RO WTP #1 HIGH SERVICE PUMP STATION ELECTRICAL IMPROVEMENTS - 14-0024-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 &Final Date: June 3, 2016
PROJECT: PROJECT NUMBER:
RO WTP 1 High Service Pump Station
Electric Improvements PO REFERENCE:
CONTRACTOR:
B.L. Smith Electric Inc
29252 US Hwy 27
Dundee, Fl 33838 CODE:
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
decreases and increases items in accordance with field conditions - see attached.
AWARD DATE:
CONTRACT DATE:
14- 0024 -UT
ST111948
August 6, 2015
August 26, 2015
0327 - 96740 - 563800 -533- 000 -0000
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - CM -
NEW CONTRACT AMOUNT
APPROVED AS 0 FO _ /
' Ass stant City Attorney
ACCEPTED BY:
$ 258,447.20
$ (8,902.25) By:
$ 249,544.95 David W. Smith,
B.L. Smith Electric Inc
Date:
Witnesses:
Matthew Sm
ATTEST:
Rosemarie Call,
Date:
Recommended By: City of Clearwater
CITY OF CLEARWATER, IN
PINELLAS COUNTY, FLORIDA
William B. Home, II, City Manager
Michael D. Quill
Page 2 of 2
Administrative Change Order 1 &Final RO WTP 1 High Service Pump Station Electrical Improvements (14- 0024 -UT)
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST
Decreases:
7 Contingency LS 1 $ 23,495.20 $ (23,495.20)
Increases
2 Installation of Concrete and LS 0.01353 $ 86,770.00 $ 1,174.26
Above Ground Ductbank
3 Demolition of Generator & Gener LS 0.10173 $ 20,416.00 $ 2,077.00
5 Instrumentation and Controls LS 0.12043 $ 69,840.00 $ 8,410.54
6 SCADA Software LS 0.19541 $ 15,000.00 $ 2,931.15
Implementation Services
Allowance in accordance with
section 01630, 1.5, F.
Total Increases: $ 14,592.95
Total Net (Decrease)/Increase: $ (8,902.25)