2011 SIDEWALK CONTRACT - 11-0012-EN - ADMINISTRATIVE CHANGE ORDER #6 & FINALADMINISTRATIVE CHANGE ORDER 6 & Final PROJECT: 2011 Sidewalk Contract CONTRACTOR: Central Florida Contractors, Inc. PO Box 3987 Seminole, Florida 33775 Date: PROJECT NUMBER: PO REFERENCE NO: CONTRACT AWARD: CONTRACT DATE: September 9, 2015 11- 0012 -EN ST108005 November 3, 2011 December 13, 2011 CODE: 0315- 92339 - 563700 -541- 000 -0000 A CODE: 0315- 92277 - 563700 -541- 000 -0000 B SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT '. "t, ft% i U ' _' To decrease unused, increase and add items according to field conditions - See details attached •:4:. i i. STATEMENT OF CONTRACT AMOUNT ACCEPTED BY: = - . `r , -' esi ORIGINAL CONTRACT AMOUNT $ 568 337.00 Centr . ract*rs►c ".s. i L.)' Admin CO 1 - CM - 2/15/2012 $ 56,832.00 �(��► �- 0 (T) ''�' C ) Admin CO 2 - CM - 3/20/2012 $ - By: �_ yy EAL• Admin CO 3 - CM - 4/25/2012 $ - George Go-s, i ''Pr�siueI nt' CO 4 - CC - 09/20/2012 $ 400,000.00 //j — CO 5 - CC - 11/20/2013 $ 200,000.00 Date: / Admin CO 6 - CM - (S8'.?-s ;.88 ( NEW CONTRACT AMOUNT $ 1,137,415.12 APPROVED TO F e4.6 Matthe Smith, Assistant :`r Attorney ATTEST: I4". 6l n l Rosemarie Call, City Clerk a/ ii //5 Date: ,t1.cte!Ift CITY OF CLEARWATER, in PINELLAS COUNTY, FLORIDA to iilLeLviA g.lam: William B. Horne, II City Manager Witnesses: Recommended By: City of Clearwater Eng Construction Manager Michael D Quillen, PE, City Engineer Page 2 of 3 Administrative Change Order 6 & Final - 2011 Sidewalk Contract ITEM DESCRIPTION UNIT Qyt UNIT COST TOTAL COST New Sidewalks Code A: 0315- 92339 - 563700- 541 -000 -0000 Decreases: 8 Remove Concrete Dumpster Pad EA 2 $500.00 (5;1.000.00 ) 9 Adjust Sanitary Sewer Manhole EA 2 $500.00 (S1.000.00) 10 10% Contingency LS 1 $14,008.46 (S1=1.008.46) 28 Construct New 4" Concrete Sidewalk (3000 PSI SF 2181 $2.45 (5,5.343.45 ) w/Fiber Mesh) 29 Construct New 6" Concrete Sidewalk (3000 PSI SF 1640 $3.80 ($6.232.00) w/Fiber Mesh and 6 "x6" /#10 x #10 Welded Wire Mesh) 30 Root Pruning LF 460 $3.00 0,1.380.00) 32 Preparation, installation and maintenance of EA 2 $500.00 0,1.000.00) Project Sign 33 Construct 4 ft. Wide ADA Ramp EA 12 $500.00 (S6.000.00) 34 Construct 5 ft Wide ADA Ramp EA 6 $500.00 (S3.000.00) 36 Upgrade 5 ft. wide ADA Ramp EA 24 $1,050.00 (S25.200.00; 37 Remove Concrete Dumpster Pad EA 1 $500.00 (5,500.00) 38 Adjust Sanitary Sewer Manhole EA 2 $500.00 ($1.000.00) Total (Decreases): (965.663.91) Increases: 1 Construct New 4" Concrete Sidewalk (3000 PSI SF 5697 $2.45 $13,957.65 w/Fiber Mesh Reinforcing) 2 Construct New 6" Concrete Sidewalk (3000 PSI SF 4330 $3.80 $16,454.00 w/Fiber Mesh Reinforcing and 6" x 6" /# 10 x #10 Welded Wire Mesh) 31 Install Detectable Warning Mat on Existing EA 27 $250.00 $6,750.00 Sidewalk 35 Upgrade 4 ft. wide ADA Ramp EA 2 $1,050.00 $2,100.00 Total Increases A: $39,261.65 Total Net (DecreasesYlncreases Code A: (526.402.26) Remove and Replace Sidewalks Code B: 0315- 92277 - 563700- 541- 000 -0000 Decreases: 11 Install Detectable Warning Mat on Existing EA 10 $250.00 (S2.5()).00 ) Sidewalk 18 Remove & Replace Straight Curb LF 16 $16.00 (5)256 00 ) 24 Install Gravity Wall (Maximum Height 24 LF 48 $50.00 (52__400.00 ) inches) 25 Install Straight Curb LF 67 $16.00 ( S 1 , 0 7 2 . ) 0 0 26 10 % Contingency LS 1 $96,825.54 (596.825.54 ) 27 Removal of 4" Sidewalk SY 552 $2.00 (S 1 104.00 ) 40 Install Detectable Warning Mat on Existing EA 2 $250.00 (5,500.00) Sidewalk 41 Preparation, installation and maintenance of EA 2 $500.00 ( 5;1.000.0( ) Project Sign 42 Remove & Replace 4" Concrete Sidewalk (3000 SF 4046 $3.20 15,12 947.20 ) PSI w/Fiber Mesh Reinforcing) 45 Remove & Replace Type I Curb LF 40 $16.00 (5640.00 ) 46 Remove & Replace Modified Curb LF 40 $16.00 (5640 0( ) 47 Remove & Replace Straight Curb LF 100 $16.00 (51.600.0( ) 48 Construct 4 ft. wide ADA Ramp EA 62 $1,050.00 (S6.5 I 0 )).00 ) 49 Construct 5 ft. wide ADA Ramp EA 12 $1,050.00 (512 600 00 ) 50 Sod SF 17280 $0.45 (57.776.(() 51 Adjust Sanitary Sewer Manhole EA 7 $500.00 (53.50(.0( ) 52 Root Pruning LF 1000 $3.00 (53.00(.(0 ) Page 3 of 3 Administrative Change Order 6 & Final - 2011 Sidewalk Contract ITEM DESCRIPTION 53 Install Gravity Wall (Maximum Height 24 Inches) 54 Install Straight Curb 55 Removal of 4" sidewalk 56 Grinding (across the sidewalk) 57 Clearing & Grubbing 58 6 -18" Wall 59 19 -30" Wall Increases: 13 Remove & Replace 4" Concrete Sidewalk (3000 PSI w/Fiber Mesh Reinforcing) 14 Remove & Replace 6" Concrete Sidewalk (3000 PSI w/Fiber Mesh Reinforcing) 16 Remove & Replace Type I Curb 17 Remove & Replace Modified Curb 19 Construct 5 ft. wide ADA Ramp 20 Construct 4 ft. wide ADA Ramp 21 Sod 23 Root Pruning 43 Remove & Replace 6" Concrete Sidewalk (3000 PSI w/Fiber Mesh Reinforcing) 44 Remove & Replace Valley Gutter Curb Additions: 60 Powerhorn UNIT Qty LF 10 LF 599.5 LF 200 LF 108 LS 2 LF 100 LF 100 SF 27211 SF 4010 LF 304 LF 155 EA 5 EA 11 SF 22000 LF 510 SF 3035 LF LF UNIT COST $50.00 $16.00 $2.00 $10.00 $5,007.00 $30.00 $55.00 $3.20 $3.80 $16.00 $16.00 $1,050.00 $1,050.00 $0.45 $3.00 $3.80 1585 $16.00 Total Increases Code B: 34.48 215.05 Total Net (Decreasesylncreases /Additions Code B: TOTAL COST 0,500 00) ($0.592.00) (9400.00) ($1.080.00! t$10.014.00) ($3.000.00) ($5500.00) (S243546.74) $87,075.20 $15,238.00 $4,864.00 $2,480.00 $5,250.00 $11,550.00 $9,900.00 $1,530.00 $11,533.00 $25,360.00 $174,780.20 $7,414.92 ($61.351.62) Total Increases to the Contract: (587.753.88)