulated Low E glass.
13. Ceramic tile at the bathroom, shower walls and shower floor is included as Daltile 6" square semi-
gloss field tile from manufacturers standard colors.
14. Resinous epoxy floor is included at the bathroom floors in lieu of stained concrete floors.
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKtS
15 Two new truck scales are included. The truck scales are Weigh-tronix BMC -HD -7011 truck scales
with factory guard rails. Western Weighing Aurora 45 remote display with pole -mounted 4.5" LED
readout, and weigh-tronic XM405 digital indicator. The cost for a desktop or laptop computer is not
included.
16 The cost for (2) built -rite model 2100 stationary knuckleboom cranes with remote power units and
dual remote operator stations is included.
a. The dual controls consist of one manual hydraulic override controls and one electronic
control.
b. A 21" trash tamping grapple is included.
c. A 5 -year maintenance agreement is included. The maintenance agreement includes costs
to conduct regular scheduled maintenance intervals. The cost for routine, daily
maintenance such as greasing, tightening of fittings & bolts, etc. is not included.
Additionally, maintenance agreement does not include damage to the loader or grapple due
to neglect or abuse.
17. A pre -assembled control booth is included as manufactured by Panel -Built, Inc. Signed and sealed
drawings are included for the pre -assembled room and the staircase.
18. The Transfer Station building is included as a Varco-Pruden pre-engineered metal building.
PrisMAX skylights are included.
19. The cost to provide hydraulic calculations and engineered drawings for the fire sprinkler system is
included. The fire sprinkler subcontractor shall design a system based on performance specs.
20. The cost to furnish and install a packaged fire pump is included.
21. The pump indicated on sheet P1.01 is included as a Goulds 1AB21HM04 constant pressure 1 -HP
booster system.
22. Air conditioning for the control booth is provide as part of the building HVAC system as indicated
on sheet V1.01 in lieu of a unit provided as part of the pre -assembled room package.
23. The lightning protection system is included as indicated in specification 13100.
24. CCTV system including head -end equipment, cameras, wiring, and terminations is not included.
The conduit raceway system is included to support the cameras where indicated.
25. Fiber optic cables and connections between buildings is not included. This work will be furnished
by the Owner.
26. The cost for a pre -fabricated pedestrian bridge at Coachman Ridge Park is included. This bridge
is included as manufactured by Bridge Builders USA. Inc.
27 The cost for a temporary leachate tank system is included.
28. Sod is included for pond banks in lieu of hydro seeding.
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KOKOLAKIS
29. An Allowance is included for additional trees that may be required by the Zoning Department.
30. The cost for additional geo-web soil stabilization is included as an Allowance.
End of Section
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
SECTION SEVEN
CONSTRUCTION SCHEDULE
*AK
KOKOLAKIS
21
Line
Unique Task ID
Preconstruction
Contract Administration
PR -00-0100
Name
Duration Start Finish
2017
2018
2019
MA i M i J J r A i S i 0 i N i D i J i FMA i M i J J i A i S i O i N, D i J i F, M i A i M, J i J A r S i 0,a1
113 13 124 105 15 126 117 i7 128 118 19 130 120 ill I1 122 i12 15 126 116 17 128 118 19 130 X20 i10 11 X20 112 13 124 154 14 125 i18 JO X29 X20 110 it r22 0..2 12 103- r14 14
Approval of GMP
ld 11/2/2017* 11/2/2017
22 26 30 34 38 42 46 50 54 58 62 66 70 74 78 82 86 90 94 98 102 106 110 114 118 122 126 130 134 138 142 146 150 154
Approval of GMP
2
PR -00-0101
Notice of Award
10d 11/3/2017 11/16/2017
Notice of Award ❑
3
4
PR -00-0200
PR -00-0201
Performance & Payment Bonds
ld 11/17/2017 11/17/2017
Project Insurance Submission
ld 11/17/2017 11/17/2017
5
PR -00-0300
Project Permit Review by AHJ
15d 11/17/2017 12/8/2017
Performance & Payment Bonds
Project Insurance Submission I
Project Permit Review by 003
6
PR -00-0400
Notice to Proceed - Contract Administration
ld 11/20/2017 11/20/2017
Notice to Proceed - Contract Administration I
7
PS -00-0100
Building/Project Permit Procurement
30d 12/11/2017 1/23/2018
Building/Project Permit Procurement
I I
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
25
26
27
PS -00-0200 Notice to Proceed - Construction
Submittals
SM -00-0100
SM -00-0130
SM -00-0151
SM -00-0154
SM -00-0157
SM -00-0160
SM -00-0190
SM -00-0220
SM -00-0250
SM -00-0280
SM -00-0310
SM -00-0340
SM -00-0370
SM -00-0400
Submit PEMB Package - Transfer Bld
Submit CMU & Reinforcing Package
Submit Concrete Mix Design - Transfer Building
Submit Concrete Reinforcing Shops - Transfer Building
Submit Structural Steel Shops - Transfer Building
Submit Concrete Mix Design - Scale Bld
Submit Concrete Reinforcing Shops - Scale Bld
Submit Concrete Mix Design - Admin Bld
Submit Concrete Reinforcing Shops - Admin Bld
Submit Structural Steel Shops - Scale Bld
Submit Structural Steel Shops - Admin Bld
Submit Roofing System Package - Scale Bld
Submit Roofing System Package - Admin Bld
ld 1/24/2018 1/24/2018
15d 11/21/2017 12/12/2017
5d 11/21/2017 11/28/2017
5d 11/21/2017 11/28/2017
Notice to Proceed - Construction I
Submit PEMB Package - Transfer Bid MI
Submit CMU & Reinforcing Package
Submit Concrete MS Design - Transfer Building
20d 11/21/2017 12/19/2017 Submit Concrete Reinforcing Shops - Transfer Building
15d 11/21/2017 12/12/2017
5d 11/21/2017 11/28/2017
15(1 11/21/2017 12/12/2017
5d 11/21/2017 11/28/2017
15d 11/21/2017 12/12/2017
15d 11/21/2017 12/12/2017
15d 11/21/2017 12/12/2017
5d 11/21/2017 11/28/2017
5d 11/21/2017 11/28/2017
Submit Structural Steel Shops - Transfer Building
Submit Concrete Mix Design - Scale Bld
Submit Concrete Reinforcing Shops - Scale Bld -
Submit Concrete Mix Design - Admin Bid,
Submit Concrete Reinforcing Shops - Admin Bq -
Submit Structural Steel Shops - Scale Bid I'
Submit Structural Steel Shops - Admin.Old -
Submit Roofing System Package - Scale BM
Submit Roofing System Package - Admin Old,
Submit Stucco Package - Scale Bld
5d 11/21/2017 11/28/2017
Submit Stucco Package • Scale B d
I -:)t)-0430 Submit Stucco Package - Admin Bld
5d 11/21/2017 11/28/2017
Submit Stucco Package - MmM'BN,
,M-00-0460 Submit Window/Glazing Package
,M-00-0490 Submit Doors & Frames
-M-00-0520 Submit Door Hardware
:sM-00-0550
Submit Metal Framing
20d 11/21/2017 12/19/2017
5d 11/21/2017 11/28/2017
15d 11/21/2017 12/12/2017
5d 11/21/2017 11/28/2017
Submit Window/Glazing Package IIIIIII.
Submit Doors & Frames I
Submit Door Hardware -
Submit Metal Framing
JK
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
a
° Ciearsvater
H
_.......„,,..,„......
U........,„,.......„...
Run Date: 10/13/ 2017
Page l of 16
Line
Unique Uni Task ID
q
Name
Duration
Start
Finish
2017 2018 2019
M, A M i l 3 1 A S 0 N D, 3 F 1 M A 1 M 3 3 A S i O N 1 D 3 1 F M i A i M i 1 i 3 A i S i 0 i N
03 13 124 105 15 126 117 17 128 Ile 19 130 120 ill 11 122 132 15 126 116 17 128 118 19 130 120.110 11 122 112 13 124 104 14 125 118 18 129 120 0.0 11 122 112 12 123.104.14
c22 ,26 130 134 138 142 146 150 154 158 162 166 170 174 78 182 186 190 194 198 1102 1106 1110 1114 ,118 1122 1126 1130 1134 1138 1142 1146 1150 1154 1
28
SM-00-0580
Submit Gypsum Board Package
5d
11/21/201711/28/2017
Submit Gypsum Board Package I
29
SM-00-0610
Submit Acoustical Ceiling Tile System
5d
11/21/2017
11/28/2017
Submit Acoustical Ceiling Tile System
30
SM-00-0640
Submit Electrical Components & Gear
15d
11/21/2017
12/12/2017
Submit Electrical Components & Gear
31
SM-00-0670
Submit Plumbing System Components
15d
11/21/2017
12/12/2017
Submit Plumbing System Components
32
SM-00-0700
Submit Plumbing Fixtures
15d
11/21/2017
12/12/2017
Submit Plumbing Fixtures mu
33
If SM-00-0730
Submit Ceramic Tile
15d
11/21/2017
12/12/2017
Submit Ceramic Tile El
34
SM-00-0760
Submit Paint Package
5d
11/21/2017
11/28/2017
Submit Paint PackageI
35
SM-00-0790
Submit Duct Shop Drawing Package
5d
11/21/2017
11/28/2017
Submit Duct Shop Drawing Package,
36
SM-00-0820
Submit HVAC Accessories Package
5d
11/21/2017
11/28/2017
Submit HVAC Accessories Package,
37
SM-00-0850
Submit AHU Units
15d
11/21/2017
12/12/2017
Submit AHU Units M
38
SM-00-0880
Submit HVAC Controls System
15d
11/21/2017
12/12/2017
Submit HVAC Contras System ir
39
SM-00-0910
Submit Fire Alarm System
15d
11/21/2017
12/12/2017
Submit Fire Alarm System Er
40
SM-00-0940
Submit CCN & Security System Package
15d
11/21/2017
12/12/2017
Submit CCTV & Security System Package
41
SM-00-0970
Submit Light Fixture Package
15d
11/21/2017
12/12/2017
Submit Light Fixture Package IIE
42
SM-00-1000
Submit Casework Package
15d
11/21/2017
12/12/2017
Submit Casework Package K
43
SM-00-1030
Submit T&B Accessories Package
5d
11/21/2017
11/28/2017
SubmitT&B Accessories Package
44
SM-00-0140
Approve CMU & Reinforcing Package
10d
11/29/2017
12/12/2017
Approve CMU & Reinforcing Package en
45
SM-00-0152
Approve Concrete Mix Design - Transfer Building
10d
11/29/2017
12/12/2017
Approve Concrete Mix Design -Transfer Building
46
SM-00-0170
Approve Concrete Mix Design - Scale Bld
10d
11/29/2017
12/12/2017
Approve Concrete MIS Design - Scale Bld Q
47
SM-00-0230
Approve Concrete Mix Desing - Admin Bld
lad
11/29/2017
12/12/2017
Approve Concrete Mix Desing - Admin Bld C
48
SM-00-0350
Approve Roofing System Package - Scale BId
10d
11/29/2017
12/12/2017
Approve Roofing System Package - Scale Bld ❑
49
SM-00-0380
Approve Roofing System Package - Admin Bld
10d
11/29/2017
12/12/2017
Approve Roofing System Package - Admin Bid Q
50
SM-00-0410
Approve Stucco Package - Scale Bld
10d
11/29/2017
12/12/2017
Approve Stucco Package - Scale Bld Q
51
SM-00-0440
Approve Stucco Package - Admin BId
l0d
11/29/2017
12/12/2017
Approve Stucco Package - Admin Bld Q
52
SM-00-0500
Approve Doors & Frame
l0d
11/29/2017
12/12/2017
Approve Doors & Frame Q
53
SM-00-0560
Approve Metal Framing
l0d
11/29/201712/12/2017
Approve Metal Framing El
54
SM-00-0590
Approve Gypsum Board Package
10d
11/29/2017
12/12/2017
Approve Gypsum Board Package Q
55
SM-00-0620
Approve Acoustical Ceiling Tile System
10d
11/29/2017
12/12/2017
Approve Acoustical Ceiling Tile System 0
56
SM-00-0770
Approve Paint Package
10d
11/29/2017
12/12/2017
Approve Paint Package E
57
SM-00-0800
Approve Duct Shop Drawing Package
10d
11/29/2017
12/12/2017
Approve Duct Shop Drawing Package
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/ 13/2017
Page 2 of 16
Ckarwater
Line
Uni ue Task ID
9
Name
Duration
Start
Finish
2017 2018 2019
M, A M: 3 J, A 5 O N D: 3 F, M A, M ) J A S, O N, D, J F M, A M J, 3 .A,S, O, N
,13 ,3 ,24 ,15 5 ,26 ,37 17 ,38 158 19 130 120 ,11 ,1 ,22 ,1.2 ,5 126 156 ,7 ,28 ,18 ,9 130 ,30 ,50 ,l ,33 ,12 ,3 ,34 ,54 ,4 ,35 ,58 ,0 ,39 ,20 ,50 ,l R2 A5 ,3 ,33 ,N 01
,22 26 30 34 38 42 46 150 ,54 58 ,62 ,66 .70 ,74 ,78 ,82 ,86 90 ,94 98 102 1106 ,110 ,114 ,118 122 ,126 ,130 ,134 ,138 1142 1146 :150 154
58
SM -00-0830
Approve HVAC Accessories Package
ltd
11/29/2017
12/12/2017
Approve HVAC Accessories Package
59
SM -00-1040
Approve T&B Accessories Package
ltd
11/29/2017
12/12/2017
Approve TM Accessories Package ■
60
SM -00-0110
Approve PEMB Package - Transfer Bld
30d
12/13/2017
1/25/2018
Approve PEMB Package - Transfer Bid -
61
SM -00-0150
Fabricate & Deliver CMU & Reinforcing Package
10d
12/13/2017
12/27/2017
Fabricate & Deliver CMU & Reinforcing Package U
62
SM -00-0153
Fabricate & Deliver Concrete Transfer Building
5d
12/13/2017
12/19/2017
Fabricate & Deliver Concrete Transfer Building,
63
SM -00-0158
Approve Structural Steel Shops - Transfer Building
30d
12/13/2017
1/25/2018
Approve Structural Steel Shops - Transfer Buildhg
64
SM -00-0180
Fabricate & Deliver Concrete - Scale Bld
5d
12/13/2017
12/19/2017
Fabricate & Deliver Concrete - Scale 81d
65
SM -00-0200
Approve Concrete Reinforcing Shops - Scale Bld
30d
12/13/2017
1/25/2018
Approve Concrete Reinforcing Shops - Scale Bld
66
SM -00-0240
Fabricate & Deliver Concrete Mix Design - Admin Bld
5d
12/13/2017
12/19/2017
Fabricate & Deliver Concrete Mix Design - Admin Bld i
67
. SM -00-0260
Approve Concrete Reinforcing Shops - Admin Bld
30d
12/13/2017
1/25/2018
Approve Concrete Reinforcing Shops - Admin BW
68
SM -00-0290
Approve Structural Steel Shops - Scale Old
30d
12/13/2017
1/25/2018
Approve Structural Steel Shops - Scale Bid
69
SM -00-0320
Approve Structural Steel Shops - Admin Bld
30d
12/13/2017
1/25/2018
Approve Structural Steel Shops - Admin Bld _
70
SM -00-0360
Fabricate & Deliver Roofing System Package - Scale Bld
15d
12/13/2017
1/4/2018
Fabrkate & Deliver Roofing System Package - Scale Bld -
71
SM -00-0390
Fabricate & Deliver Roofing System Package - Admin Bld
15d
12/13/2017
1/4/2018
Fabricate & Deliver Roofing System Package - Admin Bid -
72
SM -00-0420
Fabricate & Deliver Stucco Package - Scale Bld
5d
12/13/2017
12/19/2017
Fabricate & Deliver Stucco Package - Scale 81d 1
73
SSS -00-0450
Fabricate & Deliver Stucco Package - Admin Bld
5d
12/13/2017
12/19/2017
Fabricate & Deliver Stucco Package - Admin Rldit
74
511-00-0510
Fabricate & Deliver Doors & Frames
5d
12/13/2017
12/19/2017
Fabricate & Deliver Doors & Frames
75
SM -00-0530
Approve Door Hardware
30d
12/13/2017
1/25/2018
Approve Door Hardware IIIIII
76
51.1-00-0570
Fabricate & Deliver Metal Framing
5d
12/13/2017
12/19/2017
Fabricate & Deliver Metal Framing
77
51.1-00-0600
Fabricate & Deliver Gypsum Board Package
5d
12/13/2017
12/19/2017
Fabricate & Deliver Gypsum Board Package ro
78
SM -00-0630
Fabricat & Deliver Acoustical Ceiling Tile System
5d
12/13/2017
12/19/2017
Fabricat & Delver Acoustical Ceiling Tile System 0
79
q SM -00-0650
Approve Electical Components & Gear
30d
12/13/2017
1/25/2018
Approve Electical Components & Gear
80
i SM -00-0680
Approve Plumbing System Components
30d
12/13/2017
1/25/2018
Approve Plumbing System Components
81
SM -00-0710
Approve Plumbing Fixtures
30d
12/13/2017
1/25/2018
Approve Plumbing Fixtures
82
' SM -00-0740
Approve Ceramic Tile
30d
12/13/2017
1/25/2018
Approve Ceramic Tile 1111.1
83
SM -00-0780
Fabricate & Deliver Paint Package
5d
12/13/2017
12/19/2017
Fabricate & Deliver Paint Package
84
SM -00-0810
Fabricate & Deliver Duct Package
5d
12/13/2017
12/19/2017
Fabricate & Deliver Duct Package I
85
SM -00-0840
Fabricate & Deliver HVAC Accessories Package
5d
12/13/2017
12/19/2017
Fabricate & Deliver HVAC Accessories Package,
86
SM -00-0860
Approve AHU Units
30d
12/13/2017
1/25/2018
Approve AHU Untts
87
SM -00-0890
Approve HVAC Controls System
30d
12/13/2017
1/25/2018
Approve HVAC Controls System_
..K -
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
a
° Ciearsvater
U
Run Date: 10/13/2017
Page 3 at 16
Line
Unique Task ID
Name
Duration
Start
Finish
2017 2018
2019
M , A , M , 1 , 1 , A, 5 , O , R , 0 , ) , F , M , A , M , 1 , 1 , A , 5 , 0 , 11 , 0 , 1 , F , M , A , M , ) r 1 , A , S , 0 ,M
113 13 ,24 115 15 126 117 17 128 ,18 ,9 ,30 ,20 ,11 ,1 ,20 112 ,5 ,26 ,16 17 ,28 118 19 130 130 110 ,9 130 112 13 ,24 114 14 ,35 ,18 18 ,39 120 ,10 11 ,20 ,12 12 123 104 14
88
89
90
91
92
SM -00-0920
SM -00-0950
SM -00-0980
SM -00-1010
SM -00-1050
Approve Fire Alarm System
Approve CCTV & Security System Package
Approve Light Fixture Package
Approve Casework Package
Fabricate & Deliver T&B Accessories Package
30d
30d
30d
30d
5d
12/13/2017
12/13/2017
12/13/2017
12/13/2017
1/25/2018
......._ ....
1/25/2018
1/25/2018
1/25/2018
,22 ,26 30 ,34 ,38 ,42 ,46 ,50 ,54 ,58 ,62 ,66 ,70 .74 ,78 ,82 ,86 ,90 ,94 ,98 ,102 ,106 ,110 ,114 ,118 ,122 ,126 ,130 ,134 ,138 ,142 ,146 ,150 ,154
Approve Fire Alarm System -
Approve CCTV & Security System Package -
12/13/2017
12/19/2017
Approve Light Fixture Package
Approve Casework Package -
Fabricate & Deliver T&B Accessories Padtage
93
94
SM -00-0155
SM -00-0470
Approve Concrete Reinforcing Shops - Trans! , r Building 30d
12/20/2017
Approve Window/Glazing Package 30d
12/20/2017
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
c SM -00-0120 Fabricate & Deliver PEMB Package -Transfer Hid
5M-00-0159 Fabricate & Deliver Structural Steel - Transfer Building
• sM-00-0210 Fabricate & Deliver Concrete Reinforcing - Scale Bld
SM -00-0270 Fabricate & Deliver Concrete Reinforcing - Admin Bld
SM -00-0300 Fabricate & Deliver Structural Steel Shops - Scale Bld
SM -00-0330 Fabricate & Deliver Structural Steel Shops - Admin Bld
SM -00-0540 Fabricate & Deliver Door Hardware
SM -00-0660 Fabricate & Deliver Electrical Components & Gear
',\1-00-0690 Fabricate & Deliver Plumbing System Components
SM -00-0720 Fabricate & Deliver Plumbing Fixtures
SM -00-0750 Fabricate & Deliver Ceramic Tile
SM -00-0870 Fabricate & Deliver AHU Units
SM -00-0900 Fabricate & Deliver HVAC Controls System
SM -00-0930 Fabricate & Deliver Fire Alarm System
SM -00-0960 Fabricate & Deliver CCTV & Security System Package
S\t-00-0990 Fabricate & Deliver Light Fixture Package
S\1-00-1020 Fabricate & Delivery Casework Package
60d
1/26/2018
2/1/2018
2/1/2018
4/19/2018
Approve Concrete Reinforcing Shops - Transfer Building -
Approve Window/Glazing Package -
Fabricate & Deliver PEMB Package - Transfer Ski
30d
1/26/2018
3/8/2018
30d
30d
30d
30d
1/26/2018
3/8/2018
Fabricate & Deliver Structural Steel - Transfer Building
Fabricate & Deliver Concrete Reinforcing - Scale Bid
1/26/2018
3/8/2018
Fabricate & Deliver Concrete Reinforcing - Admin Glcl
1/26/2018
3/8/2018
Fabricate & Deliver Structural Steel Shops - Scale Bid
1/26/2018
30d
30d
30d
30d
30d
30d
30d
30d
30d
30d
30d
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
1/26/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
3/8/2018
Fabricate & Deliver Structural Steel Shops - Admin Old 10
Fabricate & Deliver Door Hardware,
Fabricate & Delver Electrical Components & Ge,,,
Fabricate & Delver Plumbing System Components -
Fabricate & Deliver Plumbing Fixtures -
Fabricate & Deliver Ceramic Tile -
Fabricate & Deliver AHU Units 11F-1
Fabricate & Deliver HVAC Controls System lirr-1
Fabricate & Deliver Fire Alarm System
Fabricate & Deliver CCN & Security System Package
Fabricate & Deliver Light Fixture Package
Fabricate & Delivery Casework Package NM
S\1-00-0156
S\1-00-0480
1'K-00-1000
Fabricate & Deliver Concrete Reinforcing - Transfer Building
Fabricate & Deliver Window/Glazing Package
Install SWPPP Controls
30d
30d
5d
2/2/2018
2/2/2018
1/25/2018
3/15/2018
3/15/2018
1/31/2018
Fabricate & Deliver Concrete Reinforcing - Transfer Building
Fabricate & Deliver Window/Glazing Package
Install SWPPP Controls
115
PK -00-1010
Layout Ground Excavation Limits
6d
2/1/2018
2/8/2018
Layout Ground Excavation LJmes,
411K
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
a
o ClearWater
f -
U
Run Date: 10/13/2017
Page k f lfi
Unique Task ID
Name
Duration
Start
Finish
2017 2018 2019
M, A M 1 ] A s O N D ] F, M A, M ] ] A 5, 0 N, D ], F M A M ] ] A S O, NLine
,13 ,3 ,24 ,15 ,5 ,26 07 .7 ,28 0.8 ,9 ,30 ,20 ,11 0. ,22 02, 15 ,26 ,16 0 128 118 19 ,30 20 ,10 0 22 0.2 3 ,24 ,14 ,4 125 118 ,9 ,29 ,20 110 10 ,22 ,12 ,2 ,23 ,14 ,4
,22 26 ,30 74 ,38 ,42 ,46 ,50 ,54 ,58 ,62 ,66 170 ,74 J78 ,82 ,86 ,90 ,94 ,98 ,102 ,106 ,110 ,114 1118 ,122 ,126 ,130 ,134 ,138 442 1146 1150 ,154 ,
116 ! PK -00-1040
117 PK -00-1050
118 PK -00-1060
119 PK -00-1070
Demo Existing Paving Locations
3d
2/1/2018
2/5/2018
Demo Exiting Paving Locations'
Owner Removal of Existing Playgrounds
3d
2/1/2018
2/5/2018
Owner Removal of Exiting Playgrounds'
Demo Existing Basketball Court
5d
2/1/2018
2/7/2018
Demo Existing Basketball Court 1
Saw Cut and Isolate Existing Limits of Construction
5d
2/1/2018
2/7/2018
Saw Cut and Isolate Existing Limits of Construction,
120
PK -00-1030
Clear and Grubb
20d
2/9/2018
3/8/2018
Clear and Grubb En
121
PK -00-1020
Excavate Si Transport Pre -Loading Fill Materials
25d
3/9/2018
4/12/2018
Excavate 8 Transport Pre -Loading Fill Materials _
122
PK -00-1080
Shape Ponds
45d
4/13/2018
6/15/2018
Shape Ponds IIIIIIIIIIIIIIIII,
123
124
125
126
PK -00-1090
PK -00-1120
PK -00-1130
PK -00-1160
Install Sidewalks
20d
6/18/2018
7/16/2018
Install Sidewalks MI
Restore Manhole Structure
5d
6/18/2018
6/22/2018
Restore Manhole Structure
Install New Storm Water Management System
20d
6/18/2018
7/16/2018
Install New Storm Water Management System III
Install Irrigation System
30d
6/18/2018
7/30/2018
Install IrrgadonSystem _
127 PK -00-1100
128 PK -00-1110
Install Trail Systems
20d
7/17/2018
8/13/2018
Install Trail Systems IMI
Install Fibermech SOG
IOd
7/17/2018
7/30/2018
-
Install ermech SOG •
Flt
129 PK -00-1140
Install Sod
7d
8/14/2018
8/22/2018
Install Sod ■
130 PK -00-1101
131 PK -00-1150
Install Boardwalk
Install Landscaping
20d
20d
8/23/2018
8/23/2018
9/20/2018
9/20/2018
Install Boardwalk ill.
Install Landscaping IIII♦
132 PK -00-1151
Site
133 SI -00-2020
Completion of Park
Install SWPPP Controls
ld
5d
9/21/2018
1/25/2018
9/21/2018
1/31/2018
Completion of Park
Install SWPPPControls /
134 SI -00-2030
Clear and Grubb
20d
2/1/2018
2/28/2018
Clear and Grubb
135 51-00-2060
136 SI -00-2080
Conduct Selective Site Demo
Install Leachate Bypass System
20d
3/1/2018
3/28/2018
Conduct Selective Site Demo
5d
3/1/2018
3/7/2018
Install Leachate Bypass System
137 SI -00-2000
Install Pre -Loading Settlement Plates
ld
3/29/2018
3/29/2018
Install Pre -Loading Settlement Plates I
138 SI -00-2010
Preloading Material Settlement
180d
4/13/2018
10/12/2018
Preloading Material Settlement
139 SI -00-0100
140 SI -00-0110
141 SI -00-0120
142 5I-00-0151
143 5I-00-0160
144 SI -00-0170
Install Reclaimed Water Line
Install Potable Water Line
15d
I5d
10/15/2018
10/15/2018
11/2/2018
Install Reclaimed Water Line MI
11/2/2018
Install Potable Water Line.]
Install Sanitary Force Main Line
20d
10/15/2018
11/9/2018
Instal Sanitary Force Main Line=
Site Electrical Power
30d
3M
15d
10/15/2018
10/15/201811/26/2018
10/15/2018
11/26/2018
11/2/2018
Site Electrical Power INN
Install Fire Water Line
Install Fire Water Line -
Install Gas Line
Install Gas rine
r
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
LL
° Clearwater
U
Run Date: 10/13/2017
Page 5 of 16
on
Line Unique Uni Task ID
Q
Name
Duration
Start
Finish
20172018 2019
M, A M,] 3, A S O N D,] F, M A, M l ] A, S, 0 N, D, 3, F M, A M, 3, 3 A, S 0, N
,13 3 ,24 ,15 ,S ,26 ,17 ,7 ,28 ,18 ,9 30 ,20 At ,1 ,22 ,12 ,5 ,26 ,16 ,7 ,28 ,18 ,9 30 20 ,10 ,l 122 ,52 13 ,24 ,14 ,4 ,25 ,18 18 ,29 ,20 ,10 ,1 122 ,52 ,2 123 114 14
,22 ,26 ,30 34 138 ,42 ,46 ,50 54 ,58 162 ,66 ,70 c74 178 182 186 190 94 ,98 ,102 ,106 1110 ,114 ,118 ,122 1126 ,130 ,134 ,138 ,142 ,146 ,150 ,154 ,
145
146
147
SI -00-0180
SI -00-0190
SI -00-2040
Install Concrete Headwall No. 1
20d
20d
15d
10/15/2018
10/15/2018
10/15/2018
11/9/2018
11/9/2018
11/2/2018
Install Concrete Headwall No. 1 MI
Install Concrete Headwall No. 2 MI
Install Concrete Headwall No. 2
Demo existing Transfer Station..
Demo Existing Transfer Station
148
SI -00-0130
Install Steel Casing for Reclaimed Water Line
5d
11/5/2018
11/9/2018
Install Steel Casing for Reclaimed Water Line
Install Steel Casing for Potable Water Line,
149
SI -00-0140
Install Steel Casing for Potable Water Line
5d
11/5/2018
11/9/2018
150
SI -00-0150
Install Steel Casing for Gas Line
5d
11/5/2018
11/9/2018
Install Steel Casing for Gas Line
Install Irrigation System
20d
11/5/2018
12/3/2018
Install Irrigation System=
151
SI -00-2008
152
5I-00-2012
Install Leachate Storage System
20d
11/12/2018
12/10/2018
Install Leachate Storage System MI
153
5I-00-0171
Set Site Light Pole Bases
7d
11/27/2018
12/5/2018
Set Site Light Pole Bases i
154
5I-00-2003
Install Bahia Sod Main Site
10d
12/4/2018
12/17/2018
Install Baha Sod Mao Site.
Install Landscaping.
155
SI -00-2004
Install Landscaping
15d
12/4/2018
12/24/2018
156
5I-00-0172
Roughin Light Pole Bases
5d
12/6/2018
12/12/2018
Roughen Light Pole Bases®
157
5I-00-0173
Set Site Light Poles
3d
12/13/2018
12/17/2018
Set Site Light Poles II
158
159
SI -00-2051
SI -00-2052
Install Site Bollards
10d
5/20/2019
6/3/2019
Install Site Bollards.
Install Guard Railing System
20d
5/20/2019
6/17/2019
Install Guard Railing System ME
160
SI -00-2009
Install Site Retaining Wall Assembly
15d
8/9/2019
8/29/2019
Install Site Retaining Wall Assembly.
161
SI -00-2005
Asphalt Paving
5d
8/30/2019
9/6/2019
Asphalt Paving,
162
163
164
165
5I-00-2050
SI -00-2002
SI -00-2006
SI -00-2007
Demo Existing Scale House
Install Geoweb
Pavement Markings
Traffic Control Signage
3d
5d
2d
2d
9/9/2019
9/9/2019
9/9/2019
9/9/2019
9/11/2019
Demo existing Scale House
9/13/2019
9/10/2019
Install Geoweb I
Pavement Markings
9/10/2019
Traffic Control Signage I
166 SI -00-2001
Transfer Building
167 TB -00-2070
Install Bahia Sod Entry
Transfer Building Footprint Preparation
2d
5d
9/16/2019
11/5/2018
9/17/2019
11/9/2018
Install Bahia Sod Entry
'0
Transfer Building Footprint Preparation
168 TB -00-0100
Form SOGCL8-7
2d
11/12/2018
11/13/2018
Fawn SOG CL8a1
169 TB -00-0110
Soil Treat SOG 8-7
ld
11/14/2018
11/14/2018
sal Treat SOG 8-71
170 TB -00-0120
Reinforce SOG CL 8-7
5d
11/15/201811/21/2018
Reinforce SOG CL 8-71
171 TB -00-0130
Place SOG CL 8-7
ld
11/23/2018
11/23/2018
Place SOG CL 8-71
172 TB -00-0140
Form SOG CL 7-6
2d
11/26/201811/27/2018
Form SOG CL 7-61
173 TB -00-0150
SoilTreatSOG7-6
ld
11/28/201811/28/2018
Soil TreatSOG7-61
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
a
° ciearwater
r
F-
U
Run Date: 10/ 13/ 2017
Page 6 of 16
Line
Unique Task ID
Name
Duration
Start
Finish
2017
20182019
M, A M, 3 3, A S, O, N D, 3 F, M A,
M 3,
3 A, S, O N, D, 3,
F
M, A M,
3,
3 A,
5
0, N
13 ,3 124 115 ,5 ,26 17 ,7 ,28 ,18 19 ,50 ,20 ,11 ,1 ,22 ,52 ,5 ,26 ,16
,7 ,28 ,18
,9 ,30 ,20 ,10 ,1 ,22 0.2 ,1 X11 ,14 19
125
,18 ,Q 129 120
110 11
,22 ,12
,2
,23 ,14 ,4
,22 ,26 ,30 ,34 ,38 42 ,46 ,50 ,54 ,58 ,62 ,66 ,70 ,74 ,78
,82 ,86
,90 ,94 ,98 J02 ,106 ,110 0.14 ,118
0.22
,126 ,130 ,134
1138
,142 ,146
,150
,154 ,
174
TB -00-0160
Reinforce SOG 7-6
5d
11/29/2018
12/5/2018
Reinforce SOG 7-61
175
TB -00-0170
Place SOG 7-6
1d
12/6/2018
12/6/2018
Place 506 7-61
176
TB -00-0180
Form SOG CL 6-5
2d
12/7/2018
12/10/2018
Form SOG CL 6-5
177
TB -00-0190
Soil Treat SOG 6-5
ld
12/11/2018
12/11/2018
Soil Treat SOG 6-51
178
TB -00-0200
Reinforce SOG 6-5
5d
12/12/2018
12/18/2018
Reinforce SOG 6-5!
179
TB -00-0210
Place SOG 6-5
ld
12/19/2018
12/19/2018
Place 506 6-51
180
TB -00-0220
Form SOG 5-4
2d
12/20/201812/21/2018
Form SOG 54
181
TB -00-0230
Soil Treat SOG 5-4
ld
12/24/2018
12/24/2018
Soil Treat SOG 541
182
1 TB -00-0240
Reinforce SOG 5-4
5d
12/26/2018
1/2/2019
Reinforce SOG 541
183
TB -00-0250
Place SOG 5-4
ld
1/3/2019
1/3/2019
Place SOG 5-41
184
TB -00-0260
Form SOG 4-3
2d
1/4/2019
1/7/2019
Form SOG 4-31
185
TB -00-0270
Soil Treat SOG 4-3
Id
1/8/2019
1/8/2019
Soil Treat SOG 4-31
186
TB -00-0280
Reinforce SOG 4-3
5d
1/9/2019
1/15/2019
Reinforce 5064-31
187
TB -00-0290
Place SOG 4-3
ld
1/16/2019
1/16/2019
PlaceSoG4-31
188
189
TB -00-0300
TB -00-0530
Form SOG 3-2
Form Columns C 1 at Ground Floor
2d
5d
1/17/2019
1/17/2019
1/18/2019
1/23/2019
Form SOG 3-21
Form Columns C 1 at Ground Floor 1
190
191
TB -00-0310
TB -00-0770
Soil Treat SOG 3-2
Install Trench Drain No.1 at Tunnel
ld
2d
1/21/2019
1/21/2019
1/21/2019
1/22/2019
Soil Treat SOG 3-21
Install Trench Drain No. 1 at Tunnel'
192
TB -00-0320
Reinforce SOG 3-2
5d
1/22/2019
1/28/2019
Reinforce SOG 3-2 1
193
113-00-0540
Reinforce Columns C 1 at Ground Floor
12d
1/24/2019
2/8/2019
Rehforce Columns C 1 at Ground Floor N
194
TB -00-0330
Place SOG 3-2
ld
1/29/2019
1/29/2019
Ptace SOG 3-21
195
TB -00-0340
Form SOG 2-1
2d
1/30/2019
1/31/2019
Form SOG 2-1
196
197
TB -00-0350
TB -00-0780
Soil Treat SOG 2-1
Install Trench Drain No. 2 at Tunnel
ld
2d
2/1/2019
2/1/2019
2/1/2019
2/4/2019
Soil Treat 50G2 -1l
Instal Trench Drain No. 2 at Tunnel
198
1 TB -00-0360
Reinfoce SOG 2-1
5d
2/4/2019
2/8/2019
Reinfoce SOG 2-11
199
200
TB -00-0370
TB -00-0550
Place SOG 2-1
Place Columns Cl at Ground Floor
ld
3d
2/11/2019
2/11/2019
2/11/2019
2/13/2019
PlaceSOG2-1l
Place Columns C 1 at Ground Floor 8
201
202
203
TB -00-0380
TB -00-0410
TB -00-0440
Form CIP Walls along CL 8
Form OP Walls along CL 3
Form OP Walls along CL 1
5d
5d
5d
2/12/2019
2/12/2019
2/12/2019
2/18/2019
2/18/2019
2/18/2019
Form CIP Walls along CL 81
Form CIP Walk along CL 31
Form CIP Walls along CL 1®
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/13/ 2017
Page 7ol 16
: Clearwater
Line Unique Task ID
Name
Duration
Start
Finish
2017
2018 2019
M, A, M 3, 3 A S, O, N, D, 3, F, M, A, M 3 3 0 A 0 S 0 O, N, D 0 3, PM, A, M 1 3 A, S, O ,N
013 13 124 015 06 R6 57 7 128 ,18 ,9 ,30 ,20 ,11 11 022 012 ,5 126 ,16 7 ,28. X18 ,9 ,30 R0 010 ,1 ,25 ,R 03 R4 54 04 25 018 ,8 ,29 20 ,30 ,1 ,22 ,12 ,2 ,53
,22 26 030 034 038 042 ,46 50 ,54 ,58 62 066 070 074 78 082 ,86 090 94 098 0102 ,106 ,110 ,114 ,118 ,122 126 130 ,134 138 ,142 ,146 0.50 0.54
204 TB -00-0560
205 TB -00-0590
Form Columns C 2 at Ground Floor
3d
2/12/2019
2/14/2019
Form Columns C 3 at Ground Floor
3d
2/12/2019
2/14/2019
Form Columns C 2 at Ground Floor
Form Columns C 3 at Ground Floor I
206 TB -00-0570
Reinforce Columns C 2 at Ground Floor
3d
2/15/2019
2/19/2019
207 TB -00-0600
Reinforce Columns C 3 at Ground Floor
3d
2/15/2019
2/19/2019
Reinforce Columns C 2 at Ground Floor
Reinforce Columns C 3 at Ground Floor
208 TB -00-0390
209 TB -00-0420
210 TB -00-0450
Reinforce CIP Walls along CL 8
5d
2/19/2019
2/25/2019
Reinforce CII' Walls along CL 3
Reinforce CIP Walls along CL 1
5d
2/19/2019
2/25/2019
5d
2/19/2019
2/25/2019
Reinforce CIP Walls along CL 8
Reinforce CIP Walls along CL 3 0
Reinforce CIP Walls along CL 1 Q
211 TB -00-0580
212 TB -00-0610
Place Columns C 2 at Ground Floor
Place Columns C 3 at Ground Floor
2d
2/20/2019
2/21/2019
2d
2/20/2019
2/21/2019
Place Columns C 2 at Ground Floor I
Place Columns C 3 at Ground Floor I
213 TB -00-0400
214 TB -00-0430
215 TB -00-0460
Place CII' Walls along CL 8
Place CIP Walls along CL 3
Place CIP Walls along CL 1
ld
2/26/2019
2/26/2019
ld
2/26/2019
2/26/2019
ld
2/26/2019
2/26/2019
Place CIP Walk along CL s
Place CIP Walls along CL 31
Pace CIP Walk along CL 11
216 TB -00-0611
Form and Shore Tipping Floor Beams
lid
2/27/2019
3/12/2019
Form and Shore Tipping Floor Beams III
217 TB -00-0612
219 TB -00-0614
220 TB -00-0615
Reinforce Tipping Floor Beams
Place Tipping Floor Beams
Install Composite Steel Beam Assemblies at Tipping Floor
Form Tipping Floor Slab 8-7
10d
3d
5d
3/13/2019
3/27/2019
4/1/2019
3/26/2019
3/29/2019
4/5/2019
2d
4/1/2019
4/2/2019
Reinforce Tipping Floor Beams®
Place Tipping Floor Beams I
Install Composite Steel Beam Assemblies at Tipping Floor 11
Form lipping Floor Slab 8-71
221 TB -00-0616
Reinforce Tipping Floor Slab 8-7
5d
4/3/2019
4/9/2019
Reinforce Tipping Floor Slab 8-71
222 TB -00-1109
Form Leachate Drain Trench at Tipping Floor
2d
4/10/2019
4/11/2019
Form Leachate Drain Trench at Tipping Floor!
223 TB -00-1119
Place Leachate Drain Trench at Tipping Floor
2d
4/12/2019
4/15/2019
Place Leachate Drain Trends at Tipping Floor!
224 TB -00-0617
225 TB -00-0760
Place Tipping Floor Slab 8-7
Install Leachate Line at Tipping Floor
ld
4/16/2019
4/16/2019
5d
4/16/2019
4/22/2019
Place Tipping Floor Slab 8-71
Install Leachate Line at Tipping Floor 1
226 TB -00-0618
Form Tipping Floor Slab 7-6
2d
4/17/2019
4/18/2019
Form Tipping Floor Slab 7-6 1
227 TB -00-0619
Reinforce Tipping Floor Slab 7-6
5d
4/19/2019
4/25/2019
Reinforce Tipping Floor Slab 7-611
228 TB -00-0629
Place Tipping Floor Slab 7-6
ld
4/26/2019
4/26/2019
Place Tipping Floor Slab 7-61
229 TB -00-0639
Form Tipping Floor Slab 6-5
2d
4/29/2019
4/30/2019
Fonn Tipping Floor Slab 6-5 I
230 TB -00-0649
Reinforce Tipping Floor Slab 6-5
5d
5/1/2019
5/7/2019
Reinforce Tipping Floor Slab 6-5,
231 TB -00-0659
Place Tipping Floor Slab 6-5
ld
5/8/2019
5/8/2019
Place Tipping Floor Slab 6-51
232 TB -00-0669
Form Tipping Floor Slab 5-4
2d
5/9/2019
5/10/2019
Form Tipping Floor Slab 5-41
233 TB -00-0679
Reinforce Tipping Floor Slab 5-4
5d
5/13/2019
5/17/2019
Reinforce Tipping Floor Slab 5-4
r
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
in.
° I.iearwater
F
0
Run Date: 10/13/2017
Page 8 of 16
Line Unique Task ID
Name
Duration
Start
Finish
2017 2018
2019
M 1 A 1 M 1 3 1 3 1 A 1 S 1 0 1 R 1 D, 3 1 F 1 M, A 1 M 1 3 1 3 1 A 1 S 0 1 R 1 D 1 3 1 F 1 M 1 A 1 M i 3 1 3 A 1 5 1 0 16
113 13 124 115 18 126 ill 17 28 118 19 130 120 ill ,1 122 112 19 126 116 17 128 118 19 130 120 130 11 122 11213 124 114 14 125 118 18 129 ,20 ,10,11 122 112 12 123 114 14
122 26 130 34 ,38 142 46 150 154 158 62 166 70 174 178 182 186 190 194 198 1102 1106 ,110 1114 1118 ,122 1126 1130 1134 1138 1142 1146 150 1154
234 ■ TB -00-0689
Place Tipping Floor Slab 5-4
ld
5/20/2019
5/20/2019
Place Tipping Floor Slab 5-41
235 ■ TB -00-0699
Form Tipping Floor Slab 4-3
2d
5/21/2019
5/22/2019
Form Tipping Floor Slab 4-31
236 ■ TB -00-0709
Reinforce Tipping Floor Slab 4-3
5d
5/23/2019
5/30/2019
Reinforce Tipping Floor Slab 4.31
237 ■ TB -00-0719
Place Tipping Floor Slab 4-3
ld
5/31/2019
5/31/2019
Place Tipping Floor Slab 4.31
238 ■ TB -00-0729
Form Tipping Floor Slab 3-2
2d
6/3/2019
6/4/2019
Form Tipping Floor Slab 3-21
239 ■ TB -00-0739
Reinforce Tipping Floor Slab 3-2
5d
6/5/2019
6/11/2019
Reinforce Tipping Floor Slab 3-21
240 ■ TB -00-0749
Place Tipping Floor Slab 3-2
ld
6/12/2019
6/12/2019
Place Tipping Floor Slab 3-21
241 ■ TB -00-0759
Form Tipping Floor Slab 2-1
2d
6/13/2019
6/14/2019
Form Tipping Floor Slab 2-11
242 TB -00-0769
243 TB -00-0790
Reinforce Tipping Floor Slab 2-1
Erection Composite Steel Beams
5d
5d
6/17/2019
6/21/2019
6/17/2019
6/21/2019
Reinforce Tipping Floor Slab 2-111
Erection Composite Steel Beams 0
244 ■ TB -00-0779
Place Tipping Floor Slab 2-1
ld
6/24/2019
6/24/2019
Place lipping Floor Slab 2-11
245
246
2244
249
250
251
252
253
254
255
256
257
TB -00-0799
TB -00-0829
TB -00-0869
TB -00-0909
8-00-1079
I 3-00-1129
IB -00-1179
TB -00-1199
TB -00-1219
TB -00-1239
TB -00-1359
TB -00-0800
TB -00-0821
Form CIP Walls Along CL 8 at Tipping Floor
2d
6/25/2019
6/26/2019
Form QP Walls Along CL 8 at Tipping Flour!
Form CIP Walls Along Row A at Tipping Floor
Form CIP Walls Along Row F at Tipping Floor
2d
6/25/2019
6/26/2019
Form QP Walls Along Row A at Tipping Floor!
2d
6/25/2019
6/26/2019
Form QP Walls Along Row F at Tipping Floor!
Form CII' Walls at CL 3-2 at Tipping Floor
2d
6/25/2019
Install Door Frames
Electrical R/I at Ground Floor
F/A Roughin at Ground Floor
CCTV Roughin at Ground Floor
Plumbing Roughin at Ground Floor
Fire Sprinkler System at Ground Floor
Roughin Traffic Control System
Form Crane Pedestals
Install Pit Brushes
258
259
260
261
262
TB -00-0809 Reinforce CIP Walls along CL 8 at Tipping Floor
TB -00-0839 Reinforce CIP Walls Along Row A at Tipping Floor
TB -00-0879
TB -00-0919 Reinforce CIP Walls at CL3-2 at Tipping Floor
TB -00-0810 Reinforce Crane Pedestals
Reinforce CIP Walls Along Row F at Tipping Floor
5d 6/25/2019
15d 6/25/2019
5d 6/25/2019
5d 6/25/2019
15d 6/25/2019
15d 6/25/2019
3d 6/25/2019
2d 6/25/2019
3d 6/25/2019
3d
3d
6/27/2019
6/27/2019
6/26/2019
7/1/2019
7/16/2019
7/1/2019
7/1/2019
7/16/2019
7/16/2019
6/27/2019
6/26/2019
6/27/2019
Form QP Walls at CL 3-2 at Tipping Floor!
Install Door Frames 0
Electrical R/I at Ground Floor 0
F/A Roughin at Ground Floor Q
CCTV Roughin at Ground Floor 0
Plumbing Roughin at Ground Floor
Fire Spdnlder System at Ground Floor
Roughin Traffic Control System 0
Farm Crane Pedestals 1
Install Pit Brushes 0
7/1/2019
7/1/2019
Reinforce QP Walk along CL 8 at Tipping Floor
Reinforce QP Walk Along Row A at Tipping Floor
3d
6/27/2019
7/1/2019
Reinforce QP Walls Along Row F at Tipping Floor!
3d
6/27/2019
7/1/2019
3d
6/27/2019
7/1/2019
263 p TB -00-1369
Install Traffic Control Lighting
7d
6/28/2019
7/9/2019
Reinforce CIP Waw at CL3-2 at Tipping Floor!
Reinforce Crane Pedestals Q
Install Traffic Control Lighting
..sx
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
u.
u. 11e arwater
?
h
U
Run Date: 10/13/2017
Page 16
Line
Unique Task ID
Name
Duration
Start
Finish
2017 2018 2019
A M 1 S N D 3 F M 6 1 A O D J F M A M 30 ] A s 04 N
j 4 5 51 6 7 7A 8 8 9 O 0 6 6 7M 8 8 9 0 0 0 2 4 4 8 9 3
22 26 30 34 38 42 46 50 54 58 62 66 70 74 78 82 86 90 94 98 102 106 110 114 118 122 126 130 134 138 142 146 150 154
264
265
266
267
268
269
270
271
: TB -00-0819
TB -00-0859
TB -00-0899
{ TB -00-0920
TB -00-1089
% TB -00-1180
! TB -00-1200
` TB -00-0820
Place CIP Walls along CL 8 at Tipping Floor
Place CIP Walls Along Row A at Tipping Floor
ld
ld
7/2/2019
7/2/2019
7/2/2019
7/2/2019
7/2/2019
Place CIP Walls along CL 8 at Tipping Floor
Place QP Walls Along Row A at Tipping Floor
Place CIF Walls Along Row F at Tipping Floor
ld
7/2/2019
Place QP Walls Along Row F at Tipping Flood
Place CIP Walls at CL3-2 at Tipping Floor
Id
7/2/2019
7/2/2019
Place QP Wats at C13-2 at llpping Floor!
Install Doors
3d
7/2/2019
7/5/2019
Install Doors 1
F/A Trim Out at Ground Floor
5d
7/2/2019
7/9/2019
F/A Trim Out at Ground Floor
CCTV Trim Out at Ground Floor
5d
7/2/2019
7/9/2019
ccry Trim Out at Ground Roar
Place Crane Pedestals
ld
7/2/2019
7/2/2019
Place Crane Pedestals!
272
TB -00-0640
Erect PEMB Columns
1Od
7/3/2019
7/17/2019
Erect PEMB Columns
273
" TB -00-1099
Install Hardware
2d
7/8/2019
7/9/2019
Install Hardware'
274
TB -00-1249
Fire Sprinkler System at Tipping Floor
20d
7/15/2019
8/9/2019
Fre Sprinkler System at Tipping Floor 1-7
275
276
TB -00-1349
Install Hose Reel Assemblies at Ground Floor
3d
7/17/2019
7/19/2019
Instal Hose Reel Assemblies at Ground Floor Q
TB -00-1389
Install Truck Loading Ventilation Control Panel
2d
7/17/2019
7/18/2019
Install Truk Loading Ventilation Control Panel 8
277
278
279
280
281
! TB -00-1139
Electrical R/I at Tipping Floor
15d
7/18/2019
8/7/2019
Electrical R/I at Tipping Floor Q
Electrical Gear Installation
Plumbing Roughin at Tipping Floor
TB -00-1149
1 TB -00-1229
TB -00-0650
TB -00-0660
Electrical Gear Installation
Plumbing Roughin at Tipping Floor
15d
10d
4d
7d
7/18/2019
7/18/2019
7/18/2019
7/18/2019
8/7/2019
7/31/2019
7/23/2019
7/26/2019
Erect PEMB Girts
Erect PEMB Girts 0
Erect PEMB Puriins❑
Erect PEMB Purlins
282
TB -00-1329
Install Eye Wash Stations at Tipping Floor
5d
7/25/2019
7/31/2019
Install Eye Wash Stations at Tipping Floor 0
283
284
285
286
! TB -00-0849
TB -00-0889
TB -00-0929
TB -00-0670
Install Wall Plating at CIP Walls Along Row A at Tipping Floor
Install Wall Plating at CIP Walls Along Row F at Tipping Floor
Install Wall Plating at CIP Walls at CL3-2 at Tipping Floor
Install PEMB Roof Panels
10d
10d
10d
10d
7/29/2019
7/29/2019
8/9/2019
8/9/2019
Install Wall Plating at CIP Walk Along Row A at lipping Floor 0
Install Wall Plating at QP Walk Along Row F at Tipping Floor D
7/29/2019
7/29/2019
8/9/2019
8/9/2019
Install Wall Plating at CIP Walk at CL3-2 at Tipping Floor ❑
Instal PEMB Roof Panels 0
287
TB -00-0830
Install Knuckle Boom Cranes
10d
7/31/2019
8/13/2019
Install Knuckle Boom Cranes D
288
289
290
TB -00-1339
TB -00-0740
TB -00-0750
Install Hose Reel Assemblies at Tipping Floor
Install Reclaimed Water Line at Tipping Floor
5d
5d
8/1/2019
8/1/2019
8/7/2019
8/7/2019
Install Hose Reel Assemblies at Tipping Floor Q
Install Reclaimed Water Line at Tipping Floor Q
Install Potable Water Line at Tipping Floor Q
Install Potable Water Line at Tipping Floor
5d
8/1/2019
8/7/2019
291
292
TB -00-1209
TB -00-1279
CCTV Roughin at Tipping Floor
5d
8/5/2019
8/9/2019
CCN Roughin at Tipping Floor Q
Install Exhaust Fans at Ground Floor
5d
8/5/2019
8/9/2019
Instal Exhaust Fans at Ground Floor 0
293
TB -00-1299
Electrical Trim Out Ground Floor
5d
8/8/2019
8/14/2019
Electrical Trim Out Ground Floor
.J�C
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/13/2017
Page 10 of 16
: Clearwater
31
Line
Uni ue Task ID
9
Name
Duration
Start
Finish
2017 2018 2019
M. A M. J J, A S O, N D,] F. M A. M ] ] A S. 0 N, D. 1, F M A M. J. J A. S O. N
,13 .3 ,24 ,15 ,5 .26 ,17 .7 ,28 ,38 .9 ,30 .20 .11 .I .22 .32 .5 .26 .16 .7 .28 .38 .9 .30 .20 .10 .t 122 ,32 ,3 ,24 ,14 .9 ,25 .18 .8 .29 .20 .30 ,3 .22 .32 ,2 .23 .34 .9
,22 .26 ,30 .34 .38 ,42 ,46 .50 .54 ,58 .62 .66 .70 74 .78 .82 .86 .90 .94 .98 102 ,106 .110 .114 ,118 .122 .126 ,130 .134 .138 ,142 ,146 ,150 .154 ,
294
295
TB -00-1309
TB -00-1379
Electrical Trim Out Tipping Floor
7d
8/8/2019
8/16/2019
Electrical Trim Out Tipping Floor ❑
Install Tipping Floor Ventilation Control Panel
2d
8/8/2019
8/9/2019
Install Tgping Floor Ventilation Control Panel V
296
297
298
299
300
301
302
303
304
305
TB -00-0789
TB -00-1059
TB -00-1159
TB -00-1169
TB -00-1189
TB -00-1210
11-00-1259
Place 2" Tipping Floor Topping
2d
8/12/2019
8/13/2019
Place 2" Tipping Floor Topping Q
Install Controller Booth Glazing Panel Assembly
5d
8/12/2019
8/16/2019
Install Controller Booth Glazing Panel Assembly Q
Install Light Fixtures Ground Floor
10d
8/12/2019
8/23/2019
Install Llght Fixtures Ground Floor ❑
Install Light Fixtures Tipping Floor
7d
8/12/2019
8/20/2019
Install Light Fixtures Tipping Floor 0
F/ A Roughin at Tipping Floor
5d
8/12/2019
8/16/2019
F/A Roughen at Tipping Floor 0
CCTV Trim Out at Tipping Floor
5d
8/12/2019
8/16/2019
CCN Trim Out at -Duping Floor 0
Install Exhaust Fans at Tipping Floor
4d
8/12/2019
8/15/2019
Install Exhaust Fans at Tipping Floor Q
-IB-00-1269
1B-00-1289
TB -00-0680
Install Supply Fans at Tipping Floor
4d
8/12/2019
8/15/2019
Install Supply Fans at Tipping Floor 0
Install Supply Fans at Ground Floor
5d
8/12/2019
8/16/2019
Install Supply Fans at Ground Floor 0
Install PEMB Wall Panels
14d
8/12/2019
8/29/2019
Install PEMB Wall Panels0
306
307
308
TB -00-0969
TB -00-1181
TB -00-1399
Install Controller Booth Stair and Rail Assembly
5d
8/19/2019
8/23/2019
8/23/2019
Install Controller Booth Stair and Rail Assembly
F/A Trim Out at Tipping Floor
5d
8/19/2019
F/A Trim Out at Tipping Floor 10
Install AHU-01 at Controller Booth
2d
8/19/2019
8/20/2019
Install AHU-01 at Controller Booth 0
309
TB -00-1409
Install HVAC Duct at Controller Booth
ld
8/21/2019
8/21/2019
Install HVAC Duct at Controller Booed
310
TB -00-1419
Install HVAC Ceiling Grilles at Controller Booth
ld
8/22/2019
8/22/2019
Install HVAC Ceiling Grilles at Controller Booth
311
TB -00-1049
Install Overhead Door Units
5d
8/23/2019
8/29/2019
Install Overhead Door Units 10
312
TB -00-1069
Install Controller Booth Gate and Railing Assembly
3d
8/26/2019
8/28/2019
Install Controller Booth Gate and Railing Assembly 0
313
314
315
316
317
318
319
TB -00-0979
TB -00-0999
TB -00-1009
TB -00-1019
TB -00-1029
TB -00-1039
TB -00-1319
Install Translucent Wall Panels South Side
Install Glass Block Panels South Side
Install Exterior Louvers South Side
Install Exterior Louvers North Side
Install Exterior Louvers East Side
Install Exterior Louvers West Side
Install Booster Pump Station at Tipping Floor
3d
3d
3d
3d
8/27/2019
8/27/2019
8/29/2019
8/29/2019
Install Translucent Wall Panels South Side 0
Install Glass Block Panels South Side 0
Install Exterior Louvers South Side 0
Install Exterior Louvers North Side 0
Install Exterior Louvers East Side 0
Install Exterior Louvers West Sae 1
Install Booster Pump Station at Tipping Floor
8/27/2019
8/27/2019
8/29/2019
8/29/2019
8/29/2019
8/29/2019
8/29/2019
3d
3d
3d
8/27/2019
8/27/2019
8/27/2019
320
321
322
323
TB -00-0939
TB -00-0949
Install Aluminum Walkway System East Side
4d
8/30/2019
9/5/2019
Install Aluminum Walkway System East Side Q
Install Aluminum Walkway System West Side
4d
8/30/2019
8/30/2019
9/5/2019
Install Aluminum Walkway System West Side 0
TB -00-0959
TB -00-0989
Install Aluminum Walkway System South Side
4d
9/5/2019
Install Aluminum Walkway System South Side ❑
Install Translucent Wall Panels North Side
3d
8/30/2019
9/4/2019
Install Translucent Wall Panels North Side 0
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
a
° i.iearsvater
1-
0
Run Date: 10/13/2017
Page n of 16
Line Unique Task ID
Name
Duration
Start
Flnish
2017
2018
2019
M, A M, 3 J, A 5 0 N D, J F, M A, M
J, J A S, O N, D, J, F
M A M J, 3 A, 5 0, N
,13 ,3 ,24 ,15 ,5 ,26 ,17 ,7 ,28 ,18 ,9 ,30 ,20 ,11 ,1 ,22 ,12 5 ,26 ,16 ,7 ,28
,18 ,9 ,30 ,20 ,10 ,1 .21 ,12 ,3 ,24 ,14 ,4 ,25
,18 ,9 ,29 ,20 ,10 ,1 ,22 ,11 ,2 ,23 ,14 ,4
,22 ,26 ,30 ,34 ,38 42 -46 ,50 ,54 ,58 ,62 ;66 ,70 ,74 ,78 ,82
,86 ,90 ,94 ,98 ,102 ,106 ,110 ,114 ,118 ,122
,126 ,130 ,134 ,138 442 ,146 ,150 ,154 ,
324
TB -00-0620
Systems Testing
14d
8/30/2019
9/19/2019
Systems Testng-
325
TB -00-0630
Final Inspections
7d
9/20/2019
9/30/2019
Rnal Inspections.
326
TB -00-0631
Completion of Transfer Station
ld
10/1/2019
10/1/2019
Layout Foundations
Completion of Transfer Station'
327
Scale Building,
SB -00-0100
Layout Foundations
2d
11/12/2018
11/13/2018
a_
328
SB -00-0200
Excavate Foundations
3d
11/14/201811/16/2018
Excavate Foundations!'
329
S13-00-0210
Form Foundations
2d
11/19/201811/20/2018
Foran Foundations
330
SB -00-0211
Reinforce Concrete Foundations
2d
11/21/2018
11/23/2018
Reinforce Concrete Foundations
331
SB -00-0220
Place Concrete Foundations
ld
11/26/201811/26/2018
Place Concrete Foundation)
332
93-00-0230
Prep Subgrade for SOG
2d
11/27/2018
11/28/2018
Prep Subgrade for 50G 1
333
334
335
SB -00-0250
SB -00-0730
SB -00-0740
FormSOG
2d
11/29/2018
11/30/2018
Form SOGI
U/G Electrical Roughin
5d
11/29/2018
12/5/2018
U/G Elecslcal Roughs 1
U/G Plumbing Roughin
5d
11/29/2018
12/5/2018
U/G plumbing Roughin 1
336
SB -00-0240
Treat Spray SOG
ld
12/3/2018
12/3/2018
Treat Spray 5001
337
SB -00-0260
Reinforce SOG
2d
12/4/2018
12/5/2018
Reinforce 5001
338
SB -00-0270
Place SOG
ld
12/6/2018
12/6/2018
Place 5061
339
SB -00-0692
Install Door Frames
ld
12/7/2018
12/7/2018
Install Door Frames 1
340
SB -00-0280
1st Lift - Set CMU
2d
12/10/2018
12/11/2018
lst uft - set CMU I
341
SB -00-0290
1st Lift - Reinforce CMU
ld
12/12/2018
12/12/2018
1st urt - Reinforce CMU 1
342
SB -00-0300
1st Lift - Fill Cell CMU
ld
12/13/2018
12/13/2018
1st LIR - Fill Cell CMU 1
343
SB -00-0310
2nd Lift - Set CMU
2d
12/14/2018
12/17/2018
2nd Lift - Set CMU 1
344
93-00-0320
2nd Lift - Reinforce CMU
ld
12/18/2018
12/18/2018
2nd Lift - Reinforce CMU 1
345
5B-00-0330
2nd Lift - Fill Cell CMU
ld
12/19/2018
12/19/2018
2nd Lift - Fill Cell CMU 1
346
5B-00-0340
3rd Lift - Set CMU
2d
12/20/2018
12/21/2018
3rd Lift - Set CMU 1
347
SB -00-0350
3rd Lift - Reinforce CMU
ld
12/24/2018
12/24/2018
3rd Lit - Reinforce CMU 1
348
S13-00-0360
3rd Lift - Fill Cell CMU
ld
12/26/2018
12/26/2018
3rd LIR - Fill Cell CMU 1
349
SB -00-0370
Final Lift - Set CMU
2d
12/27/2018
12/28/2018
Final Lift - Set CMU 1
350
S13-00-0380
Final Lift - Reinforce CMU
ld
12/31/2018
12/31/2018
Final Lift - Reinforce CMU 1
351
SB -00-0390
Final Lift - Fill Cell CbN
ld
1/2/2019
1/2/2019
Final Lift - Fill Cell CMU 1
352
SB -00-0400
Install Bar Joists
2d
1/3/2019
1/4/2019
Install Bar 301501
r
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
u.
r
°learwater
U
Run Date: 10/13/2017
Page 12of16
Line Unique Task ID
4
blame
Duration
Start
Finish
2017 2018 2019
M, A M 1 J 3 1 A S 0 N D, J F, M A, M J J A 1 S, 0 N, D J 1 F M 1 A M 1 J 1 J A 1 5 0 ,N
,13 13 124 115 ,5 126 117 17 128 138 ,9 130 120 111,i1 152 132 ,S 126 106 17 158 118 19 130 ,20 110 ,9 122.112 13 154 114 14 A25 118 ,4 129 120 130 11 122 112 12 123 114 14
,22 326 130 134 138 142 ,46 ,50 154 ,58 ,62 166 170 174 78 182 186 190 194 198 102 1106 1110 ,114 ,118 ,122 1126 1130 1134 1138 1142 1146 1150 ,154 1
353 SB -00-0410
354 SB -00-0694
Install Roof Decking
Install Metal Framing
2d
4d
1/7/2019
1/7/2019
1/8/2019
1/10/2019
Install Roof Decking
Install Metal Framing)
355 SB -00-0790
356 SB -00-0420
357 SB -00-0691
Install Truck Weight Scales
20d
1/9/2019
2/5/2019
Install Truds Weight Scales 11■
Install Roofing Insulation
2d
1/9/2019
1/10/2019
Install Rooflng Insulation 1
Install Windows
3d
1/9/2019
1/11/2019
Instalwlndows'
358 SB -00-0690
Install Roofing Membrane System
3d
1/11/2019
1/15/2019
Install Roofing Membrane System 1
359 SB -00-0700
Above Slab Electrical Roughin
5d
1/11/2019
1/17/2019
Above Slab Electrical Roughen
360 SB -00-0701
361 SB -00-0702
Above Slab Plumbing Roughin
5d
1/11/2019
1/17/2019
Above Slab Plumbing RoughinI
Above Slab Mechanical Roughin
3d
1/11/2019
1/15/2019
Above Slab Mechanical Roughing
362 SB -00-0724
Install Stucco System
10d
1/14/2019
1/25/2019
Install Stucco System II
363 SB -00-0706
Install Rooftop RTAC-SH Unit
2d
1/16/2019
1/17/2019
Install Rooftop RTAC-SHUnit 1
364 SB -00-0695
Install Wall Insulation
2d
1/18/2019
1/21/2019
Install Wan Insulation 1
365 -B-00-0703
Install HVAC Duct
3d
1/18/2019
1/22/2019
Instal HVAC Duct 1
366 tiB-00-0705
Install HVAC Controls
2d
1/18/2019
1/21/2019
Install HVAC Controls'
3t7 tiB-00-0707
368 ti3-00-0711
369 SB -00-0712
370 SB -00-0713
Pull Electrical Wire
Install Fire Alarm System
Install CCTV System
Install Security System
5d
4d
4d
4d
1/18/2019
1/24/2019
Pull Electrical Wive 1
Install Fire Alan System 1
Install CCTV System)
Install Security System 1
1/18/2019
1/23/2019
1/18/2019
1/18/2019
1/23/2019
1/23/2019
371 SB -00-0696
Hang Gyp Board - Walls
3d
1/22/2019
1/24/2019
Hang Gyp Board - Was!
372 SB -00-0697
Finish Gyp Board - Walls
3d
1/25/2019
1/29/2019
Finish Gyp Board - Walls 1
373 SB -00-0716
Exterior Painting
5d
1/28/2019
2/1/2019
exterior Paintlg II
374 SB -00-0698
375 93-00-0721
Install ACT Track
2d
3d
1/30/2019
1/31/2019
Instars ACT Trade'
Install Ceramic Tile Wall System 1
Install Ceramic Tile Wall System
1/30/2019
2/1/2019
376 SB -00-0699
377 SB -00-0704
378 SB -00-0708
Install ACT Tiles
Install Grilles and Diffusers
Install Light Fixture
ld
2d
3d
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/4/2019
2/5/2019
Instars ACT Tiles
Install Grilles and Diffusers)
Install Light Fixture 1
379 SB -00-0710
380 SB -00-0717
Install Plumbing Fixtures
2d
2/4/2019
2/5/2019
Install Plumbing Fixtures'
Install Roof Access Ladder
ld
2/4/2019
2/4/2019
Install Roof Access Ladders
381 SB -00-0718
Install Aluminum Gutter & Downspout System
4d
2/4/2019
2/7/2019
Install Aluminum Gutter & Downspout System,
382 SB -00-0723
Install HVAC Louvers
2d
2/4/2019
2/5/2019
install HvAC Louvers)
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/13/2017
Page 13 of 16
Uearwater
Line Unique Task ID
9
Name
Duration
Start
Fini•sh
2017 2018
2019
M, A M, 3 3, A S 0, N D, 3 F, 14 A, Ma3 3 A S i 0 8, 0 3, F
M, A M, 3, 3 A, s
O, N
,13 ,3 ,24 ,15 ,5 ,26 ,57 17 ,28 158 19 ,30 ,20 ,11 ,1 ,22 ,12 ,5 126 ,56 ,7 ,28 ,18 ,9 ,30 ,20 ,10 ,1 ,22 ,12 ,3 ,24 ,14 ,4 ,25
118 ,g 129 120 110 11 132 ,12 i2
123 ,14 14
,22 ,26 ,30 ,34 ,38 ,42 ,46 ,50 ,54 ,58 ,62 ,66 ,70 ,74 ,78 ,82 ,86 ,90 ,94 ,98 ,102 ,106 ,110 ,114 ,118 ,122
,126 ,130 ,134 ,138 ,142 ,146 ,150
,154 ,
383
SB -00-0715
Interior Painting
5d
2/5/2019
2/11/2019
Interior Painting 1
384
385
SB -00-0709
SB -00-0722
Electrical Trim Out
Install T&B Accessoreis
3d
ld
2/6/2019
2/6/2019
2/8/2019
2/6/2019
Electrical Trim Out 1
Install T&8 Accessorels 1
386
387
388
SB -00-0693
SB -00-0714
...............
93-00-0719
Install Doors Sr Hardware
1d
2/12/2019
2/12/2019
Install Doors & Hardware 1
Install Hot Water Heaters EWH-1
2d
2/12/2019
2/13/2019
Instal Hot Water Heaters EWH-111
Install Casework
4d
2/12/2019
2/15/2019
Install Casework 1
389
5B-00-1161
Final Inspections at Scale House
5d
2/14/2019
2/20/2019
Final Inspections at Scale House 1
390
SB -00-0720
Install Ceramic Tile Flooring System
3d
2/18/2019
2/20/2019
Install Ceramic Tile Flooring System 1
391
392
SB -00-0733
Administra
AD -00-0100
Completion of Scale House
ion Building
Layout Foundations
ld
2d
2/21/2019
11/12/2018
2/21/2019
11/13/2018
Completion of Scale House 1
Layout Foundations
393
AD -00-0110
Excavate Foundations
6d
11/14/2018
11/21/2018
Excavate Foundations®
394
AD -00-0120
Form Foundations
4d
11/23/2018
11/28/2018
Form Foundations 1
395
AD -00-0130
Reinforce Concrete Foundations
4d
11/29/2018
12/4/2018
Reinforce Concrete Foundations'
396
AD -00-0140
Place Concrete Foundations
ld
12/5/2018
12/5/2018
Place Concrete Foundations)
397
AD -00-0150
Prep Subgrade for SOG
4d
12/6/2018
12/11/2018
Prep Subgrade for 50G 1
398
399
400
AD -00-0170
AD -00-0460
AD -00-0480
Form SOG
U/G Electrical Roughin
U/G Plumbing Roughin
4d
10d
10d
12/12/201812/17/2018
12/12/2018
12/12/2018
Fornr SOG1
12/26/2018
12/26/2018
U/G Electrical Roughin
U/G Plumbing Roughin
401
AD -00-0160
Treat Spray SOG
ld
12/18/201812/18/2018
Treat Spray SOG
402
AD -00-0180
Reinforce SOG
4d
12/19/2018
12/24/2018
Reinforce 5061
403
AD -00-0190
Place SOG
ld
12/27/201812/27/2018
Place 50G1
404
AD -00-0370
Install Door Frames
2d
12/28/2018
12/31/2018
Install Door Frames
405
AD -00-0200
1st Lift - Set CMU
4d
1/2/2019
1/7/2019
1st Lift - Set CMU 1
406
AD -00-0210
1st Lift - Reinforce CMU
2d
1/8/2019
1/9/2019
1st Lift - Reinforce CMU 1
407
AD -00-0220
1st Lift - Fill Cell CMU
ld
1/10/2019
1/10/2019
1st Lift- Fitl Celt CMU1
408
AD -00-0230
2nd Lift - Set CMU
4d
1/11/2019
1/16/2019
2nd Lift - Set CMU 1
409
AD -00-0240
2nd Lift - Reinforce CMU
2d
1/17/2019
1/18/2019
2nd Lift - Reinforce CMU 1
410
AD -00-0250
2nd Lift - Fill Cell CMU
ld
1/21/2019
1/21/2019
2nd Lift- Fill Cel CMU1
411
AD -00-0260
3rd Lift - Set CMU
4d
1/22/2019
1/25/2019
3rd Lift - Set CMU I
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/13/ 2017
Page 14 of 16
Ckarwater
35
Line Unique Task ID
9
Name
Duration
Start
F. . h
2017 2018 2019
M, A M, J J, A S O N D, 3 FMA, M 3 3 AS, O N, D J, F M A M J, 3 A, S O, N
113 13 ,24 ,15 ,5 ,26 117 17 ,28 ,18 ,9 ,30 ,20 ,11 4 ,22 42.,5 ,26 46 ,7 ,28 48 ,9 ,30 ,20 40 ,1 R2 ,12 ,3 ,24 ,14 ,4 ,25 ,18 ,8 ,29 120 ,10 ,1 120 110 12 123 ,24 ,9
,22 ,26 ,30 ,34 ,38 ,42 ,46 ,50 ,54 ,58 ,62 ,66 70 74 ,78 82 86 90 ,94 ,98 402 406 ,110 414 418 ,122 426 430 ,134 4.38 4.42 446 450 454 ,
412 AD -00-0270
3rd Lift - Reinforce CMU
2d
1/28/2019
1/29/2019
3rd Lift - Reinforce CMU l
413 AD -00-0280
3rd Lift - Fill Cell CMU
ld
1/30/2019
1/30/2019
3rd Lift - Fill Cell CMU 1
414 AD -00-0290
Final Lift - Set CMU
4d
1/31/2019
2/5/2019
Final Lift - Set CMU 1
415 AD -00-0300
Final Lift - Reinforce CMU
2d
2/6/2019
2/7/2019
Final Lift- Reinforce CMU1
416 AD -00-0310
Final Lift - Fill Cell CMU
ld
2/8/2019
2/8/2019
Final Lift - Fill Cell CMU 1
417 AD -00-0320
Install Bar Joists
4d
2/11/2019
2/14/2019
Instal Bar Joists 1
418 AD -00-0330
419 AD -00-0390
Install Roof Decking
4d
2/15/2019
2/20/2019
Install Roof Decking 1
Install Metal Framing
8d
2/15/2019
2/26/2019
Install Metal Framing
420 AD -00-0340
Install Roofing Insulation
4d
2/21/2019
2/26/2019
Install Roofing Insulation 1
421 AD -00-0360
Install Windows
6d
2/21/2019
2/28/2019
Install Windows 1
422 AD -00-0350
423 AD -00-0450
424 AD -00-0470
425 AD -00-0490
Install Roofing Membrane System
6d
2/27/2019
3/6/2019
Install Roofing Membrane System II
Above Slab Electrical Roughin
10d
2/27/2019
3/12/2019
Above Slab Electrical Roughin
Above Slab Plumbing Roughin
10d
2/27/2019
3/12/2019
Above Slab Plumbing Roughin
Above Slab Mechanical Roughin
6d
2/V/2019
3/6/2019
Above Slab Mechanical Roughin
426 AD -00-0710
Install Stucco System
20d
3/1/2019
3/28/2019
Install Stucco System MI
427 AD -00-0530
Install Rooftop RTAC-ADM Unit
2d
3/7/2019
3/8/2019
Install Rooftop RTAC-ADM Unit 1
428 AD -00-0500
429 AD -00-0520
Install HVAC Duct
Install HVAC Controls
6d
4d
3/11/2019
3/11/2019
3/18/2019
Install HVAC Duct®
3/14/2019
Install HVAC Controls 1
430 AD -00-0400
431 AD -00-0540
432 AD -00-0580
433 AD -00-0590
434 AD -00-0600
Install Wall Insulation
4d
10d
6d
6d
6d
3/13/2019
3/18/2019
Install Wall Insulation 1
Pull Electrical Wire
3/13/2019
3/26/2019
Pun Electrical Wire
Install Fire Alarm System
Install CCTV System 1
Install Security System
Install Fire Alarm System
Install CCTV System
Install Security System
3/13/2019
3/20/2019
3/13/2019
3/13/2019
3/20/2019
3/20/2019
435 AD -00-0410
Hang Gyp Board - Walls
6d
3/19/2019
3/26/2019
Hang Gyp Board - Walk 1
436 AD -00-0420
Finish Gyp Board - Walls
6d
3/27/2019
4/3/2019
Finish Gyp Board - Walk 1
437 AD -00-0630
Exterior Painting
10d
3/29/2019
4/11/2019
Exterior Painting®
438 AD -00-0430
439 AD -00-0680
Install ACT Track
4d
6d
4/4/2019
4/9/2019
Install ACT Track
Install ceramic Tile wall System
Install Ceramic Tile Wall System
4/4/2019
4/11/2019
440 AD -00-0440
441 AD -00-0510
Install ACT Tiles
2d
4/10/2019
4/11/2019
Install ACT Tiles
Install Grilles and Diffusers
4d
4/10/2019
4/15/2019
Install Grilles and Diffusers 1
ex
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
LL
° (jlearSvater
U
Run Date: 10/13/2017
Page 15 of 16
Line
Unique Task 1D
Name
Duration
Start
Finish
2017
2018 2019
M, A M, J J, A 5 O N D, 1 F, M
A, M J J A, S, O N, 0, J, F M, A M,
J, J A, 5 O, N
,13 ,3 24 ,15 ,5 ,56 37 ,7 ,28 ,18 9 ,30 ,50 ,11 1 ,52 ,12 ,5 56
,16 ,7 ,58 18 ,9 ,30 ,50 50 11 152 ,12 ,3 ,54 ,14 ,4 ,55 18 ,@ 159 150
,10 ,1 ,52 ,12 ,2 23 ,14 11
,22 ,26 ,30 ,34 ,38 ,42 ,46 ,50 ,54 ,58 ,62 ,66 ,70 ,74
,78 ,82 ,86 ,90 ,94 ,98 ,102 ,106 ,110 ,114 ,118 ,122 ,126 ,130 ,134
442
AD -00-0550
Install Light Fixture
5d
4/10/2019
4/16/2019
Install Light FixtureI
,138 ,142 ,146 ,150 ,154
443
AD -00-0570
Install Plumbing Fixtures
4d
4/12/2019
4/17/2019
Install Pkimbing Fixtures'
444
AD -00-0640
Install Roof Access Ladder
ld
4/12/2019
4/12/2019
Install Roof Access Ladder)
445
AD -00-0650
Install Aluminum Gutter & Downspout System
7d
4/12/2019
4/22/2019
Install Aluminum Gutter & Downspout System
446
AD -00-0700
Install HVAC Louvers
2d
4/12/2019
4/15/2019
Install HVAC Louvers'
447
AD -00-0730
Install Shower Units
2d
4/12/2019
4/15/2019
Install Shower Units 1
448
AD -00-0620
Interior Painting
10d
4/16/2019
4/29/2019
Interior PaintingN
449
AD -00-0560
Electrical Trim Out
6d
4/17/2019
4/24/2019
Electrical Trim Out II
450
AD -00-0690
Install T&B Accessoreis
3d
4/18/2019
4/22/2019
Install T&B Accessoreis 1
451
AD -00-0380
Install Doors & Hardware
2d
4/30/2019
5/1/2019
Install Doors & Hardware
452
AD -00-0610
Install Hot Water Heaters EWH-1
2d
4/30/2019
5/1/2019
Install Hot Water Heaters EWH-11
453
AD -00-0660
Install Casework
5d
4/30/2019
5/6/2019
Install Casework®
454
AD -00-0721
Final Inspections at Admin Building
5d
5/2/2019
5/8/2019
Final Inspections at Admin BuildingI
455
AD -00-0670
Install Ceramic Tile Flooring System
6d
5/7/2019
5/14/2019
install Ceramic Tile Flooring System 1
456
AD -00-0720
Install Lockers
2d
5/15/2019
5/16/2019
Install Lockers'
457
AD -00-0722
Completion of Admin Building
ld
5/17/2019
5/17/2019
Completion of Admin Building 1
Fire Booster
Pump Building
458
FB -00-0310
Install Fire Booster Pump Building
20d
11/27/2018
12/24/2018
Install Fire Booster Pump Building -
Gas Generator
Building
459
GG -00-0330
Install Gas Generator Building
15d
11/5/2018
11/26/2018
Install Gas Generator Building Ela
Natural Gas
Fueling Station
460
FS -00-0320
Install Natual Gas Fuel Station
25d
11/5/2018
12/10/2018
Instal Natual Gas Fuel Station -
Potable Water
Pump Station
461
WB -00-0340
Install Potable Water Booster Pump Stations
15d
11/5/2018
11/26/2018
Install Potable water Booster Pump Stations (]
Project Closeout
_....
,Transfer
Building
--..---.--- .___
.__.�..._.._
462
PC -00-0100
Substantial Completion
ld
10/2/2019
10/2/2019
Substantial Completion)
463
PC -00-0200
Punch List
21d
10/3/2019
10/31/2019
Punch List
464
PC -00-0300
Final Completion
ld
10/31/2019
10/31/2019
Final Completion
185 / Transfer Station
City of Clearwater
Data Date: 11/2/2017
GMP Schedule Supplement
Run Date: 10/13/2017
Pale 16 of 16
: Clearwater
3/
City of Clearwater
Solid Waste Transfer Station Replacement Project
Project #15 -0007 -SW
Guaranteed Maximum Price
KO KOLAKIS
SECTION EIGHT
LIST OF DOCUMENTS
38
Item
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
1.
Permit Construction Documents by Thomas E. Cunningham
Architecture & Interior Design.
G0.00
Cover
G1.00
Drawing Index
6/30/2017
GI.01
Abbreviations and Legend
6/30/2017
G1.02
Notes
6/30/2017
G1.03
Parcel Legal Descriptions & Report of Survey
6/30/2017
G1.04
Construction Pollution Prevention Plan
6/30/2017
G1.05
Construction Pollution Prevention Plan (Coachman
Ridge Park)
6/30/2017
C1.01
Existing Overall Site Plan
6/30/2017
C1.03
Existing Project Site Demo and Tree Removal Plan
6/30/2017
C1.03A
Existing Project Site Post Demo and Tree Removal
Plan
6/30/2017
C1.04
Coachman Ridge Park Site Demolition and Tree
Removal Plan
6/30/2017
C2.01
Existing Condition Drainage Basin Map (1)
6/30/2017
C2.02
Proposed Condition Drainage Basin Map (1)
6/30/2017
C3.00
Overall Site Plan
6/30/2017
C3.01
Traffic Plan
6/30/2017
C3.02
Signing & Pavement Marking Plan
6/30/2017
C4.01
Paving, Grading and Drainage Plan (1)
6/30/2017
C4.02
Coachman Ridge Park Paving, Grading and Drainage
Plan (1)
6/30/2017
C4.03
Coachman Ridge Park Paving, Grading and Drainage
Plan (2)
6/30/2017
C4.04
Wetland Mitigation Grading and Planting Plan
6/30/2017
C4.05
Scale Area Paving, Grading and Drainage
6/30/2017
C4.11
Wetland Impact Pian
6/30/2017
C4.12
Coachman Ridge Park Wetland Impact Plan
6/30/2017
C4.51
Grading Details (1)
6/30/2017
C4.52
Grading Details (2)
6/30/2017
C4.53
Geoweb Details
6/30/2017
C5.00
Overall Preloading Plan
8/1/2015
C5.01
Temporary Leachate Collection System Plan and
Details
8/1/2015
C8.00
On -Site Utility Plan (1)
6/30/2017
C8.01
On -Site Utility Plan (2)
6/30/2017
8/30/2017
C8.02
On -Site Utility Plan (3)
6/30/2017
8/30/2017
C8.03
On -Site Utility Plan (4)
6/30/2017
8/30/2017
39
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
40
C8.04
On -Site Utility Plan (4)
6/30/2017
8/30/2017
TC1.00
Traffic Control Requirements
8/1/2015
D1.00
Miscellaneous Details (1)
6/30/2017
D1.01
Miscellaneous Details (2)
6/30/2017
D1.02
Miscellaneous Details (3)
6/30/2017
D1.03
Miscellaneous Details (4)
6/30/2017
8/30/2017
D1.04
Miscellaneous Details (5)
6/30/2017
D1.05
Miscellaneous Details (6)
6/30/2017
D1.06
Miscellaneous Details (7)
6/30/2017
D1.07
Miscellaneous Details (8)
6/30/2017
D1.08
Miscellaneous Details (9)
6/30/2017
M1.00
Scale House Plan
8/1/2015
M2.00
Scale House Pump Station Plan and Details
8/1/2015
8/30/2017
M3.00
Leachate Storage Tank Plan
8/1/2015
M3.01
Leachate Storage Tank Sections
8/1/2015
M6.00
Fueling Station Plan
6/30/2017
M7.00
Generator Plan and Section
6/30/2017
M8.01
Transfer Station Crane Plan - Operator Booth Level
8/1/2015
M8.02
Transfer Station Mechanical Room Plan and Details
8/1/2015
M8.03
Transfer Station Crane Sections
8/1/2015
M8.04
Pit Brush Assembly Details
8/1/2015
S1.00
General Structural Notes
7/14/2017
S1.01
Transfer Station Foundation Plan
7/14/2017
S1.02
Transfer Station Tipping Floor Plan
7/14/2017
S1.03
Transfer Station Sections 1 of 2
7/14/2017
S1.04
Transfer Station Sections 2 of 2
7/14/2017
S1.05
Transfer Station Details 1 of 3
7/14/2017
S1.06
Transfer Station Details 2 of 3
7/14/2017
S1.07
Transfer Station Details 3 of 3
7/14/2017
S1.08
Transfer Station Enlarged Plan and Steel Beam
Details
7/14/2017
S1.09
Transfer Station Schedules and Details
7/14/2017
S1.10
Transfer Station Elevated Platform Plans and Detail
7/14/2017
S1.11
Transfer Station Stair Plans, Sections, and Details
7/14/2017
S2.01
Scale Building - Floor Slab Plan and Roof Framing
Plan
7/14/2017
S2.02
Scale Building - Sections
7/14/2017
S2.03
Scale Building - Structural Elevations
7/14/2017
S2.04
Scale Foundations Plan, Section and Details
7/14/2017
40
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
41
S3.01
Administration Building - Floor Slab and Roof Framing
Plan
7/14/2017
S3.02
Administration Building - Sections
7/14/2017
S3.03
Administration Building - Structural Elevations
7/14/2017
S5.01
Site Retaining Wall Key Plan and Details
7/14/2017
S5.02
Box Culvert Headwalls
7/14/2017
S5.03
Building Details
7/14/2017
S5.04
Standard Masonry Details
7/14/2017
S5.05
Standard Structural Details 1 of 2
7/14/2017
S5.06
Standard Structural Details 2 of 2
7/14/2017
A1.01
Transfer Building Life Safety Plan
A1.02
Transfer Building Floor Plan
6/30/2017
A1.03
Transfer Building - Building Elevations
6/30/2017
A1.04
Transfer Building - Building Elevations
6/30/2017
A1.05
Transfer Building Control Booth
6/30/2017
A2.01
Scale Building Life Safety Plan
6/30/2017
A2.02
Scale Building Floor Plan, Roof Plan, Ceiling Plan
6/30/2017
A2.03
Scale Building - Accessibility Plan, Interior Elevations
6/30/2017
A2.04
Scale Building - Building Elevations
6/30/2017
A2.05
Scale Building - Building Sections
6/30/2017
A3.01
Administration Building Life Safety Plan & Code
Requirements
6/30/2017
A3.02
Administrations Building Floor Plan, Ceiling Plan,
Roof Plan
6/30/2017
A3.03
Administration Building Accessibility Plan
6/30/2017
A3.04
Administration Building Interior Elevations
6/30/2017
A3.05
Administrations Building Building Elevations
6/30/2017
A3.06
Administrations Building Building Sections
6/30/2017
A5.01
Wall Sections - Scale Building & Administration
Building
6/30/2017
A5.02
Architectural Wall Types & Details
6/30/2017
A5.03
Architectural Schedules
6/30/2017
A5.04
Architectural Details
6/30/2017
A5.05
Architectural Details
6/30/2017
E0.01
Abbreviations
6/30/2017
E0.02
Symbols
6/30/2017
E0.03
Electrical Site Plan
6/30/2017
E0.04
Power Riser 1
6/30/2017
E0.05
Power Riser 2
6/30/2017
E0.06
Controls
6/30/2017
E0.07
Panel Schedules 1
6/30/2017
E0.08
Panel Schedules 2
6/30/2017
41
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
42
E0.09
Conduit & Wire Risers
6/30/2017
E0.10
Communications & Fire Alarm Risers
6/3/2017
E0.11
Lighting Fixture Schedule & Details
6/3/2017
E0.12
Details
6/30/2017
E1.01
Transfer Building Lighting Plan
6/3/2017
E1.02
Transfer Building Power Plan
6/30/2017
E1.03
Transfer Building Fire Alarm & CCTV
6/30/2017
E1.04
Tunnel Lighting & Power Plan
6/30/2017
E2.01
Scale House Lighting & Power Plan
6/30/2017
E2.02
Scales
6/30/2017
E2.03
Scale House Fire Alarm -CCTV & Security Plan
6/30/2017
E3.01
Administration Building Lighting & Power Plans
6/30/2017
E3.02
Administration Building Electrical Room
6/30/2017
E3.03
Administration Bldg Fire Alarm & Security Plan
6/30/2017
E4.01
Gas Dispensing System & Booster Pumps
6/30/2017
E4.02
Leachate Storage
6/30/2017
F1.00
Transfer Station Fire Protection Site Plan
7/14/2017
F1.01
Transfer Station Tunnel Level Fire Protection Plan
7/14/2017
F1.02
Transfer Station Tipping Level Fire Protection Plan
7/14/2017
F5.01
Fire Protection Details
7/14/2017
V0.01
General
6/30/2017
V0.02
Schedules 1
6/30/2017
V0.03
Schedules 2
6/30/2017
V0.04
Details
6/30/2017
V0.05
Details
6/30/2017
V0.06
Details
6/30/2017
V1.01
Transfer Building Plan
6/30/2017
V1.02
Tunnel Plan
6/30/2017
V1.03
Operators Booth
6/30/2017
V2.01
Scale House Plan
6/30/2017
V3.01
Administration Building Plan
6/30/2017
P0.01
General
6/30/2017
P0.02
Schedules & Details
6/30/2017
P0.03
Standard Details 1
6/30/2017
P0.04
Standard Details 2
6/30/2017
P0.05
Standard Details 3
6/30/2017
P1.01
Transfer Building Plan
6/30/2017
P1.02
Tunnel Plan
6/30/2017
P1.03
Risers
6/30/2017
P2.01
Scale House Plan
6/30/2017
P2.02
Risers
6/30/2017
P3.01
Administration Building Plans
6/30/2017
42
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
43
P3.02
Risers
6/30/2017
L1.00
Code Landscape Plan
8/1/2016
L1.01
Code Landscape Plan
8/1/2016
LI.02
Code Landscape Plan
8/1/2016
L1.03
Code Landscape Plan
8/1/2015
L1.04
Code Landscape Plan
8/1/2015
L2.00
Code Irrigation Plan
8/1/2016
L2.01
Code Irrigation Plan
8/1/2016
L2.02
Code Irrigation Plan
8/1/2016
L2.03
Code Irrigation Plan
8/1/2015
2.
Contract Documents & Specifications by Thomas E. Cunningham
Architecture & Interior Design.
01005
General Requirements
8/18/2017
01015
Control of Work
8/18/2017
01030
Special Project Procedures
8/18/2017
01035
Prosecution and Progress
8/18/2017
01050
Field Engineering and Surveying
8/18/2017
01070
Abbreviations and Symbols
8/18/2017
01090
Reference Standards
8/18/2017
01152
Applications for Payment
8/18/2017
01153
Change Order Procedures
8/18/2017
01200
Meetings and Conferences
8/18/2017
01300
Submittals
8/18/2017
01310
Construction Schedules
8/18/2017
01340
Shop Drawings, Product Data, Working Drawings and
Samples
8/18/2017
01410
Testing and Testing Laboratory Services
8/18/2017
01500
Temporary Facilities
8/18/2017
01505
Mobilization
8/18/2017
01510
Temporary Utilities
8/18/2017
01530
Protection of Exisiting Facilities
8/18/2017
01540
Security
8/18/2017
01550
Access and Temporary Access
8/18/2017
01600
Material and Equipment
8/18/2017
01640
Manufacturer's Services
8/18/2017
01650
Quality Control
8/18/2017
01700
Contract Closeout
8/18/2017
01720
Project Record Documents
8/18/2017
01730
Operating and Maintenance Data
8/18/2017
01740
Warranties and Bonds
8/18/2017
02001
General Utility Notes
8/18/2017
43
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
44
02010
Temporary Erosion and Sedimentation Control
8/18/2017
02030
Demolition and Alternations
8/18/2017
02061
Gravity Sewer Pipe
8/18/2017
02120
Geoweb
8/18/2017
02200
Site Preparation
8/18/2017
02201
Site Preloading
8/18/2017
02202
Topsoil
8/18/2017
02240
Dewatering
8/18/2017
02300
Preloading Cover
8/18/2017
02315
Excavation
8/18/2017
02316
Fill and Backfill
8/18/2017
02319
Subgrade Preparation
8/18/2017
02320
Trench Backfill
8/18/2017
02361
Termite Control
8/18/2017
02485
Surface Restoration
8/18/2017
02640
Potable Water Mains
8/18/2017
02650
Valves and Appurtenances
8/18/2017
02700
Trees Landscape Materials
8/18/2017
02730
Leachate Gravity Sewer
8/18/2017
02811
Irrigation System
8/18/2017
02820
Metal Fencing Materials
8/18/2017
8/30/2017
02900
Landscaping
8/18/2017
03100
Concrete Formwork
8/18/2017
03210
Reinforcing Steel
8/18/2017
03251
Concrete Joints
8/18/2017
03300
Cast -In -Place Concrete
8/18/2017
03350
Specialty Concrete Topping
8/18/2017
03351
High -Strength Concrete
8/18/2017
03366
Chemically Stained Concrete Floor
8/18/2017
03370
Concrete Curing
8/18/2017
03600
Grout
8/18/2017
03720
Vertical OH Concrete Surface Repair Systems
8/18/2017
03722
Horizontal Concrete Surface Repair Systems
8/18/2017
03740
Concrete Repair Crack Injection
8/18/2017
04230
Reinforced Unit Masonry
8/18/2017
04270
Glass Unit Masonry
8/18/2017
05050
Welding
8/18/2017
05120
Structural Steel
8/18/2017
05210
Open Web Steel Joists
8/18/2017
05310
Steel Deck
8/18/2017
05500
Metal Fabrications and Castings
8/18/2017
05520
Handrails
8/18/2017
44
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
45
05530
Metal Grating
8/18/2017
06100
Rough Carpentry
8/18/2017
06400
Architectural Woodwork
8/18/2017
07200
Air & Moisture Barrier
8/18/2017
07210
Budding Insulation
8/18/2017
07260
Vapor Retarders
8/18/2017
07530
Membrane Roofing
8/18/2017
07620
Sheet Metal Flashing
8/18/2017
07700
Roof Specialties and Accessories
8/18/2017
07900
Joint Sealants
8/18/2017
08110
Steel Door Frames
8/18/2017
08212
Wood Doors
8/18/2017
08220
FRP Doors & Frames
8/18/2017
08330
Overhead Coiling Doors
8/18/2017
08520
Aluminum Windows
8/18/2017
08580
Glass Block Panels
8/18/2017
08710
Finish Hardware
8/18/2017
8/30/2017
08950
Translucent Panel Systems
8/18/2017
09510
Acoustical Ceilings
8/18/2017
09900
Painting and Protective Coatings
8/18/2017
10200
Louvers and Vents
8/18/2017
10500
Lockers
8/18/2017
10520
Portable Fire Extinguishers
8/18/2017
10800
Toilet Accessories
8/18/2017
11150
Knuckleboom Cranes
8/18/2017
9/27/2017
11300
Packaged Grinder Pump Station for Low Pressure
Sewer Collection System
8/18/2017
8/30/2017
13030
Prefabricated Rooms
8/18/2017
13100
Lightning Protection System
8/18/2017
13110
Truck Weigh Scale
8/18/2017
8/30/2017
13122
Pemb Transfer Building
8/18/2017
13210
Double Wall Leachate Storage Tank
8/18/2017
15100-01
PVC-DWV Pipe and Fittings
8/18/2017
15101
Plumbing Piping and Accessories
8/18/2017
15183
Refrigerant Piping
8/18/2017
15195
CNG Fueling Station
8/18/2017
15202
Process Valves and Operators
8/18/2017
15300
Fire Protection System
8/18/2017
15304
Packaged Fire Pump System
8/18/2017
15410
Plumbing Fixtures
8/18/2017
15730
Unitary AC Equipment
8/18/2017
15810
Metal Ductwork and Accessories
8/18/2017
45
Number
Clearwater Solid Waster Transfer Station Reconstruction
Issue For Permit
LIST OF DOCUMENTS
Submittal Date 08/24/17
Description
Dated
Revised
46
15830
Fans
8/18/2017
15850
Air Outlets and Inlets
8/18/2017
15900
HVAC Controls
8/18/2017
15950
HVAC Systems Testing
8/18/2017
15992
Piping Leakage Testing
8/18/2017
16010
Basic Electrical Requirements
8/18/2017
16015
Electrical Systems Analysis
8/18/2017
8/30/2017
16050
Basic Electrical Materials and Methods
8/18/2017
16060
Grounding
8/18/2017
16080
Electrical Testing
8/18/2017
16120
Conductors
8/18/2017
16130
Raceways and Boxes
8/18/2017
16216
CNG Generator Set
8/18/2017
16220
Low Voltage Motors
8/18/2017
16288
Transient Voltage Surge Surpressors
8/18/2017
16412
Automatic Transfer Switch
8/18/2017
16440
Low Voltage Motor Control
8/18/2017
16442
Panel boards
8/18/2017
16460
Low Voltage Transformers
8/18/2017
16500
Lighting
8/18/2017
16750
Solid State UPS
8/18/2017
3.
Geotechnical Issued
by Driggers Engineering Services, Inc.
01
Interim Report of the Geotechnical Investigation
9/24/2015
02
Addendum to Interim Report of the Geotechnical
Investigation
10/9/2015
03
Estimated Normal Season High Groundwater Levels;
Coachman Ridge Park Test Borings
12/8/2015
4.
Supplements
01
FL -0185 -16 -PC Supplement 01
9/1/2017
02
FL -0185 -16 -PC Supplement 02
9/19/2017
5.
Addenda
01
Addendum 01, Issued by King Engineering
Associates, Inc.
8/30/2017
02
Addendum 02, Issued by King Engineering
Associates, Inc.
9/18/2017
03
Addendum 03, Issued by King Engineering
Associates, Inc.
9/27/2017
6.
RFI's
01
'Responses to RFI's 001 thru 033
9/19/2017
46
*IR
KO KO LAKI S
202 E. Center Street
Tarpon Springs, FL 34689
(727) 942-2211 • www.jkokolakis.com
47