LONG CENTER RECREATION COMPLEX - AQUATIC CENTER RENOVATIONS - 16-0008-PR - ADMINISTRATIVE CHANGE ORDER #1Page 1 of 2 Administrative Change Order #1 PROJECT Long Center Pool Renovations CONTRACTOR: Khors Construction, Inc 12222 Anne Kenia Dr. Thonotosassa, FL 33592 Date: PROJECT NUMBER: PO REFERENCE NO.: DATE OF CONTRACT: CODE: 1 . BRIGHT AND BEAUTIFUL• BAY TO BEACn August 24, 2017 16- 0008 -PR ST113608 December 15, 2016 0315- 93278 - 563600 -575- 000 -0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT This change order increases and adds items according to field conditions -see details attached. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT Administrative Change Directive 1 thru 7 less contingency NEW CONTRACT AMOUNT APPROVED AS O ^ 1 RM: Matthe Smith, Attest: 879,139.80 30,286.12 909,425.92 Assistant City Attorney Rosemarie Call Date: term' 1317 CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA Clerk William B. Horne, II ACCEPTED BY: Khors Construction, Inc Kor' orsan ian Date: Witn s�es: (two) Project Manager By: Deuel & Associates Recommended By: City of Clearwater Project Engineer Project Manager City Manager Kevin Dunbar Parks & Recreation Director Page 2 of 2 Administrative Change Order 1 : Long Center Pool Renovations. ITEM Increase Line #1 Line #2 Line #3 Line #4 Line #5 Line #6 Line #7 C FARM �= BRIGHT ANT) BEAUTIFUL • MY TO BEACH DESCRIPTION UNIT Qty UNIT COST TOTAL COST Contingency (5% of contract) 1 $ 41,863.80 $ GPS Grading Panels from Natare I $ 12,208.93 $ Pinellas Pool Bond Pool Credit for Hydroblasting/Lane tile removal /Gutter Hydrazzo Baby Changing Room Pool Decking Resurfacion Well Point Systems LED Overhead Parking Lights for Pump Room 1 $ 10,760.00 $ 1 $ (45,000.00) $ 1 $ 27,511.68 $ 1 $ 29,614.04 $ 1 $ 34,960.43 $ 2,094.84 $ (41,863.80) 12,208.93 10,760.00 (45,000.00) 27,511.68 29,614.04 34,960.43 2,094.84 Total (Decreases): $ 30,286.12 Project: Location: Owner/GC Address: City/State: DATE: 04/12/17 Long Center Pool 1501 N. Belcher Road Clearwater, FL 33765 Project # 16- 0008 -PR Purchase Order # ST13608 City of Clearwater — Park, Planning & Project Mgr. Subcontractor: Parks and Recreation Address: 100 S. Myrtle Ave., Suite 120 City /state: Clearwater, FL 33756 We hereby agree to the change(s) or additional work specified below: Kea To purchase GPS Gracr1 Panels directly from Ware Corporation as requested. See attached Quote. Total Contingency this Directive Original Billable Contract Amount Original Contingency Amount Previously Utilized Contingency Amounts Utilized Total Remaining Contingency this directive Total billable contract Including Utilized Contingency Total Cost Per Quote $ 10,616.46 Sub -total $ 10,616.46 OH&P 15% $ 1,592.47 Date: THE ABOVE PRICES AND SPECIFICATIONS OF THIS CHANGE ORDER ARE HEREBY ACCEPTED. AU. WORK TO BE PERFORMED UNDER THE SAME TERMS AND CONDITIONS AS SPECIFIED IN THE ORIGINAL AGREEMENT UNLESS OTHERWISE SPECIFIED. wert 7%%orsinjtail, Signature (Contractor) 4/i:/i; Date 12,200.93 837,276.60 41,863.80 12,208.93 29,654.87 849,485.53 " resAltrieetesner °.^ -'tong Genterpool Reno Contingency Directive #2 .. ?% k,. =c , -?:, , , . DATE: 04/18/17 M Project: Long Center Pool Project # 16- 0008 -PR Location: 1501 N. Belcher Road Purchase Order # ST113608 Clearwater, FL 33765 Leroy Chin Subcontractor: Pinellas Pools Owner /GC: City of Clearwater— Park, Planning & Project Mgr. Address: 1234 Alternate 19 Address: Parks and Recreation City /state: Holiday. FL 34691 City/State: 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756 We hereby agree to the change(s) for additional worlservices as specified below: Its Increase to cover the cost of the construction bond for the pool subcontractor, Pinellas Pools. $ Total Cost per Quote 10.760.00 Sub-total $ OH &P 0% Total Contingency this Directive 10,760.00 $ 0.00 S Original Billable Contract Amount $ Original Contingency Amount S Previously Utilized Contingency Amounts S Utilized Contingency Including this directive 10,760.00 837,276 60 41,063.80 12,208.93 $ Total Remaining Contingency $ Total billable contract including Utilized Contingency S r', r 22.968.93 18,894.87 860245.53 Signature ( r) 1T_._ Date: THE ABOVE PRICES AND SPECIFICATIONS OF THIS CHANGE ORDER ARE HEREBY ACCEPTED. ALL WORK TO BE PERFORMED UNDER THE SAME TERMS AND CONDITIONS AS SPECIFIED IN THE ORIGINAL AGREEMENT UNLESS OTHERWISE SPECIFIED. Kori Khorsandian 4/18/17 Signature (Contractor) Date M1rXXk.x..kax: RY34?"< y, 1 ,WL...M '''''.". 7 a :r�r'3 47. i ..:.v a..,.�.i..m. .....s.nEY • r'=� DATE: !!�� ?? Rev 8 -16-17 Project: Long Center Pool Project # 16- 0008 -PR Location: 1501 N. Belcher Road Purchase Order # ST113608 Clearwater, FL 33765 Owner: Leroy Chin City of Clearwater — Park, Planning & Project Mgr. Address: Parks and Recreation City /State: 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756 We hereby agree to the change(s) or additional work specified below: Item Total Line Cost Une 2 Credit from Hydroblasting $ (41,190.00) Une 5 Credit for lane tile removal $ (1,587.00) Line 19 Credit from Gutter Hydrazzo $ (2,223.00) Total Contingency this Directive $ (46,000.00) Original Billable Contract Amount $ 837,276.00 Original Contingency Amount $ 41,863.80 Previously Utilized Contingency Amounts $ 22,968.93 Utilized Contingency Including this directive $ (22,031.07) Total Remaining Contingency $ 63,894.87 Total billable contract including Utilized Contingency $ ta Mk 815,24 .93 '.% -Wil (1B /),i) rl----- Signature (Owner) % Date: THE ABOVE PRICES AND SPECIFICATIONS OF THIS CHANGE ORDER ARE HEREBY ACCEPTED. ALL WORK TO BE PERFORMED UNDER THE SAME TERMS AND CONDITIONS AS SPECIFIED IN THE ORIGINAL AGREEMENT UNLESS OTHERWISE SPECIFIED. K ( xkorsand{an_. Signature (Contractor) Date i+f } 5 YL ^Ye' .; f 14 �YPi4 {AT 74711, 1 eb2La.1._�lis ' _5[, �c,s.' u+a.. t .�� g qpY tr3L s -r L iK ir%i .}u e � �.f..�..�<.L�... <..:_,,.8' _ u�.E� . P........x.,. .... . w . �L , �r4;PiS „ . 5 t °M � e 'I�✓',. rdJ��9 �. DATE: Rev 8-16-17 Project Long Center Pool Project # 16- 0008 -PR Location: 1501 N. Belcher Road Purchase Order # ST113608 Clearwater, FL 33765 Owner: Leroy Chin City of Clearwater — Park, Planning & Project Mgr. Address: Parks and Recreation City /State: 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756 We hereby agree to the change(s) or additional work specified below: Item Total Line Cost Baby Changing Room Cabanas Proposal dated 8 -7 -17 $ 27,511.68 Total Contingency this Directive $ 27,511.68 Original Billable Contract Amount $ 837,276.00 Original Contingency Amount $ 41,863.80 Previously Utilized Contingency Amounts $ (22,031.07) Utilized Contingency Including this directive Total Remaining Contingency Total billable contract including Utilized Contingency B g $ 5,383. $ 36,383.19 19 $ 842,756.61 -- i- Signature (Owner) THE ABOVE ACCEPTED. � AS SPECIFIED 7(or' xr ( orsan lian., PRICES ALL WORK IN THE Date: AND SPECIFICATIONS OF THIS CHANGE ORDER ARE HEREBY TO BE PERFORMED UNDER THE SAME TERMS AND CONDITIONS ORIGINAL AGREEMENT UNLESS OTHERWISE SPECIFIED. 6 /15/i 7 Signature (Contractor) Date Yi, .f£7i 'C :: *yk Yi ' i'..r :.,F�3 $. '....1. W...it. P- c_.;...!. .,7.�OCV :_z er..ve a.�iw.., a. .s..�.� +.L.dY_.i:.t_..� .L1.s i _ "hi.475 °*'h+'v. .�i. DATE: �dlsi Rev 8 -16-17 Project: Long Center Pool Project # 16- 0008 -PR Location: 1501 N. Belcher Road Purchase Order # ST113608 Clearwater, FL 33765 • e►: Leroy Chin City of Clearwater — Park, Planning & Project Mgr. Address: Parks and Recreation City /State: 100 S. Myrtle Ave., Suite 120 Clearwater, FL 33756 e hereby agree to the change(s) or additional work specified below: Item Pool Deck Resurfacing proposal dated 6 -20-17 Total $ Total Line Cost 29,614.04 Contingency this Directive Original Billable Contract Amount Original Contingency Amount Previously Utilized Contingency Amounts $ $ $ $ 837,276.00 41,863.80 5,480.61 Utilized Contingency Including this directive Total Remaining Contingency Total billable contract including Utilized Contingency $ $ $ 36,769. 6,769.15 5 872,370.65 Signature (Owner) Date: THE ABOVE PRICES AND SPECIFICATIONS OF THIS CHANGE ORDER ARE HEREBY ACCEPTED. ALL WORK TO BE PERFORMED UNDER THE SAME TERMS AND CONDITIONS ..c AS SPECIFIED IN THE ORIGINAL AGREEMENT UNLESS OTHERWISE SPECIFIED. 1Q,11 Inorsan4ia1L .,fir yip - Signature (Contractor) Date EAR\A/Ai BRIGHT AND BEAUTIFUL • SAY in BEACH Interoffice Correspondence Sheet To: William B. Horne, 11, City Manager From: Kevin Dunbar, Parks & Recreation Director CC: Alyce Benge, Purchasing Manager; Leroy Chin, Project Manager; Reynold Choo Chew Senior Accountant, Parks & Recreation. Date: August 24, 2017 RE: Administrative Change Order #1, Long Center Pool Renovations (16- 0008 -PR). RECOMMENDED ACTION: Approve Administrative Change Order #1 Khors Construction, Inc. of Thonotosassa, FL for Long Center Pool Renovations (16- 0008 -PR) increasing the contract amount by $30,286.12 for a new contract total of $909,425.92. BACKGROUND: Administrative change order #1 and added items according to field conditions. BUDGET AND PURCHASING DEPARTMENT REVIEW I recommend approval based on the administrative change order criteria: 1. Increase do not exceed 10% of the Council approved amount on a cumulative basis. 2. Change does not change the scope of the project. 3. Price increases do not require additional appropriation to the project. 4. Contract price decreases may be approved without limitation. 5. Completion date is not extended more than 60 days. ( 3. LI ) aVIC--e--- Alyce Benge C Dat'e te;14,i, 6,a16/7-