DRUID ROAD / ALLEN'S CREEK STORMWATER IMPROVEMENTS - 11-0044-EN - CHANGE ORDER #1Change Order 1
PROJECT:
Druid Rd/Allen's Creek Stormwater
Pipe Replacement
CONTRACTOR:
Steve's Excavating & Paving, Inc.
1741 N. Keene Road
Clearwater, FI 33755
DATE:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE:
CODE:
CODE:
September 28, 2017
11 -0044 -EN
ST112494
December 3, 2015
January 7, 2016
0315-96164-563700-539-000-0000 A
0327-96722-563800-533-000-0000 B
0327-96634-563800-535-000-0000 C
SCOPE OF CHANGE: This Change Order Accepts Revisions to the Contract
increasing and adding items to redesign Hercules from Druid Rd to Gulf to Bay and add 300 calendar days to the contract -see
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Change Order 1 -City Council 10/19/2017
NEW CONTRACT AMOUNT
CteOrkt RCrt\AUS
$2,825,423.59
$545,071.33
$ 3,370,494.92
George N. Cretekos
APPROVED AS
Mathew Smith,
ATTEST:
L.
4.,i../ .ct
Mayor
Assistant City Attorney
Rosemarie Call,
Date:
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
bOAAL-i„,,
Wiliiam B. Horne, II
City Manager
ACCEPT
B411-----111111110
Cat i ..? ago,
: Stev s Excavating & Paving, I ,c.:
Date:
Viol
Witnesses:
(SE81.4 ... c
Pttsideut
iNkRecommended By:
City of Clearwater
Roger Johnson, PE bject Manager
Michael D Quillen, PE, City Engineer
Change Order 1- Druid Rd/Allen's Creek Stormwater Pipe Replacement
ITEM
DESCRIPTION
UNIT KELY UNIT COST TOTAL COST
Code A:
Increases:
1.1 Maintenance of Traffic LS 0.18125 $ 32,000.00 $5,800.00
1.2 Mobilization LS 0.064001 $ 199,371.00 $12,760.00
2.1 Demolition LS 0.192492 $ 199,360.00 $38,375.25
3.4 Pinellas Co. Type J5 Inlet 5' x 5' Type J EA 0.113532 $ 5,875.00 $667.00
Bottom, 3.5' Dia. Riser
3.5 Pinellas Co. Type J5 Inlet 4'x4' Type J EA 0.451492 $ 4,525.00 $2,043.00
Bottom, 3.5' Dia. Riser
3.6 Pinellas Co. Type J5 Inlet 4' Dia. Type P EA 7 $ 4,525.00 $31,675.00
Bottom, 3.5' Dia. Riser
3.14 16" DIP LF 3 $ 115.00 $345.00
3.15 15" RCP LF 139 $ 67.00 $9,313.00
3.16 18" RCP LF 2 $ 72.00 $144.00
3.17 24" RCP LF 4 $ 70.00 $280.00
4.2 2.5" FDOT Type SP 12.5 Asphalt TN 508 $ 130.00 $66,040.00
4.3 8" Crushed Cone Base SY 5118.93 $ 23.00 $117,735.39
4.5 12" Stabilized Subgrade SY 3916 $ 12.50 $48,950.00
4.7 Concrete Driveway 6" Thick SF 1238 $ 6.50 $8,047.00
4.8 Concrete Walk 4" Thick SF 5447 $ 5.80 $31,592.60
4.12 FDOT Type F Curb LF 82 $ 18.30 $1,500.60
4.13 FDOT Valley Gutter Curb LF 247 $ 35.00 $8,645.00
4.14 Public Sidewalk Curb Ramps with tactile surf; EA 1 $ 1,965.00 $1,965.00
4.15 Pavement Markings & Signage LS 1.650999 $ 11,265.00 $18,598.50
5.1 Landscaping LS 0.098256 $ 12,900.00 $1,267.50
6.0 10% Stormwater Contingency LS 0.232052 $ 213,538.49 $49,551.94
Total Increases: $455,295.78
Additions:
4.16 8" Wide Retaining WaWCurb* LF 50 $ 35.00 $ 1,750.00
4.17 FDOT Type D Curb at ADA Ramps* LF 144 $ 35.00 $ 5,040.00
4.18 Traffic Loops and conduit on Hercules LS 1 $ 9,655.90 $ 9,655.90
7.1 Delay Fees LS 1 $ 73,329.65 $73,329.65
Total Additions: $ 89,775.55
Total Net Increases/Additions Code A: 5545,071.33