CORONA AVENUE GABIONS - 14-0049-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINAL:.c
ADMINISTRATIVE CHANGE ORDER 1 & FINAL
PROJECT:
Corona Avenue Gabions
CONTRACTOR:
Keystone Excavators, Inc.
371 Scarlet Blvd
Oldsmar, Fl 34677
DATE: March 5, 2015
PROJECT NUMBER:
14- 0049 -EN
PO REFERENCE NO:
ST111228
DATE OF CONTRACT:November 20, 2014
CODE: 0315- 96124 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order decreases and increases items according to field conditions - see attached
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Admin Change Order 1 &Final - CM -
NEW CONTRACT AMOUNT
ATTEST:
,ems. i ,1 tc. ()tit
Rosemarie Call,
Date:
:.2C
$ 672,210.00
($131,093.50)
$541,116.50
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
BIISHE4
William B. Horne, II City Manager
APPROVED AS TO F
Mathew Smith, Assi. ant City Attorney
ACCEPTED BY Keystone Excavators, Inc
I
By: k > i`{�iLAL)
Robert C Fornwalt, P/c ident;
Date: .3A.5— 2 B /.r
Recommended By: City of Clearwater
Project Manager
Michael D Quillen, PE,
City Engineer
Page 2 of 2: Administrative Change Order 1 & Final: Corona Avenue Gabions
ITEM
Decreases:
1.05 Gabion Baskets
6.0 10 % Contingency
DESCRIPTION
Increases:
1.07 Fence, Replace Wood Stockade
1.08 Sod Restoration (in kind)
UNIT
CY
LS
LF
SF
QTY UNIT COST
257 $295.00
1 $61,110.00
Total (Decreases):
168 $18.00
3,800 $0.70
Total Increases:
TOTAL COST
($75,667.50)
($61,110.00)
($136,777.50)
$3,024.00
$2,660.00
$5,684.00
Total Net (Decreases)/Increases: ($131,093.50)