GREENLEA-OTTEN NEIGHBORHOOD TRAFFIC CALMING & OTTEN ST ROADWAY & STORMWATER IMPROVEMENT PROJECT - 10-0003-EN - ADMINISTRATIVE CHANGE ORDER #2Administrative Change Order 2
PROJECT:
Greenlea -Otten Neighborhood
Traffic Calming & Otten Roadway
& Stormwater Improvements
CONTRACTOR:
David Nelson Construction Co.
3483 Alt 19
Palm Harbor, F134683
Date:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE A:
CODE B:
CODE C:
February 27, 2017
10- 0003 -EN
ST112763
April 7, 2016
April 20, 2016
0315- 92276 - 563700 -541- 000 -0000
0315- 96169 - 563700 -539- 000 -0000
0315- 92277 - 563700 -541- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Decreases, increases and adds items in accordance with field conditions - see attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Change Order 1 - City Council 10/5/2016
Administrative Change Order 2 - City Manager
NEW CONTRACT AMOUNT
Rosemarie Call,
$ 3,071,486.83
$685,440.00
$22,602.40 David Vekasi
ACCEPTED BY:
Dated
Nelson Construction Co'`
I 4r t;`
(Seal)
resbtint
Date: 3 " —17
Witnesses: (two)
Date: mil') /] ,2./ I�
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
it) AA/IA& 15 LIPA.ti;ar_
William B. Horne, II City Manager
APPROVED AS TO FO
Matthew Smith, Assistant City Attorney
Recommended By: City of Clearwater
7dA4714--
Tara Kivett,
Construction Manager
ichael D. Quillen ?E City Engineer
Page 2 of 2
Change Order 2: Greenlea Otten Neighborhood Traffic Calming & Otten Roadway
ITEM
Code C:
DESCRIPTION
Decreases:
136 Mill asphalt pavement, 1.5 -inch
138 5% Contingency
Increases:
137 1.5 " -2" asphalt pavement (Type SP)
UNIT Qty UNIT COST TOTAL COST
SY 41,842 $ 2.30 $
LS 1 $ 32,640.00 $
Total (Decreases) for Code C: $
TON 722 $ 100.00 $
Total Increases for Code C: $
Additions:
139 Mill Asphalt Pavement Greater than 1.5" Thic SY 31,700 $ 2.50 $
Total Additions for Code C: $
Total Net (Decreases) /Increases /Additions to the Contract: $
(96,236.60)
(32,640.00)
(128,876.60)
72,229.00
72,229.00
79,250.00
79,250.00
22,602.40