POND SEDIMENT REMOVAL AT MOCCASIN PARK - 17-0014-EN - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1 Date: May 23, 2017
PROJECT: PROJECT NUMBER:
Moccasin Lake Park - Pond Sediment Removal
PO REFERENCE: ST113971
CONTRACTOR:
Keystone Excavators, Inc.
371 Scarket Blvd
Oldsmar, F134677
17- 0014 —EN
CONTRACT DATE: April 26, 2017
CODE: 0315- 96124 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
After dewatering it was determined additional sediment required removal causing an increase in quantities - see details
attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - CM
NEW CONTRACT AMOUNT
APPROVED AS TO FORM:
Matthevi Smith,
ATTEST:
Lk/ L
Rosemarie Call,
Date:
Assistant City Attorney
ACCEPTED BY:
eystone Excavators, Inc:
77,910.00
$7,688.00 By: C t n r e2 i- Ri�s ,(SEAL) •
85,598.00 Robert C. Fornwalt - %President
Date: 'lwAe. Ls) , so l
Witnesses:
Recommended By: City of Clearwater
1 I7
CITY OF CLEARWATER, IN
PINELLAS COUNTY, FLORIDA
1
William B. Home,
B
huong Vo, Project Manager
City Manager
Michael D. Quillen, P1
City Engineer
Page 2 of 2: Administrative Change Order 1 Moccasin Park Pond Sediment Removal
ITEM DESCRIPTION JNI1 QTY UNIT COST TOTAL COST
Decrease:
12 -10 Contingency LS 1 $ 3,710.00 ($3,710.00)
Increases:
12 -04 Sediment Removal by Excavator Crew CY 1112 $ 7.00 $7,784.00
12 -05 Load fill into trucks /containers for hauling CY 1112 $ 1.25 $1,390.00
12 -06 Disposal of excavated material CY 1112 $ 2.00 $2,224.00
Totallncreasess: $11,398.00
Total Net (Decrease)/Increase: $7,688.00