2014 ANNUAL STORMWATER IMPROVEMENTS - 14-0004-EN - ADMINISTRATIVE CHANGE ORDER #1Administrative Change Order 1
PROJECT
2014 Annual Stormwater Improvements
CONTRACTOR:
Keystone Excavators, Inc.
371 Scarlet Blvd.
Oldsmar, FL 34677
Date:
PROJECT NUMBER:
PO REFERENCE:
COUNCIL AWARD:
DATE OF CONTRACT:
Code:
August 4, 2015
14- 0004 -EN
ST110786
July 17, 2014
August 7, 2014
0315- 96124 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
Adjustment of line items to reflect field conditions. See attached.
STATEMENT OF CONTRACT AMOUNT ACCEPA D BY: Keystone Excavators, Inc.
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 -CM-
NEW CONTRACT AMOUNT
eluiu._ l! q2(
Rosemarie Call,
Date: is
s
$1,144,319.00
$0.00
$1,144,319.00
CITY OF CLEARWATER, •
PINELLAS COUNTY, FLO
to
William B. Horne, II
APPROVED S TO
Matthe Smith,
City Manager
Assistant City Attorney
B :
L€ ; Pez‘.- (Seal
Robert C. Fornwalt, President
r S
Date: U61,157— •?6—
Recommended By: City of Clearwater
Nabil Bawan
Michael D. Quillen, PE,
Project Manager
City Engineer
Page 2 of 2 Administrative Change Order 1: 2014 Annual Stormwater Improvements
UNIT COST TOTAL COST
ITEM DESCRIPTION Qty Unit
Decreases:
3.11 FDOT TYPE J -7T M.H. (6X7) 3 EA $ 4,180.00 ($12,540.00)
4.11 MILLING (UP TO 2 ") 64 SY $ 5.00 ($320.00)
Total (decreases): ($12,860.00)
Additions:
2.10 Demolish/Dispose of Buried 2 DAY $ 3,823.00 $7,646.00
Concrete Slab
2.12 Planting of Viburnum Trees 13 EA $ 185.00 $2,405.00
(Clubhouse Dr. S)
5.34 Storm Control Structure in Pond 1 EA $ 2,809.00 $2,809.00
Total additions: $12,860.00
Total net (decreases) /additions: $0.00