WOODLAWN TERRACE FLOODPLAIN STORAGE PROJECT - 11-0028-EN - ADMINISTRATIVE CHANGE ORDER #1 & FINALAdministrative Change Order 1 & Final
PROJECT
Woodlawn Terrace Floodplain Storage Project
CONTRACTOR:
All American Concrete, Inc.
8770 Somerset Drive
Largo, FL 33773
Date:
PROJECT NUMBER:
PO REFERENCE NO.:
January 30, 2015
COUNCIL AWARD:
DATE OF CONTRACT
11- 0028 -EN
ST110303
February 6, 2014
February 21, 2014
Code: 15- 96185 - 563700 -539- 000 -0000
SCOPE OF CHANGE: THIS CHANGE ORDER ACCEPTS REVISIONS TO THE CONTRACT
This change order decreases, increases and adds items according to field conditions.
STATEMENT OF CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT
Administrative Change Order 1 - CM
NEW CONTRACT AMOUNT
$855,233.60
($37,201.07)
$818,032.53
ACCEPTED BY: All American Concrete, Inc.
Je ery J. Nasse,
Date: CB2 "�� �✓
(Seal)
President
1 tu6t.
Rosemarie Call,
itnesses: (two)
Date . G-Jt (& c 7i A(
CITY OF CLEARWATER, in
PINELLAS COUNTY, FLORIDA
%v R..► -�
William B. Horne, II
APPROVED AS
City Manager
Matthew Smit
Recommended By: City of Clearwater
Tara Kivett,
//*
T
Construction Manager
Assistant City Attorney Michael D. Quillen, PE, City Engineer
Page 2 of 2 Administrative Change Order 1 & Final: Woodlawn Terrace Floodplain Storage Project
ITEN DESCRIPTION S)_ yt Unit UNIT COST TOTAL COST
Decreases:
1 Floating Turbliiy Bdiiier "' ` ; 4 LF $ 31.00 ($124.00)
4 Root Pruning.. . . . 12 LF $ 7.90 ($94.80)
8 Excavation I s- t `,. _. j 1. 589.26 CY $ 4.35 ($2,563.28)
21 Indemnification 1 LS $ 100.00 ($100.00)
22 10% Contingency 1 LS $ 75,257.60 ($75,257,60)
Alt 2 Screened Debris Hauling and 72.32 TN $ 7.00 ($506.24)
Disposal
Increases:
14 Riprap, Rubble, Ditch Lining
17 Sodding
Additions:
23 Coconut Matting
139.98
3399.98
TN $
SY $
Total (Decreases): ($78,645.92)
130.00
2.55
Total Increases:
$18,197.40
$8,669.95
$26,867.35
1 LS $ 14,577.50 $14,577.50
Total Additions: $14,577.50
Total (Decreases)/Increases /Additions: ($37,20L07)