Loading...
NEW AIRPLANE T-HANGARS AT CLEARWATER AIRPARK - 14-0031-AP - ADMINISTRATIVE CHANGE ORDER #2 & FINALt Administrative Change Order 2 & Final Date: September 30, 2015 PROJECT New Airplane T Hangars at Clearwater Airpark CONTRACTOR: Cathey Construction & Development 103 N 30th Street PROJECT NUMBER: 14- 0031 -AP PO REFERENCE NO.: COUNCIL AWARD: DATE OF CONTRACT: ST111422 February 19, 2015 March 12, 2015 Mexico Beach, F132456 CODE: 0315- 94882 - 563600 -542- 000 -0000 SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT I ms cnange oraer aecreases uwner.trect rurcnase Items ano retatea sates tax savings -see attacnea. STATEMENT OF CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT Admin Change Order 1 -CM- 6/4/2015 Admin Change Order 2 & Final -CM NEW CONTRACT AMOUNT $586,752.97 ($134,328.68) ($48,758.69) $403,665.60 ACCEPTED BY: Cathey Construction & Development a t r Rosemarie Call, Date: i 0 CITY OF CLEARWATER, in PINELLAS COUNTY, FLORID C LIn v William B. Horne, II l Recommended By: City of Clearwater APPROV t AS 0 FORM City Manager Matti' mith, • Assistant City Attorney 7 im Kurtz /j Project Manager Michael D. Quillen, PE, City Engineer Page 2 of 2 Administrative Change Order 2 & Final New Airplane T Hangars at Clearwater Airpark ITEM DESCRIPTION Qty Unit UNIT COST TOTAL COST Decreases: 8 FURNISH & INSTALL 4" PVC PIPE 309 LF $ 18.98 ($5.864.82) SANITARY SEWER (INCLUDING FITTINGS) 10 FURNISH & INSTALL 100 GAL 1 EA $ 2,531.00 ($2.531.00) PRECAST CONCRETE OIL/WATER SEPARATOR 15 BURIED DEBRIS AND UNSUITABLE 200 CY $ 18.98 ($3,796.00) MATERIAL EXCAVATION 16 ADDITIONAL SELECT FILL 200 CY $ 14.87 ($2,974.00) MATERIAL 18 10 %CONTINGENCY 1 LS $ 53,341.18 ($53,341.18) Total (Decreases): ($68,507.00) Increases: 4 DESIGNIPERMITTING /CONSTRUCTI 0.022514163 LS $ 308,565.32 $6,947.09 ON OF A 325.5 FOOT X 36.33 FOOT, APPROX. 11,825 SF PRE - ENGINEERED METAL, 10 BAY ENCLOSED AIRPLANE HANGAR BUILDING, INCLUDING 7 FOOT X 7 FOOT, APPROX. 49 SF WASHROOM/RESTROOM, INCLUDING LABOR,EQUIPMENT, PLANT AND MATERIALS 6 CONSTRUCT INCH 1687 SF $ 5.06 CONCRETE WALK Total Increases: Additions: 19 Taxiway Seal Coating 1.0 LS 4265.000 $ Total Additions: $ $8,536.22 $15,483.31 4,265.00 4,265.00 Total Net (Decreases)/Increases /Additions: ($48,758.69)