SECOND AMENDMENT FOR STORMWATER IMPLEMENTATION - FLOOD PROTECTION MAGNOLIA DRIVE IMPROVEMENT AREA - N445AGREEMENT NO. 13C00000056
SECOND AMENDMENT
TO AGREEMENT BETWEEN THE
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT
AND
CITY OF CLEARWATER
FOR
STORMWATER IMPLEMENTATION - FLOOD PROTECTION
MAGNOLIA DRIVE IMPROVEMENT AREA (N445)
This SECOND AMENDMENT entered into and effective this 15th day of April 2016 by and
between the SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, a public
corporation of the State of Florida, whose address is 2379 Broad Street, Brooksville, Florida
34604 -6899, hereinafter referred to as the "DISTRICT," and CITY OF CLEARWATER, a
municipal corporation of the State of Florida, whose address is 112 Osceola Avenue,
Clearwater, Florida 33756, hereinafter referred to as the "CITY."
WITNESSETH:
WHEREAS, the DISTRICT and the CITY entered into an Agreement effective October 1, 2012
(Original Agreement), as amended October 1, 2013, for modifications to stormwater inlets,
rehabilitation of pipes and installation of debris collection devices in the Magnolia Drive
Improvement Area; and
WHEREAS, the parties hereto wish to further amend the Agreement to extend the contract
period due to residents request to install brick streets, replace additional existing sanitary pipes,
and replace an existing water main.
NOW THEREFORE, in consideration of the mutual terms, covenants and conditions contained
herein, the parties hereby mutually agree to amend the Original Agreement, as amended, as
follows:
1. Paragraph 1, Project Contacts and Notices, is hereby amended to replace the CITY'S
Project Manager with Phuong Vo.
2. Paragraph 4, Completion Dates, is hereby amended to complete construction by December
31, 2018.
3. Paragraph 7, Contract Period, is hereby amended to extend the expiration date of April 15,
2016, to June 30, 2019.
4. Exhibit "A," Project Schedule, is hereby replaced in its entirety with the following schedule.
DESCRIPTION
COMMENCE
COMPLETE
Contract Engineer for Design & Permitting
03/27/2013
12/14/2015
30% Design Plans
04/04/2013
06/10/2013
60% Design Plans
06/10/2013
10/28/2013
Page 1 of 3
Acquire Permit
12/17/2013
01/22/2016
90% Design Plans
04/08/2014
04/07/2015
Final Design Plans
11/19/2015
12/14/2015
Bidding & Contract Award
01/13/2016
04/07/2016
Construction Activities
05/30/2016
12/31/2018
Final Acceptance Inspection
02/28/2019
04/30/2019
4. The terms, covenants and conditions set forth in the Original Agreement that have not been
specifically amended herein, will continue in existence, are hereby ratified, approved and
confirmed, and will remain binding upon the parties hereto.
The remainder of this page intentionally left blank.
Page 2 of 3
IN WITNESS WHEREOF, the parties hereto, or their lawful representatives, have executed
this SECOND AMENDMENT on the day and year set forth next to their signatures below.
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT
By: OU ' / ), 6-—
MaFk A. Hammond, P.E. Date
Director, Resource Management Division
CITY OF CLEARWATER
cr( ��o'
By:
George N. Cretekos, Mayor ate
By: 3
'- -------------
William Hornell, City Manager [�,ate
Apprq,red a to f
Attest:
"qq
Camilo Soto Rosemarie Call;
Assistant City Attorney City Clerk 0 'f"!- Q,
X V
El) 10''
SECOND AMENDMENT
TO AGREEMENT BETWEEN THE
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT
AND
CITY OF CLEARWATER
FOR
STORMWATER IMPLEMENTATION-FLOOD PROTECTION
MAGNOLIA DRIVE IMPROVEMENT AREA(N445)
DISTRICT APPROVAL INITIALS DATIE
LEGAL 2.5115
RISK MGMT
CONTRACTS
----------
BUREAU CHIEF
DIRECTOR
GOVERNING BOARD
Page 3 of 3