BYRAM DRIVE CHANNEL EROSION CONTROL IMPROVEMENTS - 13-0009-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final Date:
PROJECT
Byram Drive Channel Erosion
Control Improvements
CONTRACTOR:
Bio Mass Tech, Inc.
15212 SR 52
Land O'Lakes, Fl 34638
PROJECT NUMBER:
PO REFERENCE NO.:
COUNCIL AWARD:
DATE OF CONTRACT:
Code:
September 30, 2015
13- 0009 -EN
ST111481
February 5, 2015
April 10, 2015
0315- 96124 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
To decrease, increase and add items due to unforseen field conditions - details attached.
STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: Bio Mass Tech, Inc.
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 -CM-
NEW CONTRACT AMOUNT
$307,832.00
$29,038.00',' By
$336,870.00 J
r1
(gep.1) ,
Vice President
Rosemarie Call, perk
Date: l���J l5 ' = ;
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
William B. Horne, II
City Manager
APPROV D AS TO ORM:
Ma hew Smith, Assistant City Attorney
Reco ended : y: City of Clearwa er
Roger Jour, PE,
Project Manager
N
Ar1— 61.1ullie -110K
Michael D. • uillen, %, City Engineer
Page 2 of 2 Administrative Change Order 1 & Final: Byram Drive Channel Erosion Control Improvements
UNIT COST TOTAL COST
ITEM DESCRIPTION Unit (qty
Decreases:
401 12" DIP Pipe Casing LF 20 $ 100.00
501 Sod - Seashore Paspalum SF 6330 $ 2.00
600 CONTINGENCY 15% LS 1 $ 40,152.00
Total (Decreases):
Increases:
301 Geoweb Retaining Wall SF 572 $ 42.50
Total Increases:
Additions:
307 Grout Headwalls LS 1 $ 500.00
308 Gabion 12x3x3 CY 4 $ 400.00
309 Flexipve LS 1 $ 1,500.00
310 Rip -Rap TN 45 $ 127.00
503 Crepe Myrtle EA 4 $ 175.00
504 Sod - St Augustine SF 28300 $ 1.75
Total Additions:
Total Net (Decreases)/Increases/Additions to PO:
($2,000.00)
( $12,660.00)
($40,152.00)
($54,812.00)
$24,310.00
$24,310.00
$500.00
$1,600.00
$1,500.00
$5,715.00
$700.00
$49,525.00
$59,540.00
$29,038.00