RESTROOM - PRESS BOX BUILDING AT EDDIE C MOORE FIELDS 8 & 9 - 06-0028-PR-A - ADMINISTRATIVE CHANGE ORDER #1 & FINALPage 1 of 3
Administrative Change Order 1 & Final
BR[G14 I AM) BI,AI:I II UL • BAY I( BC.ACI I
Date: April 30, 2016
PROJECT PROJECT NUMBER:
Restroom/Press Box Building @ Eddie C. Moore Fields 8 & 9.
PO REFERENCE NO.:
CONTRACTOR:
Certus Builders
304 Westland Avenue
Tampa, FL 33606
DATE OF CONTRACT:
06- 0028 -PR -A
ST112152
September 10, 2015
CODE: 0315 - 93651 - 563500 -575- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order decreases, increases and adds items according to field conditions -see details attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 598,210.00
Administrative Change Order 1 CM - ($92,843.91)
NEW CONTRACT AMOUNT $ 505,366.09
APPROVED AS TO FO :
Matthew Smith,
Attest:
Rosemarie Call
Assistant City Attorney
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
ACCEPTED BY:
Certus Builders
By:
Dean Sumner
Date:
Witnesses: (two)
ecommended By: City of Clearwater
Project Manager
City Manager Kevin Dunbar Parks & Recreation Director
Page 2 of 3
Administrative Change Order 1 & Final: Restroom/Press Box Building @ Eddie C. Moore Fields 8 & 9.
f7 ANC) /WMrJ)IIJL BAY B) BrAct)
ITEM DESCRIPTION UNIT Qty UNIT COST TOTAL COST
Decreases:
$0.00
Total (Decreases): $0.00
Additions:
City of Clearwater After Hours
1 Inspection Fees LS 2 $ 106.00 $212.00
Subcontractor Overtime - #1 Cooling
2 & Heating LLC LS 30 $ 42.00 $1,260.00
Subcontractor Overtime - Painters on
3 Demand, LLC LS 31 $ 17.50 $542.50
4 Subcontractors Overtime - Rising Force LS 1 $ 1,500.00 $1,500.00
5 Trim -Tek LLC - 36" sweeps LS 6 23 1/3 $140.00
Axiom Power - Order, pick up and
install new special order 15 amp fuses
for elevator disconnect per Schindler
5 request LS 2 $ 90.00
$180.00
6 Axiom Power - 15 Amp Fuses LS 3 $ 17.65 $52.95
Axiom Power - Fuses reducer. Needed
to install 15 amp fuses into 60 amp
7 disconnect LS 3 $ 28.25
$84.75
General Conditions - Only Applied to
5 Overtime Charges (10 %). LS 0.1885 $ 376.03 $70.88
Profit 5% - Only Applied to Overtime
6 Charges (5 %). LS 0.1885 $ 188.04 $35.45
Install sata Boxes from existing data
location. Installed a chase nipple
7 between the two boxes. LS 1 $ 98.00 $98.00
Installed conduit with wire from H
8 panel to water heater location. LS 1 $534.75 $534.75
Installed wire for new circuit existing
conduit for new fire alarm bell power
9 supply. LS 1 $447.20 $447.20
Install additional 2" pvc conduit under
10 2nd floor for projection tie in. LS 1 $1,179.10 $1,179.10
11
Install conduit from 120 volt elevator
cab light box to switch on wall with
lockable cover. Pull wire and installed
switch. Remove previously requested
SO cord for cab light and installed 1/2"
metal flexible conduit. LS
1 $337.45 $337.45
Total Net (Decreases)/Increases /Additions: $6,675.03
Pages 3 of 3
Decrease for ODP's:
T -3 Construction - Concrete &
4 Masonry. L5 -1 $17,810.00 ($17,810.00)
Probuild - Rough Carpentry Materials.
6 L5 -1 $5,013.44 ($5,013.44)
7 Angle Truss - Trusses. L5 -1
$7,950.00 ($7,950.00)
12 Pinnacle Door - Doors & Hardware L5 -1 $25,359.71 ($25,359.71)
13 Largo Glass - Windows L5 -1 $8,200.00 ($8,200.00)
19 Mardale Specialties - Accessories. L5 -1 $ 12,618.87 ($12,618.87)
22 Ferguson - Plumbing L5 -1
$14,566.92 ($14,566.92)
24 Axiom Power - Electrical L5 -1 $8,000.00 ($8,000.00)
Total (Decreases): ($99,518.94)