Loading...
2013-14 SANITARY SEWER AND MANHOLE REHABILITATION - 14-0025-UT - CHANGE ORDER #1CHANGE ORDER 1 PROJECT: 2013 -14 Sanitary Sewer and Manhole Rehabilitation - Sanitary Sewer Emergency Repair CONTRACTOR: Rowland Incorporated 6855- 102nd Avenue North Pinellas Park, Fl 33782 DATE: PROJECT NUMBER: PO REFERENCE: COUNCIL AWARD: DATE OF CONTRACT: October 15, 2016 14- 0025 -UT ST111380 February 5, 2015 February 27, 2015 CODE A: 0315- 96665 - 563800 -535- 000 -0000 CODE B: 0315- 96664 - 563800- 535- 000 -0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT to increase the funding with all unit prices and conditions remaining the same to cover emergency work within the City Water Reclaimation Facilities only through 1 /31/2018 -see attached for details. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT Change Order 1 -City Council- 10/31/2016 NEW CONTRACT AMOUNT APPRO Matth• Smith $1,000,000.00 $ 750,000.00 $ 1,750,000.00 ACCEPTED BY: Rowland Incorporated By: 'Ken Rowland, lGwiN / Date: /o/ 3/6 • . P d t,, . • 1 Gteoftt r1crC \trvs George N Cretekos, ATTEST: 4 Rosemarie Call, Date: CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA Assistant City Attorney Mayor Recommended By: City of Clearwater Lan -Anh Ngu , - Project Manager r City Manager Michael D Quillen, PE, City Engineer Page 2 of 3 RE: Change Order 1 2013 -14 Sanitary Sewer and Manhole Rehabilitation Sanitary Sewer Emergency Repair ITEM Code B: Increases: DESCRIPTION UNIT QTY UNIT COST TOTAL COST C. SEWER PIPE, FORCE MAIN, AND MANHOLE EMERGENCY REPAIR 1 Mobilization LS 5 $ 225.00 $ 1,125.00 2 Traffic Control (per day) PD 60 $ 45.00 $ 2,700.00 3 Labor Hour Foreman - regular time PH 2000 $ 66.00 $ 132,000.00 Foreman - overtime PH 700 $ 76.00 $ 53,200.00 Operator - regular time PH 1000 $ 53.00 $ 53,000.00 Operator - overtime PH 500 $ 63.00 $ 31,500.00 Truck Driver - regular time PH 500 $ 43.00 $ 21,500.00 Truck Driver - overtime PH 200 $ 53.00 $ 10,600.00 Pipe Layer - reguar time PH 500 $ 46.00 $ 23,000.00 Pipe Layer - overtime PH 200 $ 56.00 $ 11,200.00 Laborer - regular time PH 500 $ 41.00 $ 20,500.00 Laborer - overtime PH 200 $ 51.00 $ 10,200.00 4 Equipment Foreman P/U with hand tools PH 500 $ 28.00 $ 14,000.00 Job truck with tools PH 500 $ 36.00 $ 18,000.00 Tractor & Trailer (Transport) PH 520 $ 25.00 $ 13,000.00 Track Hole (to 100 HP) PH 500 $ 95.00 $ 47,500.00 Track Hole (101 HP to 170 HP) PH 500 $ 130.00 $ 65,000.00 Track Hole (171 HP and up) PH 200 $ 135.00 $ 27,000.00 Rubber Tired Backhoe PH 200 $ 55.00 $ 11,000.00 Wheel Loader (to 150 HP) PH 200 $ 65.00 $ 13,000.00 Wheel Loader (151 HP and up) PH 200 $ 70.00 $ 14,000.00 Track Type Tractors (to 100 HP) PH 300 $ 22.00 $ 6,600.00 Track Type Tractors (101 HP and up) PH 200 $ 27.00 $ 5,400.00 Dump Truck (Tandem Axle) PH 200 $ 72.00 $ 14,400.00 Plate Tamp PH 500 $ 6.00 $ 3,000.00 3" Trash Pump PH 500 $ 6.00 $ 3,000.00 4" Double Diaphragm PH 500 $ 9.00 $ 4,500.00 Air Compressor (125 CFM min) PH 500 $ 12.00 $ 6,000.00 Well Point Pump Per Day 200 $ 100.00 $ 20,000.00 Well Point LF 200 $ 26.00 $ 5,200.00 4" Jet Pump Per Day 201 $ 50.00 $ 10,050.00 Emergency Hauling up to 2500 galllons PH 200 $ 180.00 $ 36,000.00 Emergency Hauling over 2500 galllons PH 200 $ 180.00 $ 36,000.00 5 Materials Asphalt - 2" Overlay SY 1 $ 15.00 $ 15.00 3000 psi Concrete CY 1 $ 115.00 $ 115.00 Off Site Selected Fill CY 14 $ 4.00 $ 56.00 Limerock Base Material TN 1 $ 25.00 $ 25.00 #57 Washed Stone TN 118 $ 40.00 $ 4,720.00 Bahia Sod SF 1 $ 0.60 $ 0.60 City's standard manhole ring EA 1 $ 150.00 $ 150.00 City's standard manhole cover EA 1 $ 80.00 $ 80.00 Two -way Cleanouts EA 1 $ 55.00 $ 55.00 5A Sewer Pipe Replacement per linear foot 8" Diameter PVC LF 1 $ 2.75 $ 2.75 10" Diameter PVC LF 1 $ 4.50 $ 4.50 Page 3 of 3 continued: RE: Change Order 1 2013 -14 Sanitary Sewer and Manhole Rehabilitation Sanitary Sewer Emergency Repair ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST 12" Diameter PVC LF 1 $ 6.35 $ 6.35 15" Diameter PVC LF 1 $ 9.60 $ 9.60 18" Diameter PVC LF 1 $ 15.80 $ 15.80 20" Diameter PVC LF 1 $ 0.01 $ 0.01 21" Diameter PVC LF 1 $ 21.90 $ 21.90 24" Diameter PVC LF 1 $ 27.90 $ 27.90 30" Diameter PVC LF 1 $ 0.01 $ 0.01 36" Diameter PVC LF 1 $ 0.01 $ 0.01 8" Diameter DI LF 1 $ 28.90 $ 28.90 10" Diameter DI LF 1 $ 37.90 $ 37.90 12" Diameter DI LF 1 $ 44.60 $ 44.60 15" Diameter DI LF 1 $ 0.01 $ 0.01 18" Diameter DI LF 1 $ 62.40 $ 62.40 20" Diameter DI LF 1 $ 69.25 $ 69.25 21" Diameter DI LF 1 $ 0.01 $ 0.01 24" Diameter DI LF I $ 90.65 $ 90.65 30" Diameter DI LF 1 $ 101.00 $ 101.00 36" Diameter DI LF 1 $ 125.00 $ 125.00 5B Force Main Replacement per linear foot 8" Diameter PVC LF 1 $ 6.10 $ 6.10 10" Diameter PVC LF 1 $ 9.15 $ 9.15 12" Diameter PVC LF 1 $ 15.70 $ 15.70 15" Diameter PVC LF 1 $ 0.01 $ 0.01 18" Diameter PVC LF 1 $ 31.00 $ 31.00 20" Diameter PVC LF 1 $ 33.20 $ 33.20 21" Diameter PVC LF 1 $ 0.01 $ 0.01 24" Diameter PVC LF 1 $ 55.00 $ 55.00 30" Diameter PVC LF 1 $ 86.50 $ 86.50 36" Diameter PVC LF 1 $ 99.90 $ 99.90 8" Diameter DI LF 1 $ 28.90 $ 28.90 10" Diameter DI LF 1 $ 37.90 $ 37.90 12" Diameter DI LF 1 $ 44.60 $ 44.60 15" Diameter DI LF 54 $ 0.01 $ 0.54 18" Diameter DI LF 2 $ 62.40 $ 124.80 20" Diameter DI LF 1 $ 69.25 $ 69.25 21" Diameter DI LF 64 $ 0.01 $ 0.64 24" Diameter DI LF 1 $ 90.65 $ 90.65 30" Diameter DI LF 1 $ 101.00 $ 101.00 36" Diameter DI LF 1 $ 125.00 $ 125.00 Total increases Code C: S 750,000.00 Total Increases /Additions Contract: S 750,000.00