MISSION HILLS RAW WATER MAIN - 14-0038-UT - ADMINISTRATIVE CHANGE ORDER #1 & FINAL•
Administrative Change Order 1 & Final Date: April 12, 2016
PROJECT
Mission Hills Raw Water Main
CONTRACTOR:
Castco Construction, Inc,
9001 126th Ave N
Largo, F133773
PROJECT NUMBER:
PO REFERENCE NO.:
DATE COUNCIL APPROVED:
DATE OF CONTRACT:
14- 0038 -UT
ST112073
September 17, 2015
October 30, 2015
CODE: 0327 - 96741 - 563800 -533- 000 - 0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
decreasing and increasing items according to field conditions -see details attached.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 - CM -
NEW CONTRACT AMOUNT
APPROVED S TO F
Matthe mith,
Attest:
Rosemarie Call
o
Pr:
9
Date: ,J d Si -9494"
$ 281,195.92
($36,668.90)
$244,527.02
Assistant City Attorney
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
ACCEPTED BY:
Castco Construction Inc.
B:
Israel Castro,
(Sta.') t9
President k
Date: () r,1 1 1( 2,O1
? L
Witnesses: (two)
(.12t4-44, & .. J.
Recommended By: City of Clearwater
Khan guyenl.)6‘."'
Project Manager
A. r
William B. Horne, II City Manager Michael Quillen, City Engineer
A)
Page 2 of 2
Administrative Change Order 1 & Final: Mission Hills Raw Water Main
ITEM DESCRIPTION UNIT Qty UNIT COST TOTAL COST
Decreases:
4 F &I 8" HDPE Pipe by Horizontal LF 84 $ 59.88 ($5,029.92)
Directional Drill
6 F &I 8" DI Pipe by Open Cut LF 50 $ 85.58 ($4,279.00)
7 F &I 8" HDPE Pipe by Open Cut LF 50 $ 100.06 ($5,003.00)
10 F &I 8 -inch Restrained Joints for DI Pipe EA 6 $ 190.11 ($1,140.66)
13 Root Pruning LF 83 $ 7.43 ($616.69)
17 Concrete Driveway Restoration as Directed SY 29.67 $ 62.77 ($1,862.39)
by the Owner or the Owner's Authorized
Project Representative
18 Concrete Sidewalk Restoration as Directed SY 46.89 $ 57.74 ($2,707.43)
by the Owner or the Owner's Authorized
Project Representative
19 Concrete Curb Restoration as Directed by LF 25 $ 45.16 ($1,129.00)
the Owner or the Owner's Authorized
Project Representative
20 Underdrain Restoration as Directed by the LF 50 $ 48.98 ($2,449.00)
Owner or the Owner's Authorized Project
Representative
22 Unsuitable Material Excavation Below CY 100 $ 14.69 ($1,469.00)
Grade as Directed by the Owner or the
Owner's Authorized Project Representative
23 Select Backfill Below Grade as Directed by CY 100 $ 14.69 ($1,469.00)
the Owner or the Owner's Authorized
Project Representative
24 Asphalt Overlay as Directed by the Owner SY 48.67 $ 18.37 ($894.07)
or the Owner's Authorized Project
Representative
25 Contingency LS 1 $ 25,563.27 ($25,563.27)
Total (Decreases): ($53,612.42)
Increases:
3 F &I 8" PVC Pipe by Horizontal Directional LF 2.00 129.210 258.42
5 F &I 8" PVC Pipe by Open Cut LF 100.00 53.010 5301
9 F &I 8 -inch Restrained Joints for PVC or HE EA 19.00 200.670 3812.73
11 F &I Compact DI Fittings LB 228 $ 9.17 2090.76
16 Sod Restoration as Directed by the Owner SY 433.3301887 $ 9.54 4133.97
or the Owner's Authorized Project
Representative
21 Asphalt Paving Restoration as Directed by SY 24.44 $ 55.10 $1,346.64
the Owner or the Owner's Authorized
Project Representative
Total Increases: $16,943.52
Total Net (Decreases) /Increases: