ADDENDUM TO AGREEMENT FOR PROFESSIONAL SERVICES (2)ADDENDUM
TO
AGREEMENT FOR PROFESSIONAL SERVICES
This ADDENDUM is made and entered into by and between the City of Clearwater, Florida
(CITY) and Woods Consulting (ENGINEER) and hereby notes that the original Exhibit "B" was in
error and the new, corrected Exhibit "B", attached to this Addendum, supersedes and replaces the
original.
Upon its execution by both parties, this Addendum, is made an integral part of the Agreement for
Professional Services entered into by both parties on July 21, 2017.
CITY OF CLEARWATER
Date: IO]I(Q/.2,017
bltialzwi 1,11044Alczc
William B. Horne, II
City Manager
ATTEST:
WOODSCONSULTING
Date:
AEilure-‘—___
Name: Terri Skapik
Title:
President
Rosemarie Call
City Clerk
APPR I VED • • FIC
I
A. Alla
Ma M. Smit
Assistant City Attorney
Page 1
EXHIBIT "B"
PROVISION OF PAYMENT
ENGINEER OF RECORD: Woods Consulting
BASIS FOR PAYMENT
The owner shall pay ENGINEER and ENGINEER agrees to accept as full compensation for its
services (as established by Work Order) compensation as computed by one of the following
methods:
Method "A" — Costs Times Multiplier Basis —
Compensation in the form of actual costs times a multiplier as determined by the following
formula:
Actual raw Salary Cost (Hourly Rate) x Multiplier + Subconsultant Cost + Other Direct Costs.
Multiplier 2 ' 2 includes fringe benefit rate, overhead, operating margin and profit and is
subject to annual review.
Subconsultant Costs are actual costs incurred times a factor of 1.00. Actual costs shall be based on
billing rates for required labor classifications.
Other Direct Costs are actual costs incurred for travel outside of Tampa Bay area, printing, copying,
long distance telephone calls, etc., times a factor of 1.00.
Method "B" — Lump Sum —
Compensation in the form of "lump sum" for all work associated with a Work Order or task and
shall be determined by mutual agreement between the ENGINEER and the City. The lump sum
amount shall be negotiated based upon the Work Order scope of services and approved by both the
City and the ENGINEER.
Hourly Rates -
The estimated hourly rates below represent 2015 costs and categories. Periodic changes are
anticipated and modification can be made annually upon City and ENGINEER review. (Note:
All rates are hourly salary)
Exhibit B Page 1
CITY OF CLEARWATER ENGINEER OF RECORD
RFQ 28-17 2017 DIRECT HOURLY RATES
ENGINEER OF RECORD: Woods Consulting
Job Classification
Minimum
Rate
($ / hour)
Typical
Maximum
Senior Engineer
100.00
100.00
150.00
Construction Manager
100.00
100.00
150.00
Senior Permitting Consultant
80.00
80.00
120.00
Project Manager/Principal
80.00
80.00
120.00
Drafter/CADD Operator
42.50
42.50
63.75
Field Technician
42.50
42.50
63.75
Administrative/Clerical
22.50
22.50
33.75
MULTIPLIER: 2.2
Exhibit B — Page 2