2015 SIDEWALK CONSTRUCTION PROJECT - 14-0044-EN - CHANGE ORDER #1Change Order 1
PROJECT
2015 Sidewalk Construction Project
CONTRACTOR:
Central Florida Contractors
P.O. Box 3987
Seminole, Florida 33775
Date:
PROJECT NUMBER:
PO REFERENCE NO.:
COUNCIL AWARD:
DATE OF CONTRACT:
CODE A:
CODE B:
March 8, 2016
14- 0044 -EN
ST112030
September 3, 2015
September 25, 2015
0315- 92339 - 563700 -541- 000 -0000
0315- 92277 - 563700 -541- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order approves a time extension of 120 days and increases scope of project by including Lake Shore Drive
-see details attached.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Central Florida
ORIGINAL CONTRACT AMOUNT
Change Order 1 - City Council 4 /7/2016
NEW CONTRACT AMOUNT
- Cve0 1,C. Cry, tl f
$237,644.11
$138,327.20
$375,971.31
George N. Cretekos
Rosemarie Call
Date: 4// 3/f t,
By:
George Gomes
Date: 3// //'t
ntr t ors,
:;, rti)
Nr
(Seal)��
P i ient,
Witnesses: (two)
ELLIA
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
tfruAxiut-,v, 4644,4---7-
William B. Horne, II
APPRO D AS TO&ORM:
City Manager
M a e Smith, (J Assistant City Attorney
Recommended By: City of Clearwater
Tara Kivett Construction Manager
v chae Quillen, PE,
City Engineer
Change Order 1: 2015 Sidewalk Construction Project
ITEM
Code A:
Increases:
DESCRIPTION
UNIT Qty UNIT COST TOTAL COST
1.1 Maintenance of Traffic LS 1.13333 $
1.2 Mobilization and Site Preparation LS 0.83333 $
1.7 Sod SF 5014 $
2.1 4" Thick Concrete Sidewalk SF 6040 $
(3000psi w /fiber mesh reinforcing
& wwf)
2.2 6" Thick Concrete Sidewalk (3000 SF 680 $ 4.50 $3,060.00
psi w /fiber mesh reinforcing &
wwf)
2.3 6" Thick Concrete Driveway (3000 SF 238 $ 4.50 $1,071.00
psi w /fiber mesh reinforcing)
3.4 Contingency LS 0.61543 $ 20,433.30 $12,575.20
Total Increasess for Code A: $55,173.20
6,000.00
6,000.00
0.50
4.00
$6,800.00
$5,000.00
$2,507.00
$24,160.00
Additions:
1.10 Clearing and Grubbing LS 1 $ 47,500.00 $47,500.00
1.11 Silt Fence LF 885 $ 5.00 $4,425.00
1.12 Reloacte Wooden Bollards EA 24 $ 150.00 $3,600.00
1.13 Compacted Fill CY 275 $ 25.00 $6,875.00
1.14 Gravel Fill CY 5.9 $ 60.00 $354.00
1.15 Rip Rap (6" nominal diameter) CY 4 $ 150.00 $600.00
1.16 15" RCP LF 90 $ 90.00 $8,100.00
1.17 24" Contech A2000 LF 30 $ 80.00 $2,400.00
1.18 Headwall EA 1 $ 9,000.00 $9,000.00
1.19 Getextile Fabric SF 300 $ 1.00 $300.00
Total Additions for Code A: $83,154.00
Total Increases /Additions to the Contract: $138,327.20